From: (b) (6)

To: (b) (6)


Cc: (b) (6)
Subject: Re: Vf300 battle rhythm/calendar
Date: Tuesday, February 26, 2008 6:17:31 PM

Ok, thanks. That's good enough to give a head count for the hotel block.

(b) (6)
Business Manager - Operations
SBI, Tactical Infrastructure Program
(b) (6)

----- Original Message -----


From: (b) (6)
To: (b) (6)
Cc: (b) (6)
Sent: Tue Feb 26 17:58:07 2008
Subject: RE: Vf300 battle rhythm/calendar

(b)
(6)
Each sector that is involved in VF-300 will be sending a TI coordinator. From OBP,(b) (6) and I will be
attending. I’m not too sure about (b) (6)

(b) (6)

Assistant Chief

Office of Border Patrol

Tactical Infrastructure Branch

(b) (6)

________________________________

From: (b) (6)


Sent: Tuesday, February 26, 2008 5:32 PM
To: (b) (6)
Cc: (b) (6)
Subject: RE: Vf300 battle rhythm/calendar

Ok, thanks. (b) (6) – let me know who you would anticipate attending this meeting from OBP, so
we can get a head count for hotel block purposes.
Thx

________________________________

From: (b) (6)


Sent: Tuesday, February 26, 2008 5:19 PM
To: (b) (6)
Cc: (b) (6)
Subject: RE: Vf300 battle rhythm/calendar

I believe (b) (6) are our reps for VF300. I haven’t confirmed with (b) hough.
(6)

________________________________

From: (b) (6)


Sent: Tuesday, February 26, 2008 5:03 PM
To: (b) (6)
Cc: (b) (6)
Subject: RE: Vf300 battle rhythm/calendar

Sorry about that…… Yes, this a VF300 monthly meeting in El Paso on March 19th. Was originally
scheduled for March 18 through March 19.

(b) (6)

Business Manager, Operations and Reporting

SBI - Tactical Infrastructure Program (PF225, VF300)

U.S. Customs and Border Protection

(b) (6)

(b) (6) >


*** PLEASE NOTE NEW EMAIL ADDRESS ****

CONFIDENTIALITY NOTICE: The information contained in this electronic mail and its attachments are
privileged and confidential information and are intended for the use of the individual(s) or entity named
above and those who have been specifically authorized to receive it. If you are not the intended
recipient, you are hereby notified that any use, copying or distribution of this communication is strictly
prohibited.

________________________________

From: (b) (6)


Sent: Tuesday, February 26, 2008 4:50 PM
To: (b) (6)
Cc: (b) (6)
Subject: RE: Vf300 battle rhythm/calendar

What are we talking about? Is it a VF300 meeting? On March 19th? In El Paso?

________________________________

From: (b) (6)


Sent: Tuesday, February 26, 2008 4:32 PM
To: (b) (6)
Cc: (b) (6)
Subject: RE: Vf300 battle rhythm/calendar

I didn’t know the travel time from El Paso was that long when I did this, but I will revise now to correct
those instances & resend out.

(b) (6) need your recommendation on who should attend from external entities and USACE,
respectively.

(b) (6) please provide the same for OBP.

(b) – heads-up. Looks like meeting will be only on March 19th, so will need hotel block for night of
(6)
March 18th, and meeting room at sector for all day March 19. Is this possible?

Thanks,

(b) (6)

Business Manager, Operations and Reporting

SBI - Tactical Infrastructure Program (PF225, VF300)

U.S. Customs and Border Protection

(b) (6)

*** PLEASE NOTE NEW EMAIL ADDRESS ****

CONFIDENTIALITY NOTICE: The information contained in this electronic mail and its attachments are
privileged and confidential information and are intended for the use of the individual(s) or entity named
above and those who have been specifically authorized to receive it. If you are not the intended
recipient, you are hereby notified that any use, copying or distribution of this communication is strictly
prohibited.

________________________________
From:(b) (6)
Sent: Tuesday, February 26, 2008 4:14 PM
To: (b) (6)
Cc: (b) (6)
Subject: Re: Vf300 battle rhythm/calendar

Did not make much sense to have split over two half days. Make it one full day.

Take a look at the Battle Rhythm and let's deconflict so this does not happen again.

Let's also look at attendees and make sure we have the right people present, and not a cast of
thousands.

Just having it one day actually helps me. I can fly in and out after hours and only miss one day while
Loren is doing his AF AD.

(b)
(6)

----- Original Message -----


From: (b) (6)
To: (b) (6)
Cc: (b) (6)

Sent: Tue Feb 26 16:04:45 2008


Subject: FW: Vf300 battle rhythm/calendar

See (b) (6) email below -- do you want to start at 8am on the 19th instead, or just schedule to go
through other sectors first on the afternoon of the 18th??

(b) (6)

________________________________

From: (b) (6)


Sent: Tuesday, February 26, 2008 3:57 PM
To: (b) (6)

Cc: (b) (6)

Subject: RE: Vf300 battle rhythm/calendar

El Paso PDT and VF300 team members will not be able to be in Yuma at 1:00 pm. on the 18th. Our
regular PDT meeting starts at 9:00 am and ends typically at Noon. I figure it will be late afternoon-
early evening onthe 18th before we get to Yuma.

(b) (6)
________________________________

From: (b) (6)


Sent: Tuesday, February 26, 2008 2:37 PM
To: (b) (6)

Subject: FW: Vf300 battle rhythm/calendar

All - attached is the current battle rhythm for the PDTs and the VF300 project. I believe it goes thru
October 08. Please note that the upcoming face to face VF300 meeting will be on the 18th/19th of
March in Yuma. (b) s working to get a hotel IDed.
(6)

Please provide this out to your PDT team members that would need this for both PDT and VF purposes,
ie Real Estate, Envirionmental, Engineering and other support to your teams.

(b) (6) - need to coordinate for exact time and conference room for the upcoming meeting.

Please note new email that will begin as of March 2008 below

(b) (6)
Chief, Tactical Infrastructure Branch
ECSO
(b) (6)

________________________________

From: (b) (6)


Sent: Friday, February 22, 2008 4:15 PM
To (b) (6)
Cc: (b) (6)

Subject: RE: Vf300 battle rhythm/calendar

(b) (6)
Sorry for the delay. Here's the final calendar. The PM's reporting dates on here are subject to change
as the process is refined.
Let us know if you see any other potential conflicts on here.

Thanks,

(b) (6)
Business Manager - Operations & Reporting
SBI, Tactical Infrastructure Program
(b) (6)

Please note new email **

________________________________

From: (b) (6)


Sent: Fri 2/22/2008 4:09 PM
To: (b) (6)
Subject: FW: Vf300 battle rythmn/calendar

sorry, this did not go thru the first time. I forgot to add the associates.
Can you send me the final calendar. I really need to get out to the teams.

Thans

Please note new email that will begin as of March 2008 below

(b) (6)
Chief, Tactical Infrastructure Branch
ECSO
(b) (6)

-----Original Message-----
From: (b) (6)
Sent: Friday, February 22, 2008 12:44 PM
To: (b) (6)
Cc: (b) (6) '
Subject: Vf300 battle rythmn/calendar

(b) - I need the final version of this so I can distribute to the team so
(6)
they can begin planning travel for next mths.

Thanks.