Академический Документы
Профессиональный Документы
Культура Документы
RECOMMENDATION:
Enhancement in the contract of supervisory consultant M/s DMC from Rs. 29.52
Million to Rs. 40.978 Million and extension in time from 1/10/2014 to 30/06/2016 (21months) is placed before the PKHA Executive Board for its approval in the best interest of
the project.
AGENDA ITEM # 08
CONSTRUCTION SUPERVISION OF REHABILITATION OF MILL BYPASS ROAD
STAGEII. SH: EXTENSION IN TIME LIMIT.
Supervision of above cited scheme was awarded to M/S Pavron Islamabad,
vide work order No. PKHA/Consultants/No. 132/2013 dated 22/01/2013 with a completion
period from 30/1/2013 to 30/7/2014 (18 months).
The details of supervision contract is as under:
1.
2.
3.
4.
5.
6.
7.
8.
PC-II cost/AA
Bid cost
Date of commencement
Date of completion (Original)
1st Extension already granted
2nd Extension required
Consultancy cost upto 15/1/2015
Total Consultancy upto 30/4/2015
With grant of 2nd time extension the consultancy cost will be enhanced from
original amount of Rs. 7.000 million to 9.977 million with overall 42.52% contract
enhancement, which comes under the competency of PKHA Executive Board. Time
extension has already been granted to the civil work contractor due to the following
reasons:
a)
b)
c)
RECOMMENDATION:
Enhancement of consultancy contract cost from Rs. 7.000 million to Rs. 9.977 million which
is well within approved PC-II cost is placed before the PKHA Executive Board for approval
and regularizing the matter.
CONSTRUCTION SUPERVISION
INTERCHANGE TO TORU
EXTENSION IN TIME LIMIT
In the light of above the bid cost will be enhanced from 19.282 million to
20.760 million, however it is still covered within the PC-II cost of Rs.26.260 million.
The project work could not completed by target date. The main reasons of
delay are as enlisted below:a)
b)
c)
As the extension in time limit is 18 months and 16 days on the original time
hence comes under the competency of PKHA executive board, besides, the bid value has
also been enhanced from original approved bid cost of Rs. 11.052 million to Rs. 20.760
million with 88% contract cost enhancement such that its approval comes under the
competency of PKHA executive board.
RECOMMENDATION:
In view of the above, the forum is requested to approve the extension in time
limit from 01/02/2015 to 31/05/2015 (88% contract enhancement) is placed before the
PKHA Executive Board for approval in the best public interest.