Академический Документы
Профессиональный Документы
Культура Документы
TOPIC: LEVELLING
ENGINEERING SURVEYING 1
SUG113
By:
En Noorsazwan Ahmad Pugi
Dept. of Surveying Science & Geomatics
UiTM Perak
Review of levelling
z Lecture Contents :
{Introduction
{Definitions
{Principles of Levelling
{Equipment
{Levelling Procedures
{Worked Example
{Loop Misclosure
{Errors in Levelling
{Applications
Introduction
z Levelling
{Levelling is the process by which differences in
height between two or more points can be
determined.
{Its purposes include to provide heights or
contours on a plan, to provide data for road
cross-sections or volumes of earthworks, or to
provide a level or inclined surface in the setting
out of construction works.
7/5/2010
What is levelling?
z A measurement process whereby the
difference in height between two or more
points can be determined
BS
FS
Difference in height
H=BS-FS
When do we level?
z Typical examples include :
{To establish new vertical control (BM or TBM)
{To determine the heights of discrete points
{To provide spot heights or contours on a plan
{To provide data for road cross-sections or
volumes of earthworks
{To provide a level or inclined plane in the
setting out of construction works
Definitions
z Level surface
{A surface over which water will not flow
{The direction of gravity is always normal to a
l
level
l surface
f
z Horizontal surface
{A horizontal surface will be tangent to a level
surface and perpendicular to the plumb line
7/5/2010
Definitions (cont.)
direction of gravity
horizontal
surface
level surface
limit of practical
coincidence (~100 m)
Definitions (cont.)
z Datum
{A reference surface to which the heights of all points in
a survey or on a site are referred
{The height value may be assigned an assumed
elevation, but true elevation is required for the
establishment of a Bench Mark (BM)
Definitions (cont.)
z Reduced Level (RL)
{The height of a point above the datum
z Benchmark (BM)
{A stable
t bl reference
f
point
i t off known
k
RL
{Usually used as the starting and finishing point
when levelling
7/5/2010
Definitions (cont.)
z Backsight (BS)
{Always the first reading from a new instrument
station
z Foresight (FS)
{Always the last reading from the current
instrument station
Definitions (cont.)
z Change point (CP)
{Location of the staff when the level is moved
{Change points should be...
zStable
zWell defined
zRecoverable
ze.g. sharp rock, nail, change plate, etc...
7/5/2010
Principle of Levelling
z The level is an optical instrument that provides a height
reference. This reference is a horizontal plane through
the axis of the telescope, known as the "Height of
Collimation".
z Once the Height of Collimation (or Instrument Height)
has been measured, the height of other stations can be
found by measuring from this plane with a staff
staff.
z The height of collimation is found by taking a Back Sight
to a staff placed on a bench mark. The staff reading is
added to the bench mark value to obtain the height of
collimation.
z Once the height of collimation has been found, ground
height at any spot below this plane can be found by
observing the staff and subtracting the staff reading from
the height of collimation.
Equipment
z Level
z Dumpy Level
z Tilting Level
z Automatic Level
z Digital Level
z Tripod
z Staff
z Staff bubble
z 50 m tape measure
Levelling Staff
z Used to measure the vertical distance from the
horizontal plane established by a level to
points where heights are required.
z Graduated in cm and can be read to the
nearest mm by interpolation.
z The have length up to 5m.e.g. E-type staff
z Can be fitted to the circular bubble (staff
bubble) so that a staff can be held vertically at
each point.
7/5/2010
0.339
0.33
0.3
Levelling Instruments
z Dumpy level
z The telescope of the dumpy level is rigidly fixed to its supports.
z It cannot be removed from its supports nor can it be rotated about
its longitudinal axis.
z The instrument is stable and retains its permanent adjustment for
a long time.
z A dumpy level is an older style instrument that requires skilled use
to set accurately.
z The instrument requires to be set level (see spirit level) in each
quadrant, to ensure it is accurate through a full 360 traverse.
z Tilting Level
z The telescope can be tilted slightly about its horizontal axis with the
help of a tilting screw.
z In this instrument the line of collimation is made horizontal for each
observation by means of the tilting screw.
z This instrument allows the telescope to be effectively flipped through
180 ,
without
ih
rotating
i the
h h
head.
d
z The telescope is hinged to one side of the instruments axis, flipping it
involves lifting to the other side of the central axis (thereby inverting
the telescope).
z This action effectively cancels out any errors introduced by poor setup
procedure or errors in the instruments adjustment.
z As an example, the identical effect can be had with a standard
builders level by rotating it through 180 and comparing the
difference between spirit level bubble positions
7/5/2010
z Automatic Level
z This is also known as the self-aligning level.
z This instrument is levelled automatically within a certain
tilt range by means of a compensating device (the tilt
compensator).
z Digital
g
Level
z This instrument has been designed to carry out all reading
and data processing automatically via an on-board
computer which is accessed through a display and
keyboard.
z Using electronic image processing techniques built in
digital level, a special bar-coded staff is sighted to get the
height of the points.
Levelling Procedures
z Adjustment of Level
{Two pegs test
z Field Procedure
z Reduction of Levels
{Rise and Fall
{Height of Collimation
Two-peg test
z Identifies whether the level has a
collimation error
z Allows the collimation error to be
determined
7/5/2010
Ha
Suhu
No. Siri Alat
: 32C
: 2930
Hb
B
L
Hc
Hd
B
L/10
Field Procedures
z Always commence and finish a level run
on a Benchmark (BM or TBM)
z Keep foresight and backsight distances as
equall as possible
ibl
z Keep lines of sight short (normally < 50m)
z Never read below 0.5m on a staff
(refraction)
z Use stable, well defined change points
BS
IS
IS
FS
I1
TBM
7/5/2010
TBM 48.710m
I2
I1
I3
I2
B
TBM
IS
FS
BS
IS
BS
E
BS
IS
FS
FS
I1
3.824
4
2.513
1.752
2.325
E
2.811
3.019
2.505
2.1
191
1.496
6
TBM 49.873m
Levelling Sequence
I3
TBM
Booking Procedure
(All values in meters)
UKURAN NO:..
BELAKANG
(BS)
ANTARA
(IS)
HADAPAN
(FS)
NAIK
(RISE)
TARIKH.
TURUN
(FALL)
TINGGI GRN
KOLIMANTAN
(HOC)
ARAS
LARAS
(RL)
JARAK
(D)
TBM 49.873
2.191
A
2.505
3.019
2.325
B
1.496
C (CP)
D
2.513
1.752
CATATAN
(REMARKS)
2.811
3.824
E (CP)
TBM 48.710
7/5/2010
ANTARA
(IS)
HADAPAN
(FS)
NAIK
(RISE)
TURUN
(FALL)
TINGGI GRN
KOLIMANTAN
(HOC)
ARAS
LARAS
(RL)
JARAK
(D)
TBM 49.873
49.873
2.191
49.559
0.180
49.739
0.829
50.568
C (CP)
0.506
51.074
2.505
0.314
2.325
3.019
1.496
2.513
1.752
6.962
8.131
CATATAN
(REMARKS)
2.811
0.298
50.776
3.824
2.072
48.704
TBM 48.710
(2.684)
48.704
49.873
Check
Misclosure
0.006m
-1.169
Correct
(8.131)
1.515
2.684
-1.169
-1.169
E (CP)
Arithmetical Checking
ANTARA
(IS)
HADAPAN
(FS)
NAIK
(RISE)
TURUN
(FALL)
TINGGI GRN
KOLIMANTAN
(HOC)
ARAS
LARAS
(RL)
JARAK
(D)
CATATAN
(REMARKS)
TBM 49.873
2.191 (+)
3.019
52.064
49.559
2 325
2.325
49 739
49.739
(+)
1.496
53.587
2.513
1.752
6.962
8.131
49.873
2.505
(+)
2.811
(8.131)
3.824
-1.169
Arithmetical Checking
52.528
50.568
C (CP)
51.074
TBM
D 48.710
E (CP)
50.776
48.704
49.873
48.704
Check
Misclosure
0.006m
-1.169
Correct
BS - FS = last RL 1st RL
Collimation Error
z Occurs when the line of sight (as defined
by the cross-hairs) is not horizontal
z Leads to an incorrect staff reading
error
horizontal line
10
7/5/2010
Example
Setup 4
CP 3
BM A
Kerb
Setup 1
Setup 3
Kerb
Setup 2
CP 1
CP 2
Post
BM A
Back
Inter
Fore
1.32
2 56
2.56
Kerb
Setup 1
3 98
3.98
1.25
Setup 3
Kerb
2.64
Post
0.67
CP 2
1.54
CP 3
2.58
Kerb
3.79
CP 1
CP 1
Kerb
3.65
3.49
Setup 2
Point
BM A
BM A
CP 2
Post
Fore
Rise
3.98
1.31
0.67
2.98
0.91
1.04
1.54
3.79
9.98 6.24
(0.03)
Fall
RL
50.00
47.34
48.65
46 25
46.25
49.23
50.14
51.18
50.03
Comment
BM A
2.66
CP 1
Kerb
2 40
2.40
Post
CP 2
Kerb
CP 3
1.15
BM A
6.21
(0.03) (0.03)
11
7/5/2010
Loop Misclosure
z Misclosure
{The amount by which the measured height
difference (Hmeas) differs from the known
height
g difference derived from the RLs of the
starting and finishing benchmarks (Hknown)
Misclosure = Hknown - Hmeas
An acceptable misclose?
z Small misclosures in closed level loops
are expected because of the accumulation
of errors
z If the misclosure is small, it can be
adjusted
z If the misclosure is large, the loop (or part
of it) must be repeated
z Misclosures can also result from errors in
published BM levels and from BM
instability
12
7/5/2010
Point
50.00
BM A
47.34
CP 1
48.65
Kerb
46.25
Post
49.23
CP 2
50.14
Kerb
51.18
CP 3
50.03
BM A
Adjustment Adjusted
RL
13
7/5/2010
Point
Adjustment Adjusted
RL
50.00
BM A
0.000
47.34
CP 1
0.008
48.65
Kerb
46.25
Post
49.23
CP 2
50.14
Kerb
51.18
CP 3
50.03
BM A
50.000
47.332
=1*(0.03/4)
Point
Adjustment Adjusted
RL
50.00
BM A
0.000
50.000
47.34
CP 1
0.008
47.332
48.65
Kerb
0.015
48.635
46.25
Post
0.015
46.235
49.23
CP 2
0.015
50.14
Kerb
51.18
CP 3
50.03
BM A
49.215
=2*(0.03/4)
Point
Adjustment Adjusted
RL
50.00
BM A
0.000
50.000
47.34
CP 1
0.008
47.332
48.65
Kerb
0.015
48.635
46.25
Post
0.015
46.235
49.23
CP 2
0.015
49.215
50.14
Kerb
0.023
50.117
51.18
CP 3
0.023
51.157
50.03
BM A
=3*(0.03/4)
14
7/5/2010
Point
Adjustment Adjusted
RL
50.00
BM A
0.000
50.000
47.34
CP 1
0.008
47.332
48.65
Kerb
0.015
48.635
46.25
Post
0.015
46.235
49.23
CP 2
0.015
50.14
Kerb
0.023
51.18
CP 3
0.023
50.03
BM A
0.030
49.215
=4*(0.03/4)
50.000
Point
Adjustment Adjusted
RL
50.00
BM A
0.000
50.000
47.34
CP 1
0.008
47.332
48.65
Kerb
0.015
48.635
46.25
Post
0.015
46.235
49.23
CP 2
0.015
49.215
50.14
Kerb
0.023
50.117
51.18
CP 3
0.023
51.157
50.03
BM A
0.030
50.000
Errors in levelling
z Collimation
z Parallax
z Change point instability
z Instrument instability
z Staff instability
z Benchmark instability
z Refraction
15
7/5/2010
Errors in levelling
z Staff reading and interpolation errors
z Staff verticality
z Instrument shading
z Temperature on staff
z Booking errors (e.g. using just 1
benchmark)
z Earth curvature
z Magnetic field effects on auto level
Applications of levelling
z Point heights (relative to a datum)
z Height differences (independent of datum)
z Longitudinal sections and cross sections
z Data for volume calculations
z Contouring
z Setting out
16