Today, Flashing of RO Plants start at and Stop at. Please find the attachment of
log sheet of RO-I and RO-II.
There is no Mechanical and Electrical Contractor ManPower in RO plant and Ring
Dryer.
PLC Work:-vcvcvcvcv
Today, programme of these works in PLC Completed and it will download in PLC
Tomorrow as:
1. Provide Programme as Alarm feed with date and time.
1. Provide Programme as RO-I and RO-II run in one Auto other manual.
2. Provide Programme as selection of High Pressure Pump, single select then
start only single pump.
Mr.Pragatand Mr. Dinesh wants to this implementation also as
1. ORP Transmitter to check RO-I and RO-II feed quality interlocking with
auto operated Dump Valve.
2. RO-I and RO-II SMBS Dosing Unit, Acid Dosing Unit, Anti Scalent Dosing
unit control synchronized for auto operation with Feed Pump
3. Provide Differential Pressure Indicator RO-I and RO-II inlet for analysis
membrane Chocking Indication.
Pending Work:RO-I
1. Calibration of Raw water SV Series Sensor meter for check level of raw
water tank for RO-I feed.
2. Calibration of Buffer tankmeter for check level of raw water tank for RO-II
feed.
3. Change of raw water feed Pump UPVC Pipe outlet line and NRV.
4. Change Raw water Pump MGF, ACF MCF Pressure gauge.
5. Change RO Reject second stage pressure gauge.
6. Attend all leakage of RO plant.
7. Setting of Pressure Switch at outside and Inside of High pressure Pump.
RO-II
1. Change Booster Pump outlet Pressure gauge, second stage pressure
gauge and Reject pressure gauge.
2. Attend Leakage of HPP-I Outlet SS Valve.
3. Change of Feed water Rotameter.
4. Replaced End Cap.
5. Setting of Pressure Switch at outside and Inside of High pressure Pump.