dskdhlkshlknhdlknhlkDear Sir,

Today, RO Plants start at 10:00 am and run in auto mode.


There is Two Mechanical and no Electrical Contractor ManPower in RO plant
PLC Work:Today, as per your trail mail, programme of these works in PLC Completed.
1. ORP Transmitter to check RO-I and RO-II feed quality interlocking with auto
operated Dump Valve.
Instrument Work:
Instruments PH,cond1, TDS2 are calibrated. and Now Calibration ORP meter
Pending due to not available solution .one cond2 meter not working. One TDS 1
metre at feed is of low range ,TDS meter range should be of above 7000.
Mechanical Work:1. Changed all cock valve.
2. Change Rubber Gasket valve at high pressure joints of flanges
Pending Work:Change TDS Conductivity and PH meter.
Meter Calibration (ORP meter )
Thanks and Regards
Donesh