Job No:
Client:
NPM
Site Contact:
Steven Vickers & Andrew
Hubbard
Date:
22 October 2013
Arrival Time:
07:00 am
Departure Time:
02:00 pm
Exact Location:
Northparkes Mine, 27km from Parkes NSW 2870
Work Item(s) Being Inspected:
E48 ROM Bin Wall
General Site Observations; Defective Work and Materials; Non-Compliances; Test Results; Plant &
Labour on Site; Hold/Witness Points Reached:
E48 ROM Bin Wall connection to concrete columns - Significant number of sheared bolts found
E48 ROM Bin Wall steelwork Defective connections, local web buckling of main members and
deformed plate work were observed.
E48 ROM Bin Floor supports Sheared bolts and bent connection cleats observed.
Delays: NA
Environmental; OH&S; Industrial Relations Issues:
GHD team inducted and escorted to the ROM Bin Location.
Verbal Directions provide to site contact
Recommended to install and tension all the missing bolts and replace existing to assembly joints.
Verbal advice followed by email dated 23/20/13
Further Inspection on Work Item(s) Listed Above: Likely to be required during execution of remedial works.
Photographs Taken:
Yes
No
Ground Conditions:
Good
Contractors
Verification Records:
Complete
Incomplete
Non Existent
Not Applicable
Action Required ..................................................................................................
Surveyor results/comments:
Weather Conditions:
Fine
Acceptable
N/A.
Overcast
Light Rain
Heavy Rain
Other ________
Other Comments: Discussed with NPM the need to immediately address the connections of the E48 ROM Bin
wall due to the significant reduction of structural capacity. It is likely that due to the observed concrete wall
convergence, more bolts have been affected or have no additional room to allow slippage. The total loss of
bolts (4 observed) will basically redistribute stresses transferring the load elsewhere causing overload and hence
reducing structural redundancy. This issue requires urgent attention.
Reference: 22 / 16901
Procedure 3.03.08
September 2001
QA042
Distribution:
Job No:
Photo 1: E48 crusher station and ROM Bin wall & access scaffold overview.
Reference: 22 / 16901
Procedure 3.03.08
September 2001
QA042
Distribution:
Job No:
Photo 4: E48 ROM Bin wall extension (top of wall) deformations observed.
Reference: 22 / 16901
Procedure 3.03.08
September 2001
QA042
Distribution:
Job No:
Photo 5: E48 primary stiffener beam failed connection observed. Missing bolt
Reference: 22 / 16901
Procedure 3.03.08
September 2001
QA042
Distribution:
Job No:
Photo 6: E48 primary stiffener beam failed connection observed. Wall convergence caused bolt shear
failure. Deformation of the bolt hole also visible.
Photo 7: Deformed plate and vertical stiffener beams web buckling observed.
Reference: 22 / 16901
Procedure 3.03.08
September 2001
QA042
Distribution:
Job No:
Reference: 22 / 16901
Procedure 3.03.08
September 2001
QA042
Distribution:
Job No:
Photo 10: Ineffective vertical stiffener wall panel connections observed at thecentral vertical stiffener on
level 5. There are missing and loose bolts. The connection has not been executed in accordance with
the design drawings ie. There is not flange welding provided to assist with load shedding.
Reference: 22 / 16901
Procedure 3.03.08
September 2001
QA042
Distribution:
Job No:
Reference: 22 / 16901
Procedure 3.03.08
September 2001
QA042
Distribution:
Job No:
Photo 13: Deformed access ROM Bin floor connections observed, typical.
Reference: 22 / 16901
Procedure 3.03.08
September 2001
QA042
Distribution:
Job No:
Reference: 22 / 16901
Procedure 3.03.08
September 2001
QA042
Distribution:
Job No:
Reference: 22 / 16901
Procedure 3.03.08
September 2001
QA042
Distribution:
Job No:
Reference: 22 / 16901
Procedure 3.03.08
September 2001
QA042