H O S T E D BY
KEYWORDS
Sand control method;
Economic evaluation;
Skin factor
Abstract Formation sand control is always one of the main concerns of production engineers.
There are some different methods to prevent sand production. Choosing a method for preventing formation sand production depends on different reservoir parameters and politic and economic conditions. Sometimes, economic and politic conditions are more effective to choose an
optimum than reservoir parameters. Often, simultaneous investigation of politic and economic
conditions with reservoir parameters has different results with what is expected. So, choosing
the best sand control method is the result of thorough study. Global oil price, duration of sand
control project and costs of necessary equipment for each method as economic and politic
conditions and well productivity index as reservoir parameter are the main parameters studied
in this paper.
2015 The Authors. Production and hosting by Elsevier B.V. on behalf of Egyptian Petroleum Research
Institute. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/
licenses/by-nc-nd/4.0/).
1. Introduction
The production of formation sand into a well is one of the oldest problems plaguing the oil and gas industry because of its
adverse effects on well productivity and equipment. It is normally associated with shallow, geologically young formations
that have little or no natural cementation to hold the individual sand grains together. As a result, when the wellbore pressure is lower than the reservoir pressure, drag forces are
applied to the formation sands as a consequence of uid production. If the formations restraining forces are exceeded,
sand will be drawn into the wellbore. The produced sand has
essentially no economic value. On the contrary, formation
sand not only can plug wells, but also can erode equipment
* Corresponding author.
E-mail address: khamehchi@aut.ac.ir (E. Khamehchi).
Peer review under responsibility of Egyptian Petroleum Research
Institute.
http://dx.doi.org/10.1016/j.ejpe.2015.05.009
1110-0621 2015 The Authors. Production and hosting by Elsevier B.V. on behalf of Egyptian Petroleum Research Institute.
This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).
194
E. Khamehchi et al.
Nomenclature
Bo
Dperf
h
hp
Kg
Kr
m
n
qo
rl
rw
Sg
Spp
Ssl
Sww
ps
l
X
Well Data.
Table 2
ID producing tubing
Top of producing sand face
Wellhead temperature
Production uid
Thickness of producing layer
Wellbore radius
Wellhead pressure
0.08 m
2868.168 feet
25 C
Oil
45.72 m
0.1524 m
4.82 MPa
141:2qo Bo lo Sg
kr h
where Sg is:
h
rw
Kr
Sg
ln
1
rl
Kg
hP
Reservoir pressure
Solution GOR
Oil gravitya
Gas gravitya
Oil viscositya
Oil FVFa
Reservoir temperature
Bubble point pressure
Drainage area
a
27.74 MPa
323 m3/m3
37API
0.73 sp gr
0.0017 Pa s
1.954 m3/Sm3
110 C
16.71 MPa
7.65 km2
D2perf n
Table 1
96 KKgr hLP
2
2
ln
n pX
Skin factor
Reservoir permeability
Pb, Rs, Bo correlations
Viscosity correlation
8.3
53 md
Standing method
Beggs et al. method
Figure 1
Figure 2
195
196
E. Khamehchi et al.
can use Eq. (4) for skin factor due to wire wrapped screens. Eq.
(2) can be used too. But outside permeability of screen is used
instead of gravel pack permeability.
2.4. Pre-packed screen
Pre-packed screens are constructed from two concentric
screens with a layer of gravel placed in between them. The
gravel had been coated with a layer of thermosetting resin.
The construction process is as follows [5]:
Figure 4
Figure 5
(i) The dual concentric screens have been welded onto the
base pipe.
(ii) The gap between them is lled with the resin coated sand
and the nal welds made.
(iii) The completed screen is placed in an oven where
the thermosetting resin, hardens creating a strong ring
of gravel.
197
Mesh size
Permeability
Length of penetration
30/50
90 D
0.0508 m
Figure 6
Figure 7
Table 5
0.0762 m
0.0814 m
0.1524 m
0.000762 m
10
3. Model description
In this section, the production system of the real well of
Iranian eld will be investigated which has potential of sand
production and causes many problems on the surface equipment. Different strategies for completion of this well can be
designed; however, the purpose is to design a way which results
in maximum economic prot. In other words, the difference
between costs of implementation of sand control completion
and the benets of oil production after that should be maximized. This is not true that the method for less skin effect is
198
E. Khamehchi et al.
0.067 m
1000 md
0.054 m
0.08128 m
Figure 8
Figure 9
199
Cost (1000$)
400
600
1000
1500
30 20
6000
300
8000
3 300
10 20
80
400
3 800
10 20
400
4 1200
10 20
400
Production rate at
operating point
Total skin
factor
1410
1078
1310
8.7
14.8
10.2
1370
9.5
Figure 10
200
E. Khamehchi et al.
Figure 11
Figure 12
201
Figure 13
Figure 14
202
E. Khamehchi et al.
4. Economic evaluation
5. Conclusion
As said before, the skin value and the operation rate are not
the only main parameters for choosing the best project.
Economic evaluation is the most important step of deciding.
In this section, it is tried to compare all methods economically
by using approximate operating cost of any method. Finally,
the best project will be found.
Table 8 provides the typical approximate operation
expenditures, which are necessary for economic evaluation,
for all sand control methods. Also, oil barrel price should
be known. It is assumed as 80 $/bbl. Other assumptions
are as follows:
References
[1] E. Khamehchi, I. Rahimzadeh Kivi, M.R. Akbari, A novel
approach to sand production prediction using articial
intelligence, J. Petrol. Sci. Eng. 123 (2014) 147154.
[2] R. Risnes, R.K. Bratli, P. Horsrud, Sand arching a case study,
In: paper EUR 310, presented at the European Petroleum
Conference, Oct 2528, 1982.
[3] B. Wu, C. Bahri, S. Carigali, C.P. Tan, Q. Li, H. Rahim, G.
Kartoatmodjo, T. Friedel, Sand production prediction for a mature
oil eld offshore East Malaysia a case study, SPE 133375, In: SPE
Asia Pacic Oil & Gas Conference and Exhibition, Brisbane,
Queensland, Australia, 1820 October 2010.
[4] C.U. Okoye, S. Suriyakriangkai, A. Ghalambor, Analysis of
skins and the performance of gravel packed completions in oil
and gas wells, SPE 23827, In: SPE Symposium or Formation
Damage Control Held in Lafayette, Louisiana, 1992.
[5] S. Michael, Resin coated pre-packed sand control liner, SPE
83480, In: SPE Western Regional/AAPG Pacic Section Joint
Meeting, California, 2003.
[6] T.M.V. Kaiser, S. Wilson, Inow analysis and optimization of
slotted liners, SPE 80145, In: SPE Drilling and Completion, 2002.