Академический Документы
Профессиональный Документы
Культура Документы
kr~
@ TECHNIP-EXT
To:
cc:
Subject: Re: Advice on storage tank heating coil calculation
Dear Jawed
I have had a quick look at your query and following are my observations in this regard :
We need to maximise the length of the heating coil to be provided in the tank.
If SKEC are agreeing to provide 11568m coil length then this should be implemented.
Coil pitch normally becomes a limitation if the coil was being bent in a U-form or inserted in tubesheet
etc. therefore I do not foresee any problems in this regard. It should be possible to reduce the coil
pitch if required.
To maximise efficiency of the heat transfer it is important that the coil length provided in the shell is
maximised. If we provide too much length in the bottom then localised temperature gradient might
develop leading to increased heat losses through the tank bottom.
You should also consider the fact that the heating of the tank contents is likely to occur in three
phases :
Sensible heating from 15 Deg.C to 114.5 Deg.C
Fusion of sulphur at 114.5 Deg.C
Sensible heating again from 114.5 Deg. C to 140 Deg.C.
Therefore, the corresponding heat transfers will occur at different levels of LMTD. Further, since it is a
batch operation therefore LMTD in each of these phases will constantly keep changing. For this I
would recommend you to refer chapter 18 on batch heating in KERN and study the impact of
equation 18.5. Additionally, you can quickly run through this chapter on batch and unsteady-state
processes and see if something else is also applicable or not.
The heating coil length at the bottom I would suggest you to increase in same proportion as the
increase in bottom area from the existing tank.
Once again carefully analyse the roof losses and confirm the applicability of the equations used. I
hope winter ambient conditions have been considered in this regard.
I would refrain from taking credit for the roof coils / shell coils (top 20% height) in the heating of the
tank contents.
Finally, we shouid try to minimise deviating from the existing approach with respect to coil
arrangement.
I hope the above addresses your concerns. I am sorry for the delay in this response as I am just too
tied up on other issues.
Convey my hello to Sridhar and ask him to drop an email to me.
Bye and best wishes.
Anil
An11Bhatla
24/08/99 17 51
To:
@ TECHNIP-EXT
'jawed ismail" ~jawed@cosmos.skec.co.kr~
cc:
Subject: Re: Advice on storage tank heating coil calculation
One thing to add : For your information the shell coil pitch in the existing tank as per Snamprogetti
data sheet is 215 mm.
......................
..... ...,..... .,...,....
'
p..
,
>
A,A
...
? .
,.<, .........
Anll Bhatla
24/08/99 17 47
To:
'lawed ismail" ~jawed@cosmos.skec.co.kr~
@ TECHNIP-EXT
cc:
Subject: Re: Advice on storage tank heating coil calculation
Dear Jawed
I have had a quick look at your query and following are my observations in this regard :
We need to maximise the length of the heating coil to be provided in the tank.
If SKEC are agreeing to provide 11568m coil length then this should be implemented.
Coil pitch normally becomes a limitation if the coil was being bent in a U-form or inserted in tubesheet
etc. therefore I do not foresee any problems in this regard. It should be possible to reduce the coil
pitch if required.
To maximise efficiency of the heat transfer it is important that the coil length provided in the shell is
maximised. If we provide too much len h in the bottom then localised temperature gradient might
develop leading to increased heat losses through the tank bottom.
You should also consider the fact that the heating of the tank contents is likely to occur in three
phases :
Sensible heating from 15 Deg.C to 114.5 Deg.C
Fusion of sulphur at 114.5 Deg.C
Sensible heating again from 114.5 Deg. C to 140 Deg.C.
Therefore, the corresponding heat transfers will occur at different levels of LMTD. Further, since it is a
batch operation therefore LMTD in each of these phases will constantly keep changing. For this I
uld recommend you to refer chapter 18 on atch heating in KERN and study the impact of
uation 18.5. Additionally, you can quickly
h this chapter on batch and unsteady-state
processes and see if something else is also applicable or not.
h at the bottom I would s gest you to increase in same proportion as the
increase in b a o m area from the existing tank.
ain carefully analyse the roof losses and nfirm the applicability of the
hope winter ambient con itions have been considered in this regard.
I would refrain from taking c
tank contents.
it for the roof coils I shell coifs (top 20% height) in the heating of the
Finally, we should try to minimise deviating from the existing approach with respect to coil
arrangement.
I hope the above addresses your concerns. I am sorry for the delay in this response as I am just too
tied up on other issues.
Convey my hello to Sridhar and ask him to drop an email to me.
Bye and best wishes.
Anil
And Bhatla
11108199 16 26
Tawed ismail" ~jawed@cosmos.skec.co.kr~
@ TECHNIP-EXT
To:
cc:
Subject: Re: Query
Dear Jawed
I am sorry for the delay in answering your query. The difference in the steam consumption is because
the existing system considers 77 truckslday unloading whereas the new system considers 90
truckslday unloading after expansion. This is based on the no. of trucks that will be unloaded once
the system is expanded based on the bay occupancy of 75% and that each truck will consume
approx. 49.7 Kg of steam. Total 5000 MTPD of sulphur is assumed to be unloaded after expansion.
Existing sulphur unloading rate is 2300 MTPD. The figure in table 2 is the additional consumption.
I hope this clarifies your query.
.#
*'
An11Bhatla
04/08/99 09 38
To:
"jawed ismaif" <jawed@cosmos.skec.co.kr>@ TECHNIP-EXT
cc:
Subject: Re: STORAGE TANKS - REVfSlON
Dear Jawed
I have no objection to use of hi in equation 13. This only marginally reduces the heat transfer
co-efficient as long as hv is correctly accounted for because that is what is going to determine the
overall heat transfer co-efficient. Just for cdnfirmation purposes I would suggest you to ask SKEC to
furnish you the source of the formula in equation 14 for hv.
Regarding the steam info I think that for consistency sake the two should be same.
I am pleased to note that you have moved to a new apartment. On TV we have been regularly seeing
news clippings about the massive rains that are taking place in that area. Were you adequately
prepared for this contingency?
Bye and best wishes
Anil
To:
Anil BhatIanPGAUH
cc:
Subject: Advice on storage tank heating coil calculation
Dear Bhatlaji,
SKEC have revised their heating coil calculation for storage tank based on FEED
in 120 hrs. I need your advice
criteria i.e. heating sulphur from 15 *C to 140
on the result. I am summarising the result for easy reckoning. Just for
comparison purpose I am mentioning the relevant details for the existing storage
tank as well.
A) Existing storage tanks:
Diameter = 32.325 m
Height = 7.315 m
Op. temp. = 138 * C
Sizing criteria: To heat sulphur from 15 *C to 140 *C in 120 hrs( Taken from
Ph-I d,s)
@
4
'
Coil Details :
Shell side: 6 coils of 400 m each = 2400 m
pitch = 250 mm
Roof side: 8 coils of 400 m each = 3200 m
pitch = 250 rnm
Bottom side: 8 coils of 400 m each = 3200 m
pitch = 250 mm
Please note that for roof side coils are placed outside the tank roof.
i-/
r^
-\
;zc-
P ;
-ia
I
sw
f
, Sk""
5n
4.
P* *v-
c -7 h
,>
Ire
- -3
cr
3,"e*,
7-:"B
5sq5
"",$
Ideally speaking coil length required to heat the sulphur to 1351140 g C shall be
in contact with sulphur. Based on this philosophy coil used for heating sulphur
shall be placed in bottom and shell(upto 80% height) only. If we extend this
philosophy we will have following coil arrangement:
Case-I
Coil length to be placed in Shell(upto 80% height) + Bottom = 8579+639=9218 m
From Table-I it is clear that even with 200 mm pitch we can place only 3360+5375
= 8735 m of coil. So for putting 9218 m of coil we will have a pitch of less than
200 mm which looks a bit too less. For roof side, coil pitch of slightly less
than 500 mm will be required to place coil length of 2350 m.
Case-I1
Coil length to be placed in Shell(upto 80% height) + Bottom = 7000+639=7639 m
From Table-I it is clear that with 250 mm pitch we can place only 2670+4360= 7030
m of coil. So for putting 7639 rn of coil we will have a pitch of slightly less
than 250 mm which looks reasonable. For roof side, coil pitch of slightly less
than 500 mm will be required to place coil length of 2350 m.
Conclusion
I propose to follow Case-I1 for design. I will fine tune the calculation little
bit. Like presently whole of shell is considered as immersed in liquid sulphur.
But for top 20% of the height I will follow roof side approach as it is not
immersed in liquid sulphur. This will increase the total coil length marginally.
In total new tank will be almost similar to existing tank wrt shell and bottom
side coil. But for roof side we will have a pitch of about 500 mm as compared to
250 mm in existing tank.
I need your advice/comment on above mentioned approach. One more question. Can we
take credit that roof coils/shell coils(top 20% of height) also contribute in the
heating of the contents. If we take credit, we can fix the min. pitch as 250 mm
on bottom and shell and balanced coils(7639-7030=609 m) can be placed in
shell(top20%) and roof side. I still don't have answer about equal length of coil
in bottom and roof in the existing tank.
I hope you will take out some time for me to give your advice.
Sorry for troubling you once again
Rest is fine. I have completed P&ID review as well on last Friday. I am reviewing
few other documents such as design basis, op. & control philosophy and
instruments d/s.
Sridhar has also arrived and is busy in clearing backlogs.
Thanks
&
regards,
Jawed
- attl .htm
To:
Anil BhatlaTTPGAUH
cc:
Subject: Query
Dear Bhatlaji,
Sorry to bother you for one more query on steam calculation. In Table 2 of
'Steam & Condensate System Study' steam requirement for existing truck
unloading baysi5 nos.) is indicated as 159 kg/hr whereas for new unloading
bays (2 nos.) steam quantity is 186 kglhr. Could you please tell me why
steam consumption is more for new unloading bays although no. of bays are
less.
Thanking you in advance,
Regards,
Jawed
To:
Anil BhatlalTPGAUH
cc:
Subject: AdvicelHelp
Bhatlaji,
I need your help/advice on steam material balance shown in PFD. During FEED
you have carried three sets of steam calculations, First one is actual
steam consumption which is indicated in Table 1 of 'Steam and Condensate
Study' and also indicated in 'Utility Balance Summary'. Second one is
normalised steam consumption indicated in Table 2 of above study. Table 2
is generated from Table 1. I could correlate these two tables with respect
to Unit 40 LP steam consumption. But I am unable to do so for Unit 30 LP
steam consumption. Could you please tell me how you have generated Table 2
from Table 1 wrt Unit 30 LP steam consumption (Table 2 figure is 2.08 times
Tablelfigure).
Table 2 figure is reported as average flow in PFD. Third set of figures are
the further normalised values (for total steam consumption of 10,000 kgihr)
using consumption figures of Table 2 . These values are indicated as
Instantaneous flow in PFD.
It is really difficult for SKEC to find out the basis for average flow. I
have thought one easier approach to indicate flows in PFD but I need your
ratification. For average flow I will indicate the actual consumption based
on heat transfer calculations. For new facilities, SKEC's calculated values
will be used. For existing facilities I will use the figures indicated in
Table 1 of study. For calculating instantaneous flow I will normalise all
the values as follows:
MP steam : 450 kg/hr
Unit 30 LP steam : 2000 kgihr
Unit 40 LP steam : 7550 kgihr
Another approach could be to normalise only those values for which
normalisation was done in FEED.
One more clarification. On Page 6 of study, it is stated that temp. rise in
the tank could be around 0.16 'Cihr. But I come up with a figure of 0.246
'Clhr for a heat transfer rate of 501800 kcal/hr, mass as 8500 tons(tank
full) andsp. heat of 0.24 kcal/kg'C.
To:
cc:
Anil BhatlalTPGAUH
Subject:
Hello Bhatlaji,
I am fine here and hope the same for you. Here, SKEC have issued most of the
process documents for company's approval and I am reviewing them. It is
keeping me extremely busy for the time being. I need your guidance, help and
offcourse your invaluable time out of your busy schedule for heating coils
calculation for storage tank and pits. I am attaching their calculations
for storage tank, day pit and the remelt pit.
Overall their approach is OK and the calculations are well documented.
However, I have noticed some discrepancies and drawbacks in their
calculations and will discuss with you once you have reviewed them.
SKEC have done these calculations themselves. For day pit and remelt pit
they have based their calculations on a paper published in Oil & Gas Journal
written by two persons of B&V Pritchard, USA.
During FEED we had estimated coil length for day pit and remelt pit. SKEC
have estimated a coil length of 765 m for day pit as compared to our
estimation of 720 m which is ok. But problem is with remelt pit and storage
tank.
We made a mistake in calculation for remelt pit. Me considered a figure of
157.4 Btuilb for latent heat of fusion of sulphur as compared to actual
figure of about 23 Btu/lb. I checked with Narang on the source of this
figure and he confirmed that there was a mistake. SKEC have estimated a
coil length of 30 m . As you know new remelt pit is identical to existing
remelt pit in size. Unfortunately I don't recollect the coil length in the
existing
pit. Only thing I remember is that it was modified in Phase I and 4 more
rows of coils were added. You may be able to find out this figure in the
file for existing data.
As you know we had already anticipated problem in storage tank and the time
has come to take a decision. SKEC have estimated a figure of 4500 m(tank
capacity = 11500 tons) for the new tank . Existing tank (capacity = 8500
ton) have total coil length of 8800 m with 3200 m each on roof and floor and
2400 m on the shell. What is your suggestion on the coil sizing criteria
indicated in FEED data sheet for heating sulphur from 15 "C to 140 eC in
120 hrs. With the sizing criteria indicated in FEED data sheet, I come up
with the figure of about 7 tihr of steam which doesn't look reasonable. I
am really unable to decide what to do with this criteria and need your
guidance. We had taken this criteria from Phase-I data sheet prepared by
Technip, Paris.
On the personal front things are falling in line one by one, Last week I
shifted to an apartment temporally and next week I will shift to my assigned
apartment. We have found a good Korean restaurant near our office for our
lunch. It has lot of variety and the price is very reasonable. Here rainy
season is at its peak. It is raining almost daily.
How a r e things at your end Must be very busy due to new jobs. You were
ood experienced process engineers to join the group. Rave
any of them joined so far.
Rest is fine. Convey my regards to Bala and other colleagues. I will be
happy if 1 could be of any use to you.
Regards
Jawed
- cal-304.~1~
- pro-304.~1~
- P ro-30 I. pdf
- cal-301 r . xls
To:
Anil BhatlaRPGAUH
cc:
Subject: AdvicelHelp
Bhatlaji,
I need your helpiadvice on steam material balance shown in PFD. During FEED
you have carried three sets of steam calculations. First one is actual
steam consumption which is indicated in Table 1 of 'Steam and Condensate
Study' and also indicated in 'Utility Balance Summary'. Second one is
normalised steam consumption indicated in Table 2 of above study. Table 2
is generated from Table I. I could correlate these two tables with respect
to Unit 40 LP steam consumption. But I am unable to do so for Unit 30 LP
steam consumption. Could you please tell me how you have generated Table 2
from Table 1 wrt Unit 30 LP steam consumption (Table 2 figure is 2.08 times
Table 1 figure).
Table 2 figure is reported as average flow in PFD. Third set of figures are
the further normalised values (for total steam consumption of 10,000 kgihr)
using consumption figures of Table 2 . These values are indicated as
Instantaneous flow in PFD.
It is really difficult for SKEC to find out the basis for average flow. I
have thought one easier approach to indicate flows in PFD but I need your
ratification. For average flow I will indicate the actual consumption based
on heat transfer calculations. For new facilities, SKEC's calculated values
will be used. For existing facilities I will use the figures indicated in
Table 1 of study. For calculating instantaneous flow I will normalise all
the values as follows:
MP steam : 450 kg/hr
Unit 30 LP steam : 2000 kgihr
Unit 40 LP steam : 7550 kgihr
Another approach could be to normalise only those values for which
normalisation was done in FEED.
One more clarification. On Page 6 of study, it is stated that temp. rise in
the tank could be around 0.16 Vihr. But I come up with a figure of 0.246
SCihr for a heat transfer rate of 501800 kcalihr, mass as 8500 tonsitank
full) and sp. heat of 0.24 kcalikg "C.
-----------..---------------------------- 6 SHEETS
( 5340-~~-100
)2
&
Kmncem
~wlstnrcfmco.,~td. Heating Coil Length
Project
NO.
Date
3210
09 JUL 99
Sheet
Rev
Calculation
Calculation
ITEM NO
5340-TK-1002
LOCATION
RUWAIS. UAE
SERVE
AREA
UNIT 40
Tank data
41 'F
5 'C
91,423 mileihr
Wind veloc~tyt3)
5.0 misec )
4.18E*.08 ftlhr2
1 27E+08 mlhR )
Gravcty accelerat~on(g)
(
D~ameter
Height
Stored Temp =
(
1790 kglm3 )
0.@MBtulft.hr 'F
8 cP)
0&@022I r F
OA3
0.005 ft;?.hr.'FIBtu
Ground temp,
(fg) =
(k& =
(Qh) =
7.315
2fS.00
135
14.70
11124 lblft3
Dens~ty (r)
37.43
24.80
Pressure
f22.80
1.033
ft
m)
ft
m)
'F
'6)
psia
kglcm2a )
Insulation data
Ther Cond (K,)
Th~ckness
6.6393
(
(
Resistance R
(),
0.828
Btu&.hr 'F
Wlm 'C )
ft
100
8.348
mm)
ftZ.hr.'FlBt~
0.0680
,~td
I
Project
NO.
Date
3210
09 JUL 99
ITEM NO
5340-TK-1002
SERVIC
AREA
Rev
Sheet
UNIT 40
(t)=
(td =
(b)=
(ki)=
Vapor temp.
Vapor coff.
=at x At =
1397266.4
Btuihr
(Q,) =at x At =
248397.28
&&&
IQJ
R2 "'
11837.6744
Qb + Qs +
Q,
1691759.57
Btuthr
542890.413
----->
Btufhr
136806.8 Kcallhi
2.45 'C
293 ' F-
3.23 kgicrn2 g
45.5136 Ps~g
915.23 Btuirb
----->
838.44 kgihr
Latent heat
Not rnsul roof case
Insulated roof case
593 Ib/hr
-----a
269.06 kglhr
3,
inch
0 1583333 R )
I
Sheet
ITEM
- NO
5340-TK-1052
SERVlC
h, =
15.48
Btu/ftZ.hr.'F
LOCATION
RUWAIS. UAE
AREA
UNIT 40
Project
NO.
Date
3210
09 JUL 99
Sheet
Rev
Calculation
(DOCNO. CA3210-00-PRITEM NO
5340-TK-1002
SERVIC
AREA
UNIT 40
3178-35 ft3ihr
90 m3lhr
0.W9lblft3
Denslty of Air
Speclhc Heat (c,)
Temp Dlff ( tf - t, )
1 27 kgim3
0 46 kcalfkg'C
234 'F
Q=
4.3) Calculat~onof Cod Length
A, =
27124.3 Btulhr
==== >
6835.14 kcallhr
1115,86 ft2
6437 m3
1790 kglm3
0.24 kca1lkg.C
0.1 'C
Del. T to be elevated
5.2) Heat Loss Calculation
Q = 1097384.7 Btulhr
.4282,80 ft2
====
276533.52 kcaVhr
~td.
ITEM NO
5340-TK-2002
SULPHUR STORAGE TANK
--
Sheet
09 JUL 99
LOCATION
RUWAIS UAE
AREA
UNIT 40
6. Conclusion
6.1 Total Heating Coil Length
According to the above calculation result, the length of heating coil is as follows ;
64.90 m
- For heat consumptionto elevate the temperature of stored liquid sulphur by 0.1'C in one hour.
Roof =
Shell =
Bottom =
I000 m
2000 m
1500 m
Rev
NO.
3210
SERVIC
Date
Project
ITEM NO
SERVIC
5340-TK-1002
SULPHUR STORAGE TANK
AREA
UNIT 40
542890.41
Btulhr
27124.30
Btulhr
- For heat consumptionto elevate the temperature of stored liquid sulphur by 0.1'C in one hour.
Q=
1097384.75
Btulhr
QT=
1667399.46
Btulhr
HL=
915.23
Btullb
'1821'84
lblhr
Ws=
826.37
kglhr
Date
ConstntcZim Go, Ltd.
09 JUL 99
3210
ITEM NO.
5330-TK-1003
LOCATION
RUWAIS, UAE
SERVICE
AREA
UNIT 30
Pit data
Inside length
Inside wldth
4.17Ei-08 Whr2
fta
3 20
721
m
ft
2.20
m)
ft
m)
4d0
(
140
Thermal conduct~v~ty
(Kf)
(
lns~dedepth above =
ground
0 19 kcallkg 'C )
26.610 LBtft hr
Viscos~ty, cp X 2 42
Material
Thickness
Conductivit
(
Coff of Vol Expansion
Fouling factor
Conductivity of soil
Liquid sulphur temp ( tf )
12 inch
(
=
(
Thickness of underground(x,,)
wall concrete
Thickness of above ground(x,,)
12 inch )
wall concrete
Thickness of roof concrete(x,) =
0.30
ft
m)
Insulation data
Conductivity of concrete(K,)
304.8 mm {
6 inch
150.24 mm
1 ftZ.hr.'F/ Btu
oam glass
15267
6925
"t
Ib
kg)
hhr
Maximum sulphur
level in pit
Insulation
SK
Engineering&
Constmion &,Ltd.
Calculation
I
project
3210
Sheet
Date
Rev
NO .
09 JUL 99
21 5
ITEM NO.
5330-TK-1003
LOCATION
RUWAIS, UAE
SERVICE
AREA
UNIT 30
23.7 ft2
230.2 Btu 1 hr ,l
Assumed
1,
2.336
I
IIh,
I Calculated
0.230
R,ns
8.4677
(a,>
--
Reit
20.386
Re,
10.688
qef
10.154
51.98 ft2
527.84
Btu 1 hrv/
758.02 Btu 1 h
( 0.6 ,q
,
BtuIhr
--
f ,
2.336
ITEM NO
5330-TK-1003
LOCATION
RUWAIS, UAE
SERVICE
AREA
UNIT 30
--.
tss
244.014
I
1
calculated
t,w
233.68
I
/
1IC,
0.522
ft2.hr.'F IBtu
ft2.hr.'F IBtu
calculated
0.4679
Ratio of above ground side wall area to roof area ( r )
Total heat loss from above ground walls and roof ( Q, + Q, ) =
2285.1 Btu / hr
Btu / hr
ITEM NO,
5330-TK-1003
LOCATION
RUWAIS, UAE
SERVICE
AREA
UNIT 30
'C
338 'F
880.00
kglcm2 g
99.561 Psig
Latent heat
Iblhr
Steam consumption
----->
2,374 inch
0.1978333 ft )
3.2) Inside F
BtulfU.hr.'F
ho
8.65+00
1.91 +01
2.12E+01
19.06
ITEM NO.
5330-TK-1003
LOCATION
RUWAIS, UAE
SERVICE
AREA
UNIT 30
ft3fhr
O.QT9 Ib/ft3
0.46 E3tullb.F
207 'F
Temp. Diff, ( tf - t, )
1)
747.4 Btulhr
--
==== >
1883.5 Kcal / hr
0.48 ft2
5. Conclusion
According to the above calculation result, the length of heating coil is as follows ;
- For heat loss through the floor, roof, underground and above ground walls
LT=
I,PURPOSE
This design guide describes the method of tank heat loss and heatin
2. SCOPE
2 1 Calculation of heat loss from hot surfaces
2.2 Siting of tank heating coil length
3. DESIGN BASIS
3.1 Calculation of heat toss from hot surfaces
3.1.1 Natural Convection at tank outside
For heat toss from surface by natural convection to air at atmospheric pressure and
at ordinary temperatures, the coeRcient is given by the following dimensionat equations
Horizontal Pipes :
Vertical Pfates
a2
P,ject
No,
3210
Date
Sheet
Rev
09JUL99
3/17
Horizontal Plates
Facing Upward :
h, = 0 . 3 8 ~ t ~ . ' ~
Horizontal Plates
Facing Downward:
hc = 02 4t '.'j
Equation (4) can be used for tank heat transfer coefficient by convection.
And in case of considering wind effect, the following equation can be used.
where
I?,,
4
i
I,Y
re
,"
&amtmim6o,lld,
Date
Sheet
09JiJL99
4/17
3210
where,
h,
(BtulFM-hr-"F)
P,,. =
Tv~ical" b value fa
R ~ V
NO.
P1 t- P.?
&d.
ate
street
RW
09JUL99
5/57
NO.
3210
3.1.3 Radiation
For heat loss from surfaces by radiation, the coefficient is given by the following
equations.
where,
hr
(BtufFt2-Hr-"F)
: Surface emissivity
0.8
* Aluminum
0.12
* Aluminum Paint
0.55
* Oxidized Aluminum
0.2
0.6
- 0.6
For heat loss from a flat bottom tank sitting on the ground by conduction, the
coefficient is given by the following equations.
where,
J;?
: Temperature of
K.e
(BtulFt-Hr-' F)
0.2
(DRY SOIL)
%
1.0
(WET SOIL)
where,
ky
X,
Ktm
Constru~mhLzd.
Date
Projmt
No,
3210
03 JUL 39
The overall heat transfer coefficient, ( C ,),for the side of insulated tanks would be
where,
h, = h,
+ h,
rr
tanks
1 0 ~ PO'
'
(ti}-"
GI,- IK)'"
where,
f,
1,
tl heat transfer
(OF)
('F)
: Temperature of vapor
fly = 0 . 5 - ( t j + t R } )
(OF)
cient,
tanks
where,
h, = h,
U,
+ h,
5
h, = 9.686 x
P"[(~~)-"(I,
- IR)02'
where,
f t,
ft.
I,$
(OF)
( O F )
: Temperature of vapor
f f V = 0.5f-bf + t N ) )
(OF)
Date
Stwet
Rev
03 JUL93
8117
Where,
P b
4
4
h, = 0.53-(G,
4,
Where,
I..
P,)
'"
'
ovM.
Project
3220
NO,
G,
: Grashof Number
'r
: Prandtl Number
di
h,
where,
U,
(BtulWr)
: Overall heat transfer coefficient at Coil (Btulft2-Hr-"F)
T,
Ti
A,
ate
Sheet
Rev
09JUL39
$0117
NO.
(DOCNO. CA3210-00-PR-301)
3240
4. CALCUUTION PROCEDURE
The heat transfer quantity Q1 at inside film, Q2 at out ide film, and Q3 through insulation
K,s
X
Tank Fluid
he.
Kt,
~~~~
4
lw
l.
rcc
In this cafculation,
Q2
f%
Galculate hI
k"tn,i
4p SK
akd.
Design Guide
Date
Sheet
09 JULSS
12/17
3210
Using eq*(12)
U,
BtulFt2-
As
Ft2
Q,
Btu/Hr
f~
"F
Q , ~ ~ ( Jt , - Jt o )~
4.2 HEAT LOSS FROM BOTTOM
Assume
tx
BtuiFt-Hr-'F
ga
BtulHr
R ~ V
No.
0
o,ttd.
Project
No.
Calculation
(DOCNO,CA3210-00-PR-301)
3210
Ot
EftulFt2-Mr-"F
Calculate qt = Ut ( ti - ta )
Btul Hr-Ft2
Calculate tf = ti - qwhi
tf
tr = ts
= ta + qt I ho
Try until the assumed values of tf, tr / ts match the calculated values.
Q, = uu:
A,
( i , -t,)
f-l,
BtufXr
Steam condition
Steam Pressure
psia
Steam Temperature
f,
'F
/Z
BtulLb
: Grashof Number
: Diameter of Coil outside (Ft)
Calculate G, ' P,
Check calculation of
t,
Project
No,
Date
3210
09 JUL 99
where,
U,
Th
: Steam temperature
Ti
( O F )
(T)
Date
Sheet
Rev
09 JUL 99
1/16
TABLE OF CONTENTS
3.
DESIGN BASIS
4.
CALCUMTIOM PROCEDURE
5,
---------------------
( 5330..~~-1003
)
5 SWEETS
Design Guide
Project
NO.
Date
3210
09 JUL 99
1. PURPOSE
This design guide describes the method of sulphur day pit & melt pit heat loss and heating coil length calculation
2. SCOPE
3. DESIGN BASIS
-. Floor
-. Side walls below ground level
-. Roof
-. Water Infigration
Sheet
2115
Rev
8SK
Date
Sheet
Rev
No.
Calcuiation
Design Guide
09 JUL 99
3210
3115
311
*,Y" -rr
0 25
h, = 0.45K,
(11
\-
J*
3.1.2
3.1.3
Resistance of insulation
3.1.4
The floor is divided into a center section and into end sections with a length
equal to half the tank width
3.1.5
where
3.1.7
(5)
Red=X4/Ks
(7)
3.1.6
Xaf= r i l 2 ( ~+
~X
, I / 1 2 + 1~6 )
Ltd.
Design Guide
Date
3210
3.2 Heat loss from the underground vertical walls ( Fully sulphur wetted )
3.2.1
The heat loss I unit area from the underground vertical walls decreases with depth
since the soil heat flow path increases for greater depths. The heat loss is calculated
at each foot of depth and the total heat loss from the sidewalls below grade is the
sum of these increments.
The ground path heat flow length for walls at
different depths
3.2.2
Sheet
Rev
NO.
09 JUL 99
5115
Enginewing &
Construction Co,,kd,
Design Guide
3.3
NO.
3210
Date
Sheet
6115
09 JUL 99
Rev
3.3.1
3.3.2
Conductance of air gap between sulphur surface and wall & roof given by
where
C,,,=0.0042twav+0.912
(30)
C,. = 0 . 0 0 4 2 t r a v -t0.912
(31
L=0.5(4, +tJ
(32)
+ tss)
( 33 )
trav
3.3.3
where r is the ratio of the above sulphur side wall area to the roof area
=o.'(tir
Af,,
= q,
C,
(34)
At,
= q r fC,
(35)
QSK
Engrneerin~
&
Constnrction C4L3.d.
Design Guide
Project
NO.
Date
3210
09 JUL 99
Sheet
7115
Rev
3.4 Heat loss due to water infiltration into the pit at the rate of 0.05 gpm per
@vi
for G, P,
<
lo4
for l o 4 .:G , P ,
for G;P,
.:109
> 109
Where,
G,
4, CAtCUUTfON PROCEDURE
: Prandtl Number
( 38
QSK
m~neeri~lg
&
Construction Co,,Ltd.
Design Guide
Project
NO.
Date
3210
09 JUL 99
l i f
Calculate
&,,
Calculate
Rtn8
Calculate
cd
Calculate
e d
Assume
!I
t , $
Calculate
Try till
Assume
Calculate
t~
Calculate
ef
At3 = %,
ih.5
Calculate
Try till
Sheet
8115
Rev
Q SK
Engrneenng&
Construction Co,,Ltd.
Design Guide
I
Coil Length
Calculation
(Doc No. CA3210-00-PR304)
Date
09 JUL 99
Calculate
lef
Qf
Btuihr
Sheet
9/15
Rev
Calculation
Calculate
R,,
Rim
Calculate
( Using eq. (3))
Assume
Calculate
..,
;Y uw a?-zdR
Calculate
PW
ft2-hr-olBtu
ft2-hr-olBtu
Calculate
and 4
u,,
w
,
.,
calculate
bS
=qu,/hs
tt,
Calculate
uw
f2
rn
Btulhr
Construction Ca,Ltd.
Project
NO.
Date
Sheet
3210
09 JUL 99
11 / 15
Calculate
t s
1 I h ,
Calculate
I?
ft2-hr-u/Btu
f i w
K3
Calculate
( Using eq. (3))
1 1h
Assume
Gw
1 /Cw
Calculate
Calculate
At, = t ,
-r,
=q,
/hs
and
QSK
Eng~neenng&
Constmion Co, Ltd.
Design Guide
Project
No.
Date
Sheet
Rev
3210
09 JUL 99
12115
Calculate
1 l h
ft2-hr-alBtu
1 ,
caicuiate
( Using eq. (29))
Calculate
'im
1 1h
Assume
ar
7',
Calculate
Btulft2-hr
Calculate
t, -ti, = q , / C ,
=
"or
A t
/'or
LA
tar
il
calculate
G? w
G? r
and
Btulhr
Calculate
( Using eq. (38))
wz
Btulhr
QSK
Enginewing &
Constmtim Co.,Ltd,
Design Guide
Project
NO.
Date
Sheet
Rev
3210
09 JUL 99
13115
nZ
Btulhr
I!
LIP
Btulhr
Caicuiate
e m
Mp
em
Btulhr
psia
Lblhr
Steam Temperature
Latent heat of steam
Calculate Steam consumption
Project
NO.
3210
Assume t,
Gaiculate G,
Calcufate G, P,
Gr
: Grashof Number
: Prandtf Number
Sheet
Rev
Check calculation of t ,
Try again until the calculated value oft, matches with the assumed.
Overall heat transfer coefficient
where,
UC
Th
Ti
(Btuihr)
to)