BHAGYANAGAR GAS LIMITED

(A JOINT VENTURE OF HPCL & GAIL)

CNG & CITY GAS DISTRIBUTION PROJECT AT


KAKINADA

ADDENDUM-I
For
BID DOCUMENT FOR

LAYING & CONSTRUCTION OF 10”- 46Km , 6” - 19 Km


& 4” NB - 10 Km U/G STEEL P/L NETWORK &
ASSOCIATED WORKS IN KAKINADA CITY

Bid Document No.: 05/51/23LZ/BGL-KAKI/001-i)

PREPARED AND ISSUED BY


MECON LIMITED
(A Govt. of India Undertaking)
Delhi, India

1
ADDENDUM #1
Date : 13.04.2010
LAYING & CONSTRUCTION OF 10”- 46Km , 6” - 19 Km & 4” NB - 10 Km U/G STEEL P/L NETWORK & ASSOCIATED WORKS IN KAKINADA
Tender Document No. 05/51/23LZ/BGL-KAKI/001-i)
CITY
FOR
MECON LIMITED
CNG & CITY GAS DISTRIBUTION PROJECT AT KAKINADA
Owner : BHAGYANAGAR GAS LIMITED

Clause /
Sl. Tender Page
Description Volume Para / Amendment / Addition / Modification / Deletion Remarks
No. No.
Section
1.0 Annexure-I to IFB Vol I of III 9 5.2.2.2 Modification The table stands mofiied to the following extent

Sl. No. Group Minimum Annual Turnover Requirment

For Indian Bidders


(in INR)
1 Total Package basis 5.75 crores (each partner)

9.0 Schedule of Rates (SOR) Vol I of III 316 to 348 10 Modification The revised Schedule of Rate is attached as Annexure - 1 to this Addendum.

For and on Behalf of Bhagyanagar Gas Limited

S. S. Roy
DGM I/c (Contracts)
MECON, Delhi

Page 1 of 1
2
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
1.0 CARBON STEEL PIPES
1.1 PIPELINE LAYING / INSTALLATION in normal surface/ unprepared surface built up
surface / hard surface.
"Receiving and taking over" as defined in the specifications, handing, loading, transportation
and unloading of Owner supplied 3-Layer PE coated and bare linepipes from Owner's
designated stack-yard to Contractor's stock yard/workshop/work-site including preliminary
activities, preparation of drawings, wherever required for crossing etc. including handling,
stacking, stringing on the pipeline Right-of-Use/ pipeline route alignment, carrying out
inspection of company supplied materials including linepipes at the time of taking over, laying/
installation of coated linepipes, associated burried valves, barred tees, insulating joints,
flanges & fittings of all sizes, thickness & ANSI class rating and accessories as per
specification wherever required depending on site condition including execution of all works,
"taking over", handling , including loading and unloading, transportation of Owner supplied
materials other than linepipe from Owner's designated place (s) of issue to work site,
additional lands required for Contractor's storage, fabrication, access for construction,
procurement and supply of all materials (except Owner supplied materials), consumables,
equipment, labour and other inputs, carrying out all temporary, ancillary, auxiliary works,
ready for commissioning of pipeline as per drawings, specifications, other provisions of
Contract document and instructions of Engineer-in-charge, including but not limited to carrying
out the following works:
- Surveying of route and detours required at the time of execution including marking the same in
topographical sheet, preparation of construction drawings showing survey details, and submit
same to Owner for review / approval.
- Staking and installation of construction markers, clearing, fencing, grubbing, cutting of trees,
full filling all the requirements of various statutory/ environment authorities to the entire
satisfaction of concerned authorities, grading of work area. Shifting of all obstruction within the
ROU/ Pipeline route alignment viz. electrical lines/ poles, telephone line / poles, etc. co-
ordination with concerned authorities and obtain permissions from these authorities.
- Barricading the pipeline construction area prior to execution of the works as per
drawing no. MEC/23LZ/05/21/M/000/0004 enclosed with tender document and to the
entire satisfaction of Owner / Engineer-in-charge.

3
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 1 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
- Trenching to all depths by excavation in all types of soils including soft/ hard rock and
different type of pavement / footpath / roads etc. including rock breaking, chiselling or
otherwise cutting etc. as required and storing excavated soil, reusable materials at
designated area as directed by Engineer in charge and to a width to accommodate the pipeline
and HDPE conduit for OFC as per the relevant standard/ specification etc. [The minimum
depth of the top of pipeline shall be 1.0m measured from top of pipeline coating to the top of
undisturbed surface of the soil or as per SCC/ OISD - 226, whichever is higher]. Dewater of
trenches if required as per site condition.
- Carrying out repairs of pipe defects/ replacement in case of irreparable defects and repairs of
defects of pipe coating not attributable to Owner including defects/ damages occurring during
transportation / handling.
- Stringing of line pipes along pipeline trench / ROU on straw / sand / soft soil bags including
supply of bags and its filling materials.
- Checking, cleaning, aligning, bending, cutting and bevelling (as required) of pipes for welding
and field adjustments including pipe fittings, welding, carrying out non-destructive testing of
welds as required including 100% radiography by X-ray and providing all requisite equipment,
labour, supervision, materials, films, consumables, all facilities and personnel to process,
develop, examine and interpret radiographs and other tests as required, carrying out repairs of
weld joints found defective by Engineer-in-Charge, carrying out re-radiography and other tests
as required on repaired joints.
- Carrying out installation of carrier line pipe at all minor crossing viz. road, carttrack, pathway,
water bodies etc. at designated depth by open cut (except at crossing by HDD method).
- Carrying out installation of carrier line pipe in the casing pipe at cased crossing (excluding
installation of casing pipes which is covered separately).
Installation of LR Bends where ever required.
- Coating of field weld joints, long radius bends (R=3D), elbows, buried fittings and valves etc.
including supply of coating materials etc. (i.e. heat shrinkable sleeves and high build epoxy
etc.) as per PJS & Technical Specification compatible with 3 layer PE coating material of the
line pipe.
- Counting the number and type of trees cut in presence of DFO/concerned authorities and
keeping record thereof, stacking and handing over of all cut tress.

4
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 2 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
- Installation / lowering the pipeline in trench to required depth as per PJS, Technical
Specification & drawings, supply & placement of 1.0mm thk. & Pipe dia plus 300mm width
HDPE Yellow colour warning mat over the pipeline & HDPE duct in same trench along the
complete route as per standard drawings, data sheets & technical specifications, padding
around pipeline as per Standard Drg. no. MEC/SD/05/21/PL/WS-001/004 including supply of
suitable padding material duly approved by EIC , backfilling to its original condition with
excavated earth / borrowed select soil duly approved by EIC & its compaction &
crowning. At certain specific area of ROU, trench shall be backfilled & compacted and
shall be made ready for restoration & their Restoration shall be carried as per separate
SOR item mentioned elsewhere in the SOR or to be done by Owner / concerned
authorities.
- Supply and installation of slope breakers, wherever required or, as directed by Onwer /
Engineer–in–charge.
- Supply and installation of bank protection alongwith backfill materials duly approved by EIC for
pipeline trench and banks falls under minor water body crossing as per technical specification
& Std. Drg. No. MEC/23LZ/05/11/C/001/0001, wherever required or, as directed by Onwer /
EIC.
- Training and diversions of streams in steep slope area, wherever required.
- Carrying out air cleaning, pigging, flushing, cleaning and hydrostatic testing of complete
pipeline with required quantity of corrosion inhibitor including pre-testing of designated
sections complete as per specification and approved by Engineer–in–charge to specified
pressures indicated elsewhere and duration after stabilization as per specification, providing all
equipment, pumps, fittings, instruments, dead weight tester, pressure recorder, thermocouples
etc., and services, supervision, labour, consumables, water including supply of corrosion
inhibitor, air, etc. as required, locating of leaks and rectification of defect attributable to
Contractor (rectification of defects in linepipe material not attributable to contractor shall be
paid separately as per other item of schedule of rate), re-testing after rectification, dewatering
after successful completion of hydrotesting of entire section and as approved by Engineer-in-
- All tieing-in, including the tie-in(s) of the pipeline with the adjacent sections of pipeline
including cutting of test header, rebevelling as required, radiography and other NDT
examination, joint coating as per specification.
- Final clean-up of right-of-use or area disturbed by contractor during their construction activities
for laying of pipeline works and disposal of debris and surplus material to designated disposal
areas and backfilling of trench and compaction of the same as per satisfaction of Owner and /
Or as directed by Engineer–in–charge.
- Installation of all burried valves (except extended stem valves) inside the valve pit and making
provision to operate the valve.

5
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 3 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
- Liasioning & follow up for Permission with all the concerned authorities & boards viz
Railways, NH, R&B, Local Municipal, Panchyat, Electricity, REC, RES, Sewage water,
Drinking water, Forest, Social Forestry, Owners of OFC, Traffic, Law & Order, Fire
Brigade etc. for entire pipeline length and associated terminals alongwith associated
work as per tender.
- Preparation of as-built drawings, pipe-books (1 set of tracing on polyester film and 6 sets of as-
built drawings and 1 soft copy and 6 hard copies of pipe book) All the works shall be executed
in accordance with the provision of contract including carrying out all temporary/ ancillary/
auxiliary works required for the performance of the works and all other acts, deeds, matters
and things necessary to make the pipeline ready for precommissioning activities.
Specified dia Thk (mm) Material Coating Type Length of each pipe
(inches) NB
1.1.1 10" 6.4 API 5L Gr. X-42 3 Layer PE Double random Meter 46000
Coating (Externally) (approx. 11.5 m to 12.5 m)
1.1.2 6" 6.4 API 5L Gr. B 3 Layer PE Double random Meter 19000
Coating (Externally) (approx. 11.5 m to 12.5 m)
1.1.3 4" 6.4 API 5L Gr. B 3 Layer PE Double random Meter 10000
Coating (Externally) (approx. 11.5 m to 12.5 m)

Note:
i) This item shall be applicable for the underground steel grid main pipeline & branch pipeline
including tap-off for distribution pipelines, OLS, DRS, MS etc.along with installation of
necessary valves, insulating joints, bends (R=3D), flanges & fittings, accessories etc. and
aboveground approach pipeline upto Insulating Joint (excluding installation of aboveground
insulating joint) for various stations.
ii) Contractor shall not perform any pipeline activities along ROU without specified
barricading as per Drg. No. MEC/23LZ/05/21/M/000/0004 and other safety measures. In
case contractor does not provide specified barricading, Owner will levy penalty at 5%
of the pipeline laying running meter rate, for the relevant section of the pipeline apart
from other actions as per contract.
iii) Items except above are covered separately. The lengths of pipelines are tentative.
iv) For restoration of asphalt / concrete roads, the item for construction of asphall top / concrete
top / red stone / paver shall be paid separately as per the rates quoted for the same elsewhere
in the SOR.

6
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 4 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
2.0 RESTORATION
2.1 Restoration of asphalt / concrete / red stone roads / pavement including compaction of soil, to
original condition as per requirement and to the entire satisfaction of EIC and / or concerned
Owners having jurisdiction for following thickness.
2.1.1 Restoration of Asphalt road upto 10 cm thickness Sq. metre 100

2.1.2 Restoration of Asphalt road beyond 10 cm upto 20 cm thickness Sq. metre 100

2.1.3 Restoration of Concrete road upto 10 cm thickness Sq. metre 150

2.1.4 Restoration of red stone road / footpath / pavement upto 4 cm thickness Sq. metre 150

2.1.5 Restoration of Paver block Sq. metre 150

3.0 CONTINUOUS CONCRETE COATING (FOR CS PIPES)


3.1 Supply of all consumables, materials and application of 80mm thk continuous concrete weight
coating of minimum density 2245 kg/m3 of mininum grade M-20 (nominal mix) and field joints
thereof in all areas of work wherever required as per site condition and performing all works as
per specification on the line pipe for following sizes :-
3.1.1 10" NB x 6.4 mm W.T. Meter 36
3.1.2 6" NB x 6.4 mm W.T. Meter 45
3.1.3 4" NB x 6.4 mm W.T. Meter 60
4.0 CONCRETE SADDLE WEIGHTS(Precast/Cast in situ)
4.1 Unit rate for additional works over and above item no. 1.0 for supply of all consumables and
materials including supply of 3mm, HDPE sheets, fabrication and installation of concrete
saddle weights on pipeline and performing all works as per specifications, drawings, and
instructions of Engineer-in-charge and other provisions of the Contract document.
4.1.1 Specified 10"NB x 6.4 mm W.T. Nos. 10
4.1.2 Specified 6" NB x 6.4 mm W.T. Nos. 10
4.1.3 Specified 4" NB x 6.4 mm W.T. Nos. 10

7
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 5 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
5.0 MAJOR CASED Crossing
5.1 Complete work of the rail crossing (between the limits as defined in approved drawings)
excluding supply of casing pipe (for 10" NB & 6" NB Pipeline) & Bare CS conduit of size
150mm x 6.4mm thk (for OFC / HDPE duct) confirming to API 5L Gr. B / IS : 3589 or
equivalent ERW pipe alongwith handling, loading, transportation, unloading to Contractor's
own stock yard/ work site.
Pre-construction survey and making of crossing drawing based on site visit and getting their
approval from concerned Authority/ Engineer-in-charge prior to start the execution of work.
Installation of casing pipe by jacking/ boring/ for rail crossings in all type of soil strata including
soft / hard rock and open cut for adjacent service road, canal, minor nature of water channel,
utility line crossing etc. (if any) wherever required for all depth in all type of soils and terrrain
for carrier pipe insertion and for OFC/ HDPE duct. All other Contractor supplied materials like
casing insulators, Zinc Ribbon Anodes and casing end seals as per enclosed specification/
drawings materials for casing vents and drain assembly etc. including supply of all other
materials, equipments, consumables, manpower, welding including visual inspection of all
weld joints.
Preparation of required length of carrier pipeline welded string including all other works as
mentioned in item no. 1.0 above and as per specification/ drawings. Pulling of OFC/ HDPE
duct through CS conduit & insertion of carrier pipe in casing pipe after above ground
pretesting at specified test pressure including installation of casing insulators and Zn ribbon
anode as per approved design calculation, specification/ drawings. Insatllation of vent and
drain assembly, fixing of end seals, backfilling and restoration as original of the facilities
crossed and performing all other works including pigging, cleaning, final hydrotesting etc.
alongwith mainline works (as mentioned in item no. 1.0 above) and as per specification,
approved procedure, drawing etc. and instruction of Engineer-in-charge and provision of
contract document, getting NOC from all concerned Authority of the facilities crossed.
Details of X-ings
5.1.1 Madhavapatinam Railway Line at chainage approx. 4.3 km in the sarpavaram to peddapuram
section

a) By Jacking/ Boring of Casing Pipe - 16" NB, mm wall thk. (for 10" NB pipeline) M 35

b) By Jacking/ Boring of CS Conduit 150mm NB, 6.4mm wall thk. (for OFC & their conduit) M 35

8
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 6 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
5.1.2 Samalkot Railway crossing at chainage apprx. 11.1 Km in the sarpavaram to peddapuram
section

a) By Jacking/ Boring of Casing Pipe - 12" NB, mm wall thk. (for 6" NB pipeline) M 65

b) By Jacking/ Boring of CS Conduit 150mm NB, 6.4mm wall thk. (for OFC & their conduit) M 65

5.1.3 Railway crossing at chainage approx. 11.93 km in the sarpavaram to pithapuram section

a) By Jacking/ Boring of Casing Pipe - 12" NB, mm wall thk. (for 6" NB pipeline) M 35

b) By Jacking/ Boring of CS Conduit 150mm NB, 6.4mm wall thk. (for OFC & their conduit) M 35

5.1.4 Railway crossing at chainage approx. 2.06 km in the Bhanugudi to Zillaparisad section

a) By Jacking/ Boring of Casing Pipe - 16" NB, mm wall thk. (for 10" NB pipeline) M 20

b) By Jacking/ Boring of CS Conduit 150mm NB, 6.4mm wall thk. (for OFC & their conduit) M 20

5.1.5 Other unspecified cased crossing

a) By Jacking/ Boring of Casing Pipe - 16" NB, mm wall thk. (for 10" NB pipeline) M 60

b) By Jacking/ Boring of Casing Pipe - 12" NB, mm wall thk. (for 6" NB pipeline) M 25

c) By Jacking/ Boring of Casing Pipe - 10" NB, mm wall thk. (for 4" NB pipeline) M 25

d) By Jacking/ Boring of CS Conduit 150mm NB, 6.4mm wall thk. (for OFC & their conduit) M 110

5.1.6 Cased crossing by Open cut method

a) By Open Cut of Casing Pipe - 16" NB, mm wall thk. (for 10" NB pipeline) M 40

b) By Open Cut of Casing Pipe - 12" NB, mm wall thk. (for 6" NB pipeline) M 40

9
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 7 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)

c) By Open Cut of Casing Pipe - 10" NB, mm wall thk. (for 4" NB pipeline) M 10

d) By Open Cut of CS Conduit 150mm NB, 6.4mm wall thk. (for OFC & their conduit) M 90

Note: (i) Actual length & cover from top of casing pipe string may vary depending upon site
conditions, approved drawings, specification etc. and / or as decided by concerned Authority /
Engineer-in-charge.
(ii) Exact centreline location of boring of 6" NB CS conduit as a casing pipe shall be minimum
4.0m or as per available ROU either side based on as installed centreline dimension of carrier
pipe inside casing pipe at all cased crossing. The cover to top of casing pipe for cable conduit
shall be same as cover to top of the pipeline/ casing pipe as applicable.
(iii) Payment for supply & installation of Zinc ribbon anode and its design excluded from above
item and covered elsewhere in the SOR.
(iv) Payment for the length carrier pipeline string inserted in casing pipe laid by Boring are
covered separately and shall be paid under other items mentioned elesewhere in the SOR.
(v) Width of above crossings indicated are tentative. The width indicated in SOR item 5.1.5 &
5.1.6 are not for any single crossings. This shall be as per requirement at site for crossings at
different locations.
6.0 Supply of Casing Pipe
6.1 Supply of following casing pipe including handling, loading, transportation & unloading etc. to
contractor's own stock yard / worksite(s).

6.1.1 Supply of Casing Pipe - size 16" NB, mm wall thk. of material API 5L Gr. B / IS : 3589 or M 90
equivalent ERW Pipe (for 10" NB pipeline) duly Corrosion coated of High build epoxy of
minimum 450 microns thickness.
6.1.2 Supply of Casing Pipe - size 12" NB, mm wall thk. of material API 5L Gr. B / IS : 3589 or M 120
equivalent ERW Pipe (for 6" NB pipeline) duly Corrosion coated of High build epoxy of
minimum 450 microns thickness.
6.1.3 Supply of Casing Pipe - size 10" NB, mm wall thk. of material API 5L Gr. B / IS : 3589 or M 25
equivalent ERW Pipe (for 4" NB pipeline) duly Corrosion coated of High build epoxy of
minimum 450 microns thickness.
6.1.4 Supply of CS Conduit 150mm NB, 6.4mm wall thk. API 5L Gr. B / IS : 3589 or equivalent ERW M 235
Pipe (for OFC & their conduit) duly Corrosion coated of High build epoxy of minimum 450
microns thickness.

10
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 8 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
7.0 ROAD CROSSING BY HDD
7.1 Complete work of the road crossing (between the limits are defined as approved drawings) by
HDD method including "Receiving and taking over" owner supplied three layer PE coated line
pipes from Owner's designated place to issue/ dump site(s) and transportation to Contractor's
stock yard/ work shop/ work site including all handling loading, unloading, aligning etc. supply
of all Contractor supplied material including required length of CS conduit duly Corrosion
coated of High build epoxy of minimum 450 microns thk duly for OFC laying of size 150mm
NB; 6.4mm thk. of API 5L Gr. B / IS : 3589 or equivalent ERW pipe to work site(s), manpower,
equipment, other resources and aquiring the required land for storage, fabrication inclduing
string preparation of pipes, welding, welding repair, radiography, coating of field joints with
special type Heat Shrink Sleeve and repair of pipeline coating with special repair patch
materials as per
specification, pre-testing etc. of complete string made for crossing access for Contractor etc.
and execution of, but not limited to, following works in accordance with specifications and
instruction of Engineer-in-charge and as per all provision of Contract Document.
Pre-construction survey based on site visit, collection of data (if required) from concerned
Authority including design and detail engineering and making of crossing drawings for getting
their approval from concerned Authority/ Engineer-in-charge, getting work permit/ NOC for
road crossing as well as utility crossings (if any) encountered during road crossing prior to start
the execution of work.

Directional drilling to required depth from top of road including maintenance of drill hole in all
types of strata including rocky terrain at all depth to accommodate the pipeline and CS conduit
for OFC laying at all conditions encountered during rail/ road crossing by approved HDD
methods for providing minimum cover specified in code/ specification or the actual depth as
decided by concerned authority, whichever is more.

Backfilling of the ditch/ trench including restoration and cleanup of area and all other works
including pigging, cleaning, final hydrotesting etc. alongwith mainline works (as mentioned in
item no. 1.0 above) required as per specification, approved drawings, calculations, methods
and to the satisfaction of Engineer-in-charge and/or as directed by concerned Authority.
Details of Road Crossing
Road Crossings at various locations as decided by EIC at site as per concerned authority
requirement.
7.1.1 Line pipe detail 10" NB, 6.4 mm thk API 5L X 42 pipe, C.S. conduit 6"NB, 6.4mm thk of API 5L Meter 80
Gr. B / IS: 3589 / or equivlent ERW pipe)
7.1.2 Line pipe detail 6" NB, 6.4 mm thk API 5L X42 pipe, C.S. conduit 6"NB, 6.4mm thk of API 5L Meter 60
Gr. B / IS: 3589 / or equivlent ERW pipe)

11
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 9 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
7.1.3 Line pipe detail 4" NB, 6.4 mm thk API 5L X42 pipe, C.S. conduit 6"NB, 6.4mm thk of API 5L Meter 60
Gr. B / IS: 3589 / or equivlent ERW pipe)
Note: (i) Crossing width may vary as per site condition. Tenderer are advised to visit site for
actual assessment of extent of crossing. Actual string length for HDD shall be as per design
calculations so that pipe is not under stress as permitted by codes/ specifications. However
final length of string & cover from top of pipe shall be decided by concerned Authority/
Engineer-in-charge.
(ii) Payment for the length of final tied-in carrier pipeline string with mainline and CS conduit
made for crossing laid by HDD method are inclusive in the above item rate and no separate
payment shall be made under other item mentioned elsewhere.
(iii) The Contractor has to quote alongwith 6" CS conduit. No any extra payment shall be
made against this item. It is sole descretion of the Contractor to do HDD crossing of mainline
pipe as well as CS conduit pipe either by suitabily strapping together both the carrier pipe &
CS conduit and pulled through the same drill hole. or making separate HDD for 6" CS conduit
for OFC laying at minimum 4m distance apart from centreline of HDD of mainline either side.
No separate payment for HDD for 6" Dia CS conduit shall be paid.
(iv) Width of above crossings indicated are tentative. The width indicated are not for any single
crossings. This shall be as per requirement at site for crossings at different locations.
8.0 WATER BODY CROSSINGS BY HDD METHOD
8.1 Complete work of the water crossings i.e. Canal / Nala / Drain / Pond etc. (between the limits
as defined in approved drawing) by Horizontal Directional Drilling (HDD) method including
"Receiving and taking over" owner supplied three layer PE coated line pipes from owner's
designated places of issue/ dump site(s) and transportation to Contractor's stock yard/ work
shop/ worksite including all handling, loading, unloading, aligning etc. supply of all Contractor
supplied material including required length of CS conduit of size 150mm NB, 6.4mm thick. of
API - 5L Gr. B / IS : 3589 or equivalent ERW Pipe duly Corrosion coated of High build epoxy
of minimum 450 microns thk for OFC laying works site(s)manpower, equipments, other
resources and acquiring the required land for storage, fabrication, access for Contractor etc.
and execution of, but not limited to, following works in accordance with specifications scope of
work and instructions of Engineer-in-charge and as per all provision of Contract Document.
- Pre-construction surveys based on site visit, collection of historical data from irrigation/
concerned department including design & calculation and detail engineering and making of
crossing drawing for getting their approval from concerned Authority/ Engineer-in-charge,
getting work permit/ NOC for water crossings/ road crossings as well as utility crossings (if
any) encountered during crossing prior to start the execution of work.

12
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 10 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
- In case of water crossing, drilling to the required depth on the banks and bed including
maintenance of drill hole in all types of soil strata including soft / hard rock, all depth to
accommodate the pipeline and CS conduit for OFC laying at all conditions of the water
crossings by HDD methods for providing with minimum cover over top of the pipe at all point
across the maximum possible width of water bed (as per drawing) either 1.5 mtrs. below the
predicted scour profile expected during the life time of the pipeline or 2.5 mtrs. below the
available lowest firm bed (if scour profile/ depth not available) of the water crossing by
ascertaining bed level upto 50 mtrs. both the side from crossing location or the actual depth as
decided by concerned Authority/ Engineer-in-charge whichever is more.
- Laying of the pipeline by the approved HDD method across the crossing including, strings
preparation of pipes, welding, testing, radiography, welding repair and retest, coating of field
joints with special type Dirax Heat Shrink Sleeve or equivalent and repair of pipeline coating
with special PERP-80 repair patch or equivalent material as per specification, pre-hydrotest of
complete strings made for crossing etc.

- Backfilling of the ditch/ trench including restoration and clean-up of area etc. to the satisfaction
of Engineer-in-charge/ Concerned Authority.

- Post installation hydrotest dewatering and tie-in with pipeline at either banks etc.

- All other works including pigging, cleaning, final hydrotesting etc. alongwith mainline works (as
mentioned in item no. 1.0 above) required as per specifications, codes, approved drawings,
calculations, methods and as directed by Engineer-in-charge.

8.1.1 Crossing of other water/ canal/ nallah/ drain/ channel crossings by carrier pipeline of size 10" Mtrs. 100
NB x 6.4 / 9.5 mm thk. of API 5L X42 and CS conduit of 6" NB x 6.4mm thick. of API 5L Gr. B
or equivalent ERW Pipe for cable Conduit.
8.1.2 Crossing of other water/ canal/ nallah/ drain/ channel crossings by carrier pipeline of size 6" Mtrs. 120
NB x 6.4 / 9.5 mm thk. of API 5L X42 and CS conduit of 6" NB x 6.4mm thick. of API 5L Gr. B
or equivalent ERW Pipe for cable Conduit.
8.1.3 Crossing of other water/ canal/ nallah/ drain/ channel crossings by carrier pipeline of size 4" Mtrs. 100
NB x 6.4 / 9.5 mm thk. of API 5L X42 and CS conduit of 6" NB x 6.4mm thick. of API 5L Gr. B
or equivalent ERW Pipe for cable Conduit.

13
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 11 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
Note: (i) Crossing width may vary as per site condition. Actual string length for HDD shall vary
as per design calculations so that pipe is not under stress as permitted by codes/
specifications. However final length of string & cover from top of pipe shall be decided by
concerned Authority/ Engineer-in-charge.
(ii) Payment for the length of final tied-in carrier pipeline string with mainline and CS conduit
made for crossing laid by HDD method are inclusive in the above item rate and no separate
payment shall be made under other item mentioned elsewhere.
(iii) The Contractor has to quote alongwith 6" CS conduit. No any extra payment shall be
made against this item. It is sole descretion of the Contractor to do HDD crossing of mainline
pipe as well as CS conduit pipe either by suitabily strapping together both the carrier pipe &
CS conduit and pulled through the same drill hole. or making separate HDD for 6" CS conduit
for OFC laying at minimum 4m distance apart from centreline of HDD of mainline either side.
No separate payment for HDD for 6" CS conduit shall be paid.
(iv) Width of above crossings indicated are tentative. The width indicated are not for any single
crossings. This shall be as per requirement at site for crossing at different locations.
9.0 Excavation of hard rock
9.1 Excavation of hard rock wherever hard rock of single piece exceeding 1.0 m in length Cub.m 10
removable by pneumatic chisel/ drill as per direction of EIC.

10.0 REPAIR OF DEFECT IN PIPES (NOT ATTRIBUTED TO CONTRACTOR)


10.1 Repair of defects on Owner supplied linepipes of all grades and wall thickness as specified in
following items, noted and recorded at the time of "receiving and taking over" by Contractor in
the presence of Engineer-in-charge.
10.1.1 Cutting and rebevelling for dents in bevels exceeding 3 mm in depth for pipe sizes:
10.1.1.a Specified OD 10" Nos. 10
10.1.1.b Specified OD 6" Nos. 10
10.1.1.c Specified OD 4" Nos. 10
10.1.2 Jack out of dents in bevels ranging between 1.5 mm and 4 mm in depth for pipe sizes:
10.1.2.a Specified OD 10" Nos. 10
10.1.2.b Specified OD 6" Nos. 10
10.1.2.c Specified OD 4" Nos. 10

14
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 12 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
11.0 REPAIR OF COATING DEFECTS (NOT ATTRIBUTED TO CONTRACTOR)
11.1 Repair of Holiday in Coating (Noted and recorded at the time of "receiving and taking
over")
Supply of all coating repair materials as per requirements of specification to be compatible with Sq. cm 100
line pipe coating material, supply of all consumables, utilities, equipments and all manpower
required, pipe cleaning and surface preparation, repairing of coating defects (resulting in
holiday) and testing including all handling, transportation, etc. for line pipes, performing all
works necessary for the completion of the works stirctly in accordance with relevant
specification and instructions of Engineer-In-Charge. This rate shall be applicable per sq. cm
of the exposed steel area exposed steel area.
12.0 PERMANENT MARKERS
12.1 Supply, fabrication and installation of all types of permanent markers along the route including
all associated civil works such as excavation in all types of soil, construction in all types of soil,
construction of pedestals and grouting with concrete, clearing, supply and application of
approved colour and quality of primer and paint, stencil letter cutting for numbers, direction,
change etc., restoration of area to original condition and performing all works as per drawing,
specification and instruction of engineer-in-charge.
12.1.1 Pipeline RCC boundary / route marker as per drawing Nos. 1500

12.1.2 Pipeline warning markers / Direction marker with post & foundations Nos. 330

12.1.3 Pipeline KM with post & foundations Nos. 75

12.1.4 Pipeline Arial marker Nos. 10


13.0 LEAK / BURST (ATTRIBUTABLE TO OWNER)
13.1 All works for locating leak / burst in Company's supplied material only (occurred during hydro-
static testing) including necessary repairing/replacing defective pipe lengths including cutting
and out and removing the defective pipe, pre-testing and welding of replacement pipe, NDT of
welds, repair and retesting of defective welds, coating/painting of replacement pipe, pretesting
the replacement pipe into mainline/branch line, coating/painting of welding joints, cleanup,
retesting including cost of all labour materials, consumables and performing all works in
accordance with the provisions of the Contract document and as directed by Owner /Engineer-
in-charge/ Engineer in-charge
13.1.1 For 10" NB Line Lumpsum 1
13.1.2 For 6" NB Line Lumpsum 1
13.1.3 For 4" NB Line Lumpsum 1

15
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 13 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
Note:
i) This rate is applicable for manufacturing defects in Owner supplied material only.
ii) Leak detection, its rectification and successfully re-hydrotesting shall be carried out as per
approved procedure by Contractor with a view that completion of all activity for successful
hydrotesting is not inordinalely extended which will hamper the overall project schedule.
14.0 PRE-COMMISSIONING AND ASSISTANCE IN COMMISSIONING OF PIPELINE SYSTEM
14.1 Swabbing, drying, purging with nitrogen of the complete pipeline network and the associated
facilities being installed to the specified acceptance criteria, carrying out pre-commissioning
works, providing assistance during the complete duration of commissioning operations for
entire pipeline network system including supply of all equipment, man-power, consumables
(including pigs & nitrogen required for purging with maintaining nitrogen column of mininum
10% of pipeline geometric volume) materials for all temporary works and performing all
associated works, complete as per the relevant specifications, other provisions of Contract
document and instructions of Engineer-in-charge.
14.1.1 For 10" NB Line Meter 46000
14.1.2 For 6" NB Line Meter 19000
14.1.3 For 4" NB Line Meter 10000
15.0 IDLE TIME PRESERVATION OF PIPELINE
15.1 Preservation of complete pipeline and associated facilities forming part of the pipeline as per
Bid document and its maintenance including supply of all consumables, all equipment, man-
power, etc. complete as per the requirements of specifications, other provisions of Contract
document and instructions of Engineer-in-charge.
Note : Owner reserves the right to exercise either or none of the rates below.
15.1.1 By filling and pressurizing with nitrogen to a pressure of 2 bar(g) for a period of 3 months.

15.1.1.a For 10" NB Pipeline Meter 46000


15.1.1.b For 6" NB Pipeline Meter 19000
15.1.1.c For 4" NB Pipeline Meter 10000
15.1.2 For every additional period of three month or part thereof

15.1.2.a For 10" NB Pipeline Meter 46000


15.1.2.b For 6" NB Pipeline Meter 19000
15.1.2.c For 4" NB Pipeline Meter 10000

16
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 14 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
16.0 PIPING WORKS FOR SECTIONALISING VALVE STATION-CUM-TAP-OFF POINT
16.1 All works for fabriaction and installation of all piping above ground at all elevations and below
ground at all depth for Sectionalising Valve Station alongwith preparation of construction
drawings duly approved by EIC, in all type of terrains and soils including transportation and
handling of all Owner supplied materials and contractor supplied materials as per PMS,
respective data sheet and TS (payment for contractor supplied shall be made as per separate
item mentioned elsever in SOR) i.e. extended stem butt welded sectionalising ball valve,
other types of valves, Barred Tee,line pipes for mainline, Only 4" NB pipe for all branch line
including ventlines from Owner's designated place(s) of issue to work site. Contractor shall
supply of all consumables, manpower, machinaries, materials etc. and carrying out all
mechanical works of underground and above ground piping including fabrication, welding,
nondestructive testing of welds, weld repairs/ retesting, cleaning/ flushing, pre-hydrotesting &
hydrostatic testing,
dewatering, functional testing, cutting of mainline and bevelling (if required), tie-in of valve
assembly, including radiography of tie-in joints, corrosion, coating and external painting as
required, installation of instruments like pressure/ temperature instruments/ gauges alongwith
complete SS Tubing works including supply of SS Tube and thier accessories etc., as
required, obtaining all statutory clearances, approvals and permissions for the works
(wherever required), making of valve pit (for detail refer relevant drawings. Also refer note-iii)
for SV Stations-cum-tap-off points enclosed with tender filled with sand, excavation and filling
in all types of soils including soft/ hard rock for installation of piping/ pipe supports providing
pipe supports, area fencing and gate including all associated civil and structural works;
painting, finishing, clean-up and restoration of site; preparation of as-built drawings,
documents and project records and performing all works as per drawings, PJS, Technical
Specifications, other provisions of Contract document and instructions of Engineer-in-charge.

16.1.1 Type - I SV Station with vent


16.1.1.a For 10" NB Pipeline Lumpsum 7
for each
16.1.1.b For 6" NB Pipeline Lumpsum 4
for each
16.1.1.c For 4" NB Pipeline Lumpsum 1
for each
16.1.2 TYPE - II SV STATION WITH VENT & FUTURE TAP-OFF
16.1.2.a For 10" NB Pipeline Lumpsum 9
for each
16.1.2.b For 6" NB Pipeline Lumpsum 2
for each

17
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 15 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
16.1.2.c For 4" NB Pipeline Lumpsum 1
for each
Note:
i) Work under above items are exclusive of all works associated with main pipeline covered
under Item No. 1.0 above.
ii) All civil/ structural works including area fencing and gate except items mentioned in note-iii will
be paid separately as per unit rate provided elsewhere in the SOR.
iii) Construction of valve pits and Pipe Supports are included in the above item and no separate
payment will be made for them.
iii) All Assorted pipe,fittings & flanges including Olet below 2"& all sizes of ,coupling, nipples etc.
as required shall be suplied by contractor but no separate payments shall be made as it is
covered under above item rate.

17 SUPPLY OF ASSORTED PIPE, FITTINGS, FLANGES & VALVES


Complete works of supply of pipes, flanges & fittings for aboveground & underground
installation including all taxes, duties, transportation and inspection charges but not limited to,
the following items in accordance with PMS (piping material specification), relevant
specifications & drawings indicated in job specification under SCC (technical) and instructions
of Engineer-in-charge and as per all provisions of the CONTRACT DOCUMENT.
- Handling including lifting, transportation from Contractor Stores to CONTRACTOR's workshop
for fabrication and/ or to work site for field fabrication and erection for all piping items supplied
by Contractor.
17.1 Carbon Steel Pipe (API 5L Gr. B PSL-2, BE SEAMLESS )
Size Rating/ Schedule
i) 10" NB, BE Sch. Std. Meter 18
Ii) 8" NB, BE Sch. 40 Meter 45

17.2 Carbon Steel Pipe (A 106, Gr. B(Charpy), Seamless B-36.10)


Size Rating/ Schedule
i) 4" NB, BE Sch. 40 Meter 36

ii) 2" NB, BE Sch. XS Meter 30

18
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 16 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
17.3 Flanges
a) Weld Neck (B-16.5, 300# A105(Charpy))RF,125AARH)
Size Rating/ Schedule

ii) 4" NB, RF End thickness to match with pipe wall thickness Nos. 8

iii) 2" NB, RF End thickness to match with pipe wall thickness Nos. 8

b) Blind Flanges (B-16.5, 300# A105(Charpy))


Size Rating/ Schedule

ii) 4" NB RF 125AARH Nos. 8

iii) 2" NB RF 125AARH Nos. 8

17.4 Elbow (Seamless)

a) 90° Elbow (A234 Gr. WPB(Charpy), B-16.9, 1.5D)


Size Rating/ Schedule
i) 8" NB BW, End thickness to match with pipe wall thickness(Sch.40) Nos. 2

ii) 4" NB BW, End thickness to match with pipe wall thickness(Sch.40) Nos. 40

iii) 2" NB BW, End thickness to match with pipe wall thickness(Sch.XS) Nos. 20

b) 90° Elbow [MSS - SP - 75, Gr. WPHY-52, MSS - SP - 75, 3D, BW]
Size Rating/ Schedule
i) 10" NB BW, End thickness to match with pipe wall thickness(sch 40) Nos. 30

c) 90° Elbow (A234 Gr. WPB(Charpy), B-16.9, 3.0D)


Size Rating/ Schedule
i) 6" NB BW, End thickness to match with pipe wall thickness(Sch.40) Nos. 20

ii) 4" NB BW, End thickness to match with pipe wall thickness(Sch.40) Nos. 15

19
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 17 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
d) 45° Elbow [MSS - SP - 75, Gr. WPHY-52, MSS - SP - 75, 3D, BW]
Size Rating/ Schedule
i) 10" NB BW, End thickness to match with pipe wall thickness(sch 40) Nos. 25

e) 45° Elbow (A234 Gr. WPB(Charpy), B-16.9, 3.0D)


Size Rating/ Schedule
i) 6" NB BW, End thickness to match with pipe wall thickness(Sch.40) Nos. 15

ii) 4" NB BW, End thickness to match with pipe wall thickness(Sch.40) Nos. 10
f) 22½° Elbow [MSS - SP - 75, Gr. WPHY-52, MSS - SP - 75, 3D, BW]
Size Rating/ Schedule
i) 10" NB BW, End thickness to match with pipe wall thickness(sch 40) Nos. 30

g) 22½° Elbow (A234 Gr. WPB(Charpy), B-16.9, 3.0D)


Size Rating/ Schedule
i) 6" NB BW, End thickness to match with pipe wall thickness(Sch.40) Nos. 10

ii) 4" NB BW, End thickness to match with pipe wall thickness(Sch.40) Nos. 10
h) 15° Elbow [MSS - SP - 75, Gr. WPHY-52, MSS - SP - 75, 3D, BW]
Size Rating/ Schedule
i) 10" NB BW, End thickness to match with pipe wall thickness(sch 40) Nos. 20

i) 15° Elbow (A234 Gr. WPB(Charpy), B-16.9, 3.0D)


Size Rating/ Schedule
i) 6" NB BW, End thickness to match with pipe wall thickness(Sch.40) Nos. 10

ii) 4" NB BW, End thickness to match with pipe wall thickness(Sch.40) Nos. 8

17.5 Tees (Seamless)


a) Equal Tee (A234 Gr. WPB(Charpy), B16.9)
Size Rating/ Schedule

ii) 4" NB x4" NB x 4" NB BW, End thickness to match with pipe wall thckness(Sch.40) Nos. 16

iii) 2" NB x2" NB x 2" NB BW, End thickness to match with pipe wall thckness(Sch.XS) Nos. 8

20
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 18 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
b) Unequal Tee (A234 Gr. WPB(Charpy), B16.9)
Size Rating/ Schedule

i) 8" NB x8" NB x4" NB BW, End thickness to match with pipe wall thckness(Sch.40) Nos. 1

4" NB x 4" NB x 2" NB BW, End thickness to match with pipe wall thickness (Sch 40) Nos. 8

17.6 Weldolet and Sockolet


a) Weldolet (A 105 (Charpy),MSS-SP97)
Size Rating/ Schedule
6"NB X 2"NB BW,S80 Nos. 12
b) Reducer (A234 Gr. WPB(Charpy), B16.9)
10"NB X 8"NB BW,S40 Nos. 2
c) Disc End( A234 Gr. WPB(Charpy), B16.9)
10" NB Disc End Nos. 2
6" NB Disc End Nos. 4
4" NB Disc End Nos 12
17.7 Barred Tees
a) Equal / Unequal Barred Tees (As per Data Sheets)
Size Rating/ Schedule
i) 10"X10"X10" BW,End thickness to match Pipe thickness Nos. 3

ii) 10"X10X6" BW,End thickness to match Pipe thickness Nos. 4

iii) 10"X10X4" BW,End thickness to match Pipe thickness Nos. 46

iv) 4"X4"X4" BW,End thickness to match Pipe thickness Nos. 1

v) 6"X6"X4" BW,End thickness to match Pipe thickness Nos. 3

b) Equal / Unequal Tees (A234 Gr. WPB, B16.9)


i) 4"X4"X2" BW,End thickness to match Pipe thickness Nos. 4

21
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 19 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
17.8 Insulating Joints
i) 10" NB , ANSI Rating 300# (As per Data Sheet enclosed) Nos. 2

ii) 4" NB , ANSI Rating 300# (As per Data Sheet enclosed) Nos. 8

18.9 Ball Valve (BS5351, B 16.11 ANSI Rating 800#)


ii) 3/4" NB BW,FB (As per Data Sheet enclosed) 800# Nos. 12

Note:
i) For all the supply items mentioned above, procurement shall be made as per enclosed Data
Sheets and respective technical specification, after due approval of Engineer-in-charge.
ii) The quantities mentioned above are tentative and quantities for above supply items shall be
finalised & procured by Contractor only after due approval of EIC. Contractor supplied any
surplus item during reconciliation shall not be accepted / taken by the Owner.

19.0 PLANT PIPING (ABOVEGROUND)


Transportation of all piping items from Owner's and/ or Contractor's storage point to work at
site/ workshop as applicable, complete work of fabrication, erection, painting, testing of pipes,
flanges and fittings and making ready for further Commissioning / Start-up of carbon steel
piping of all sizes and ratings including supply of all consumables, equipment, manpower and
other resources and execution of, but not limited to, the following works in accordance with
relevant specifications indicated in item 5.5 of PJS & scope of work indicated in SCC,
drawings, specification and instructions of Engineer-in-charge and as per all provisions of the
CONTRACT DOCUMENT.
- Fabrication including cutting, edge preparation, inclusive of grinding the edges of pipes,
fittings, flanges etc. to match with the matching edges of uneven/different thickness wherever
required, welding, attachment of all pipe fittings like elbows, tees, reducers. Supply of all sizes
of nipples and coupling etc. as required for completion of job.
- Weldolets, sockolets, flanges, vent and drain point connection etc., including providing stub-in
connections, fabricated fittings and reinforcement pads etc., as required.
- Erection including prior cleaning, lifting, placing on pipe sleepers and supports, overhead on
racks, skids and at all elevations including installation and carrying out connected activities for
all types of valves including supply and fixing of gaskets, studs/ bolts, nuts wherever required
for all sizes, levelling, aligning, joining of flanges, blind flanges, connecting with equipment,
nozzles, strainers, tie-in with existing piping/facilities, etc. tapping for inline instruments like
pressure gauges, thermowells, sample connection, etc.
- Preparation of final bill of material based on piping GADs.

22
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 20 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
- Preparation of isometric and fabrication drawings.
- Carrying out Non-destructive testing as required. Except item mentioned in sl.no. 22 of SOR.
- Surface preparation before application of primer by means of sand blasting including supply of
approved quality of sand, manpower, machineries, tools & tackles to achieve required
roughness as per specification and as per instruction of Engineer-in-charge.
- Painting of entire system (including aboveground all pipes fittings, flanges and accessories) as
per specification MEC/S/05/21/07 suitable for highly corrosive area environment including
supply of approved paints and primers, application of primer and paints, indentification
lettering/ numbering, colour coding, etc. as specified including rub down & touch up of shop
primer or scrapping of shop primer wherever required by COMPANY and providing scaffolding
for all heights etc.
- Cleaning and flushing by water/ compressed air, testing of the systems including hydrostatic,
pneumatic and any other type of testing as specified, draining, drying by compressed air/other
methods approved by COMPANY.
- Precommissioning & making operational all piping system and equipments.

- Commissioning Contractor scope shall provide all necessary assistance in term of supply of
man-power, equipment, tools and tackles required amount of nitrogen for purging of entire
terminal piping system including equipments etc. to the company during commissioning
activities.
- Completion of all such work in all respects as per scope of work and as per drawings,
specifications and instructions of the COMPANY and keeping the system ready in all respects
for further commissioning and start up.

- Hook-up works (with client/ consumer piping at battery limits):

19.1 Complete Carbon Steel aboveground Piping Work with painting including all fittings, flanges
and supply of all required gaskets, studs bolts & nuts etc. as described under item 20.0 above

Carbon Steel Pipe (ASTM A 106, Gr. B, Seamless B-36.10)


Size Rating/ Schedule
i) 10" NB, BE S40 Meter 18

ii) 8" NB, BE S40 Meter 45

iii) 4" NB, BE S40 Meter 36

23
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 21 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
iv) 2" NB, BE S80 Meter 30

Note: 1) Pipe Specification and thickness may vary depending upon availability of pipe. No extra
payment shall be made for this.
2) All butt welded fittings & flanges end shall generally match with connecting pipe wall
thickness. However, in case of misalignment, Contractor shall have to do end preparation
without any extra cost.
3)All Assorted pipe,fittings & flanges including Olet below 2"& all sizes of ,coupling, nipples
etc. as required shall be suplied by contractor but no separate payments shall be made as it is
covered under above item rate.
20.0 RADIOGRAPHY

Performance of radiographic inspection by gamma radiation as per scope of work and as per
specifications in piping of all types and thickness including providing/hiring of all necessary
equipments, supply of all consumables, and whatever else even though not expressely
mentioned but required to perform the work as per specifications and instructions of Engineer-
in-Charge (full circle re-radiography of the repaired joint and additional radiography
necessitated due to poor performance of contractor's welder shall be carried out by the
Contractor at his own cost and shall not be paid extra by Company). Radiographs shall be
submitted to the Engineer-in-Charge for acceptance, whose decision shall be final and binding.

Size
i) 10" NB No.of 8

ii) 8" NB No.of 20


Joints
iii) 4" NB No.of 40
Joints
iv) 2" NB No.of 24
Joints
Note:
i) The quantities mentioned above are tentative.

24
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 22 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
21.0 Aboveground installation of Insulating Joint & Valves etc.

Handling including lifting and transportation from COMPANY's warehouse to CONTRACTOR'S


Stores and/or work site and installation of all types of valves, insulating joint including
assembly of valve accessories, (if any) by bolting, threading or welding, supply and insertion of
gaskets, nuts & bolts, nipples, etc. at all elevations of pipe sleepers, supports or overhead on
racks, equipments nozzle, skid & painting etc. supply of all consumables, manpower,
equipment, etc. for completion of all works as per scope of work and as per drawings,
specifications and instructions of Engineer-in-charge including servicing/ cleaning of valve
wherever requried.
21.1 Flanged/ Welded Valves (Full Bore/ Reduced Bore)
Ball / Globe / Plug Valve
Size Rating/ Schedule

ii) 8" NB 300# Nos. 6

iii) 4" NB 300# Nos. 9

iv) 2" NB 300# Nos. 10

21.2 Sockolet Welded Valve (Ball / Globe /Plug )

Size Rating/ Schedule


i) 1" NB 800# Nos. 18

3/4" NB 800# Nos. 10


21.3 Insulating Joint
i) 10" NB, 300# Nos 2

4" NB, 300# Nos 8

Note:
The quantities mentioned above are tentative.

25
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 23 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
22.0 Supply of Coating repair material

i) Cross linked Thermoplastic adhsive of Repair patch( Perp 80 patch of covalance raychem or Sq.m. 25
equivalent)

ii) Coating Silicon Roller Nos. 10

iii) PERP FILLER of Covalance Raychem or equivalentt. Sq.m. 15

23.0 STRUCTURAL WORKS


23.1 Supply of erection of single leaf mild steel gate 2.5m high with mesh upto 2m height and No. 24
barbed wire fencing and 2m wide complete in all respect including painting as per TS on all
MS items, all works as per specification and drawings excluding foundations and RCC beams.

23.2 Supply of all materials, fabrication and erection of chain link fencing 2.5m high with mesh up to RM 720
2m height and barbed wire fenching complete in all respects including painting as per TS on all
MS items, all works as per specification and drawings excluding foundation and RCC beams.

23.3 Pipe Supports & Other Structures


a) Supply, fabrication and erection of all types of pipe supports like clamps, saddle, guide stops, M.Ton. 4
cradles, turn buckles, anchors, T-posts; stockade/ trestle and pipe bridge for overhead piping;
frames for canopy, approach ladders and platforms, crossover, cable tray supports, etc.
including painting suitable for highly corrosive area as per specification labour and
supervision & complete work as per drawings, specifications and instruction of Engineer-in-
charge. (Bolts, nuts, washers, U-clamps etc. for supporting shall be supplied by the Contractor
within the rates quoted. These items will not be measured and paid seperately). The work is
to be completed in all respect as per scope of work and specification.
Notes:
i) The quantities indicated are estimated values and hence are approximate. Final payment will
be made based on actual quantities to be certified by the Purchaser.
ii) The cost of MS bolts (permanent and service(, washers, electrodes, putty, gases, cost of
straightening the raw materials, cutting of flats from plates and providing splices, paints, tools,
plants etc., as required for the work shall be deemed to be included in the quoted rates.
iii) All handling and transport charges of raw materials and fabricated structures including double
handling, as required, for completion of work in accrodance with time schedule, are deemed
be included in the quoted rates.

26
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 24 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
24.0 CIVIL WORKS (for GAIL Tap-off, CGS, PRS, SV's cum Tap-off and Mainline)
24.1 Site Grading
Earth in excavation and filling to the grades and levels shown in the approved drawings in all M3 150
kinds of conditions including for Road embarkments, using approved quality good earth from
designated borrow area, for all heights and depths including clearing and stripping (min.
150mm) of the area marked for filling, taking spot levels, consolidating the exposed natural soil
surface, excavating the earth from borrow area loading, transporting & unloading, spreading in
layers not exceeding 150mm thickness, breaking clods, watering (if reqd.), ramming and
compacting by manual/ mechanical means to give minimum 92% of modified Proctor's density
of earth, testing & dressing including disposal of all unserviceable material all complete as per
specifications and directions of Engineer-in-charge.
(Rate to include cost of all labour, tools, tackles, equipment, hire charges, cost of borrow earth
by way of royalties, right of way, cess etc., as applicable with all bye works and sundry works).

24.2 Plain Cement Concrete


Supplying and laying plain cement concrete (including shuttering of required) in all types of
concrete works including levelling courses below foundation, substructure, superstrcuture,
chambers, cable tranch, under floors and any other locations, at all leveies as per drawings,
specifications and directions of the Engineer-in-charge.

a) PCC 1:4:8
1 Cement : 4 Coarse sand : 8 stone aggregate 40mm nominal size. M3 15
(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all
materials, shuttering, earthwork in excavation and backfilling using approved earth in all
conditions etc. with all bye works and sundry works.)

27
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 25 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
24.3 Reinforced Cement Concrete

Providing and laying reinforced cement of grade M-20 with 20mm and down grade crushed M3 170
stone aggregate in all types of structures like foundations, pedestals, pedestal bases, pipe
supports, sleepers cable trench inlcuding constrcution joints, bitumen painting on surface in
contact with soil, providing and fixing reinforcing steel, shuttering, inserts, finishes etc. at all
depths and heights complete as per drawings, specifications and direction of the Engineer-in-
charge.
Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all maerials
such as minimum 43 grade cement including sulphate resistant cement for sub-structures, R/F
steel, Inserts, bolts, conduits, bitumen, other minor constrcution materials, shuttering,
stanging, earthwork in excavation and backfilling using serviceable earth in all conditions,
shorting bailing and pumping out water, testing of concrete, curing etc. with all bye works and
syndry works.
24.4 Concrete Pavement
Providing and laying reinforced cement concrete of (M-20 grade) with 20mm and down grade
crushed stone aggregate in pavement, including preparation of base (i.e. compacted
subgrade, 200 thk sand and 50 thk PCC M-10 grade), leaving pockets if necessary, making
recess, projections, fixing inserts conduit pipes (GI, PVC, HDPE, etc.) laying in alternate
panels, filling the gaps between the panels with bitumen etc., making slopes, finishing edges,
leaving bars for pedestals & sleepers including providing sand fill isolation , shuttering,
providing and fixing reinforcing steel, curing, chipping and modification works etc. as specified
in any shape, thickness, position and finishing the top surface smooth as per requirement etc.
all complete as per drawings, specifications and directions of the Engineer-in-charge.
- 150 mm thick (Type-I) M2 100

24.5 Brick Work


Providing brick work with brick class designation M-7.5 of IS:1077 in cm1:4 (1 cement : 4 M3 180
sand) in steps, walls, retaining walls and load bearing structures drains, or any shape with all
lead, depths & height including curring, scaffolding, etc., as per specifications and drawings
with all bye-works and direction of the Enfineer-in-charge.
(Rate to include cost of all labour, tools, tackles, equipment, hire charges, supply of all
materials such as minimum 43 grade cement bricks, finishes, bitumen, other minor
constrcution materials, shuttering, staging, masnory work, plastering, painting etc. with all bye-
works and sundry works).

28
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 26 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
24.6 Laying of Brick / Concrete / or impact resistant tape
Providing single layer of Brick / Concrete / or impact resistant tape to entire width of trench
above Warning Mat placed in trench over the laid pipeline as per OISD 226, standard drawing,
specification and instruction of Owner.
(Rate to include cost of all labour, tools, tackles, equipment, hire charges & supply of all
materials, etc.)
24.6.1 Brick Layer for width of 16" pipeline trench as per drawing (75 mm thk.) Sq. m 100

24.6.2 Concrete for width of 16" pipeline trench as per drawing (80 mm thk.) Sq. m 100

24.6.3 Impact Resistant Tape of 3 mm thk for width of 16" pipeline trench Sq. m 100

25.0 TEMPORARY CATHODIC PROTECTION SYSTEM

25.1 Design, detailed engineering, supply, installation, testing and commissioning of the temporary
Cathodic protection system using Mg/ Zn galvanic anodes to protect the external surface of 3
LPE coated entire 78.0 km (approx.) long steel pipeline network against corrosion for design
life of minimum 1 year or till commissioning of PCP system whichever is later as per standard
specification No. MEC/TS/05/21/016A for temporary cathodic protection system. Scope shall
also include but not limited to the following for completion of jobs:

a) Measurement of soil resistivity along the right of way of the main pipeline route as per
specification for design & installation of anodes.

b) Collection of additional data related to cathodic protection along the right of way of pipeline as
per specifications.

c) Supply, installation, testing & commissioning of one set of spark gap arrestor with 2 plate Zinc
grounding cell of 20 kg net weight each across each insulating joint as per specification.

29
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 27 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
d) Supply, installation, testing & commissioning one set of polarisation cell with zinc anode at all
high tension (66KV or higher) electrical power transmission line/Equipment crossing or running
parallel to the pipeline for grounding purpose as per specification. The rating shall depend
upon anticipated fault current & ground bed resistance at the location of installation. However,
the rating of polarisation cell (krick) shall not be less than 5 KA & number of 20 kg net weight
zinc anode shall not be less than two.

e) Supply & installation of Zinc Ribbon Anodes at 4-8 O’Clock position in the interval of 2 metre
(max.) on carrier pipes at all cased crossings i.e. railways/ roads etc.

f) Monitoring of the protection system for 6 months

g) All civil/ structural works related to TCP system including supply of bricks, cement & steel etc.
required for completion of the system.
For 10" meter 46000
For 6" meter 19000
For 4" meter 10000

28.0 FIELD INSTRUMENTATION


28.1 PRESSURE INSTRUMENTS
28.1.1 Supply, Calibration, Installation of Pressure Gagues and their accessories inclusive of supply Nos. 4
of necessary piping materials and tubings alongwith all necessary valves & fittings, fabrication
and installation of impulse lines/ manifolds & hydraulic testing as per installation standard
attached elsewhere in Tender Document and Supply as per Data Sheet
No.MEC/23LB/05/E5/I/001/DS-PG. Give breakup of supply and Installation rate.
28.2 TEMPERATURE INSTRUMENTS
28.2.1 Supply, Calibration, Installation of Temperature Gauges with flanged Thermowell inclusive of Nos. 4
installation of thermowell on the nozzle and installation of instruments as per installation
standard attached elsewhere in Tender Document and Supply as per Data Sheet No.
MEC/23LB/05/E5/I/001/DS-TG. Give breakup of supply and Installation rate.

30
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 28 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
28.3 FREE ISSUE ITEM
Handling, including lifting, transportation from Company's stores to Contractor's work-shop for
fabrication or/ and to worksite for field fabrication, assembly of parts/ sub-assemblies erection
for all vessels, equipments supplied by company above ground/ underground at all elevation/
depth, fixing of foundation bolts welding wherever required, alinging, grouting, hooking-up,
cleaning and flushing by water draining, drying by compressed air providing all mountings,
ancilliary, enabling works as required and completing in all respect as per drawings,
specification and instruction of Engineer-in-charge. Contractor's scope shall include supply of
all material and accessories including but not limited to any fixtures, clamps, gasket, nut bolts,
finish coat of painting including rub down & touch up of shop primer/ paint scrapping of shop
primer/ paint and further their painting after application of primer as per specification, wherever
required by Company.
Approx. erection weight and Details of major equipments are as under
(Refer P&ID included with Tender).
Details of major equipments are as under
Details of Equipment Nos.
28.3.1 Metering Skid alongwith all accessories and control panel at CGS-I 1 MT 10

28.3.2 Metering Skid alongwith all accessories and control panel at CGS-II 1 MT 10
Note:
i) The quantities mentioned above are tentative and quantities for above including supply items
shall be finalised & procured by Contractor only after due approval of EIC. Contractor supplied
any surplus item during reconciliation shall not be accepted / taken by the Owner.
ii) For all the supply items mentioned above, procurement shall be made as per specification &
Data Sheets, after due approval of Engineer-in-charge.
29.0 TELECOMMUNICATION WORK : SUPPLY AND LAYING HDPE DUCTS AND ASSOCIATED
WORKS: Supply of materials/ equipments ,storage,erection and services (as per
specification, drawings etc. provided in this Bid Document ).

29.1 Supply of Permanently Lubricated Telecom HDPE Duct & Accessories as per MECON
Technical Specification No. MEC/TS/05/E5/T/037 Rev 1. Design, Manufacturing,factory
testing, inspection, packaging, forwarding, transportation, insurance,receipt and storage at site
etc.

31
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 29 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
29.1.1 Supply of 40 mm OD , permanently lubricated HDPE DUCT, Factory Acceptance Testing,: Meter 75000
Factory acceptance testing of 40 mm OD, 6 Kg/cm2, permanently lubricated HDPE duct as
per spec.

29.1.2 Supply of HDPE Duct Accessories: Supply of HDPE Duct accessories required including Lumpsum 1
Plastic Couplers, End Plugs, Cable Sealing Plugs, End Caps, etc suitable & sufficient for
above supplied Duct with extra 20 % quantity for future use.
30.0 TELECOMMUNICATION SITE WORK (as per scope of work, Standard Specification no.
MEC/S/05/E5/T/001 Rev 0 & ../002 Rev 0 of Bid documents)

30.1 Submission of optical fiber cable & HDPE alignment sheets (CAS) based on the existing Lumpsum 1
pipe line survey (No separate survey reqd.),estimation of OFC & HDPE duct including all
accessories in accordance with the alignment sheet and specifications.Laying work can not
be started without approval of these documents from Client / Consultant / EIC.

30.2 Blowing of Optical Fiber Cable

All activities pertaining to blowing of optical fiber cable (after testing of drum at site) in PLE Per Meter of 75000
HDPE Duct laid in same pipeline trench,through CS/ HDPE conduits at crossing, cable Trench
sealing, padding, backfilling if required separately etc. using all materials required including Length
Supply and Laying of Warning Mats if required separately, etc. , at the each end OFC to be
stored in pit with proper sealing all complete as per specifications and drawing provided in the
bid document & as per direction of consultant.

30.3 Laying of HDPE Telecom Duct as per specification

Laying of 40mm OD permanently lubricated HDPE ducts( PLE HDPE Duct), in same pipeline Per Meter of 75000
trench direct buried or cased crossing through CS/ HDPE conduit in all type of soil & terrain, Trench
excavation as required, padding, backfilling if required separately etc. including cleaning and Length
sealing of ducts at the end of laid drum lengths, preparation & Supply of Cable Blowing Pit at
each KM including sand, jointing of HDPE conduit, Testing of HDPE Duct and accessories
after laying,preparation of report and final drawing & documents as per specification, joint
location marking , erection accessories (suitable for min 8 kg/cm2 pressure rating) ,all
complete as per specifications provided in the bid document & as per direction of consultant.

32
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 30 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
30.4 Supply and installation of jointing pits, including sand, etc. all complete as per spec., Nos. 25
drawing provided in the bid document and the direction of consultant. (Quantity shall vary as
per project / site requirement based on approved Cable Alignment Sheet).

30.5 Supply & installation of 300 dia cable markers at all pipeline marker locations on same Nos. 50
pipeline marker post (including at every crossing etc.) as per specifications & drawing
provided in the bid document and direction of consultant.

29.6 Splicing, Jointing of optical fiber cable (including supply and installation of joint Lumspum 1
markers, etc.), end to end testing all completed as per specifications & drawing provided in
the bid document and direction of consultant.Splicing with steet fibre, test of the fibre for the
smooth operation system on wavelength. Power Testing of laid OFC, end to end testing
,Identification of the fault,Rectification, final testing & commissioning , preparation of reports
etc. work complete in all respect with all necessary accessories for all location till the final
Handing over & taking over by Owner of the laid Optical Fiber Cable alongwith HDPE Telecom
Duct complete as per specification,Drawings and Documentation as per specification &
contract agreement and as per the direction of Engineers in charge.

33
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 31 of 32
REVISED SCHEDULE OF RATES
FOR
LAYING & CONSTRUCTION OF CITY GAS STEEL PIPELINE GRID & ASSOCIATED WORKS IN KAKINADA

MAINLINE, TERMINALS & ASSOCIATED WORKS Unit Rate (in Rs.) inclusive of all taxes and duties including Total Amount
service tax and WCT inclusive of all
Item Description of items Unit Quantity In Figure In Word taxes and duties
including service
No tax and WCT
(in Rs.)
30.7 Supply and Installation & Commissioning of Electronic Marker System as per
specification , test certificate and documents etc. consisting of :
a) Electronic Markers (To be buried underground along with OFC Joints at all jointing location) Nos. 25
- The make & model shall be same as of existing electronic marker.
- Detail of marker will be provided to successful bidder.
- Quantity shall vary as per project / site requirement based on approved Cable Alignment
Sheet.
Note : The quantites of individual item can varied as per site requirement.The payment will be
made as per actual certified measurement at site.For the Payment purpose the actual pipeline
length will be considered for the payments of laid OFC and HDPE Duct along the pipeline and
length upto control room inside terminal will be considered separately.The location of Jointing
and the quantity of jointing pit and closure may be finalised with the Cable alignment sheet
approval as per actual laying conditions at site.
General Note :
1 All SOR item shall be quoted by the bidder in the price part of the bid other-wise bid will
be rejected.
2 All Bidders are requested to refer clause no. 17C.0 of Particular Job Specification for
Mainline, Mechanical &
Associated works before filling the price against each item of above SOR.
Total Amount in INR (inclusive of all taxes & duties) in Figures :
in Words :
%age of VAT considered in the above price
Amount of VAT included in the above total price in INR
%age of Service Tax considered in the above price
Amount of Service Tax included in the above total price in INR
%age of custom duty on CIF value considered included in the above price
CIF value of imported component included in the above total price in INR
%age of Excise Duty in the above total price
Amount of Excise duty included in the above total price in INR

34
D:\BGL - Kakinada\Laying\Addendum-I\SOR - BGL_KAK_NEW -12.04.10-FINAL.xls SOR No. 05/21/23LZ/CG/SOR-01, Rev.-1 Page 32 of 32
2) SUMMARY OF PRICES (To be submitted with priced part of the offer)
[LAYING & CONSTRUCTION OF 10”; 6” & 4” NB U/G STEEL P/L NETWORK & ASSOCIATED WORKS IN
KAKINADA CITY – {Part of Tender No. : 05/51/23LZ/BGL-KAKI/001-i)]

(In Figures) (In Words)

1. Gross Total amount of quoted price for Mainline & Associated Work
SOR

2. Grand Total Amount (inclusive of all applicable taxes & duties)

3. Rebate (if any) offered on gross total amount (Sl.No. 2) above. ________________ % of ____________________ Percent of quoted rates
(which will be applicable on each item of Schedule of Rate) quoted rate

4. Amount of Rebate as per Sl.No. 3 above

5. Net total amount {2-3} (after considering rebate indicated at Sl.No.


3)

Note: The total amount shall also be given by the bidder in the quoted currency(ies).

Place : _________________ Signature of Authorised Signatory


Date : _________________ Name :
Designation :
Seal :
Tender No.: ________________________________________________

Offer No. & Date : ___________________________________________

D:\old data\Vijyant\BGL-23LB\BGL-Kakinada\Tender\Laying\Summary of Prices-BGL.doc


35
REPLY TO BIDDERS QUERIES RAISED DURING PRE BID MEETING

TENDER NO. 05/51/2LZ/BGL-KAKI/001-i)

S.No. Cl.No. Page no. Volume Tender Specifications Query Addendum / Clarification

1 1.1 ii) 192 I of III Terms of Payment : - Tender Condition Prevail


In tender document: ii) The second stage payment of 10% as per sub-
clause 1.1.2 above will be released on completion of continuous stretch of
4 km
We request you to change the continuous stretch of 4 Km. to 2 Km.

2 1.6.1 a) 200 I of III Reconciliation of Owner supplied In Tender Document: Tender Condition Prevail
materials :- a) For the purpose of accounting of coated pipes following allowances
shall be permitted :
i) Unaccountable wastage : 0.1%
ii) Scrap (all cut pieces of pipes measuring less than 2 m) : 0.25%
iii) Serviceable materials (all cust pieces of pipe) : 0.5%

1.1 As it is city gas pipeline there are more number of turning points and
crossings comparatively normal cross country pipelines. So, we request
you to chnage the scrap and other allowances as follows:-
i) Unaccountable wastage : 0.25%
ii) Scrap (all cut pieces of pipes measuring less than 2 m) : 0.1%
iii) Serviceable materials (all cust pieces of pipe) : 0.3%

2.1 Also, we request you to consider the serviceable length of 2 t 9 mm to


2 to 8 m and from 8 m and above length to be considered as good length.

3 13.0 43 II of III Working Spread Limitations : Working Spread Limitations : Accepted


In tender document: Contractor shall, in general, observe the following
maximum distances between the working mainline spread:
Between ROW grading, clearing and backfilling : 30 kms
Between backfilling and final clean-up : 05 kms.

As it is city gas pipeline, we request you to remove the clause of working


spread limitation because the front availability will be based on the
authorities permissions only. Hence limitation of working spread may not
be possible during execution.
4 - 187 I of III Annexure-3 to SCC In tender document : Tender Condition Prevail
The time completion period for the project is 11 months.
As the pipeline rute seems to be too conjected, so we kindly request you
to ammend the time of completion from 11 months to 18 months.

36
Page 1 of 1