NJIT
PLANNING
Planning is the determination of
the individual operations which
must be performed in order to
carry out a project, and the
establishment of the sequential
relationships between them.
Project Control IE 699
NJIT
SCHEDULING
Scheduling is the development of
time requirements for each
operation, and the relating of
each to calendar time.
NJIT
January 1
January 10
January 15
March 15
March 15
April 15
April 30
July 1
NJIT
Basic Schedule
JAN
FEB
MAR
APR
MAY
JUN
Description
Tank Design
General Project Design
Construction Fdn./Racks
Erection of Tanks
Construct R.R. & Roads
NJIT
NJIT
PROCUREMENT &
ENGINEERING
NJIT
Detail
Engineering
DESIGN ENGINEERING
PIPING
30.00
INSTRUMENTATION 30.00
MECHANICAL
30.00
ELECTRICAL
30.00
CIVIL
30.00
CATEGORY
6782
4660
1895
2663
8486
68277
MANHOURS
30.00
7302
219063.
PROCESS ENGINEERING
30.00
422
12672.
DESIGN ENGINEERING
PIPING
INSTRUMENTATION
MECHANICAL
ELECTRICAL
CIVIL
30.00
30.00
30.00
30.00
30.00
6782
4660
1895
2663
8486
203454.
139791.
56844.
79896.
254574.
30.00
30.00
30.00
30.00
30.00
13671
4880
0
2091
8048
410124.
146415.
0.
62736.
241428.
30.00
30.00
30.00
30.00
428
675
2368
3907
12831.
20238.
71049.
117204.
68277
2048300.
DRAFTING
203454. PIPING
INSTRUMENTATION
139791. EQUIPMENT
56844. ELECTRICAL
CIVIL
79896.
OTHER
254574. GENERAL DRAFTING
2048300.SUBTOTALS
OVERHEAD ITEMS:
REPRODUCTION
COMMUNICATIONS
TRAVEL
COMPUTATION
PAYROLL BURDENS/FRINGES
INDIRECT OFFICE EXPENSES
Detail
Engineering
Drawings
ENGINEERING
COST
PROJECT ENGINEERING
SUBTOTALS
RATE
$/MH
56300.
8400.
21600.
101400.
512100.
1536200.
68277
4284300.
62.75
46
2917
DRAWING
CATEGORY(PLANS & ELEVS.)
PIPING
ARRANGEMENTS
PIPING ISOMETRICS
SPECIAL HANGER/SUPPORT DRAWINGS
STEAM TRACING DRAWINGS
PIPING MODEL
NUMBER
35 OF
726
DRAWINGS
16
29
2
28
373
16
3
7
4
14
7
3
10
7
0
5
0
0
37
4
10
19
0
21
22
7
26
5
9
6
6
12
TOTAL DRAWINGS
1469
NJIT
General Schedule
DETAIL ENG'G
PROJECT
1JUL95
*******************
CCCC **** CC *-**
16FEB96
:
:
:
:
:
1JUL95
***** CCCCCCCCCCCCCC ***
28NOV95
:
:
:
:
:
CIVIL
1JUL95
**********************
28NOV95
:
:
:
:
:
STEELWORK
31JUL95
******* CCCCCCCCCCC
28NOV95
:
:
:
:
:
INSTRUMENTS
1JUL95 CCCCCC
**************
13NOV95
:
:
:
ENG'G PROJECT ELECTRICAL 1JUL95 18JUL95
*******************
CCCC ****: CC *-** :
*---**************
16FEB96 13NOV95
: :
: :
::
::
::
PROCUREMENT
PIPING EQUIPMENT 1JUL95 1JUL95
********************************
CCCCCCCCCCCCCC
***
5JAN96
:
:
:
:
:
PIPING
***---************
28NOV95 31AUG95
:
:
:
:
:
29DEC95
:
:
:
:
:
CIVIL STEELWORK 1JUL95 23AUG95
**********************
*******--****************
28NOV95 6FEB96
: :
: :
::
::
::
INSTRUMENTATION
1JUL95
**--******--*****************
STEELWORK
31JUL95 16JAN96
*******
CCCCCCCCCCC
:
:
:
:
:
ELECTRICAL 28NOV95 1JUL95
: ******-***********************
:
:
:
:
23JAN96
:
:
:
:
:
INSTRUMENTS
1JUL95
CCCCCC
**************
SITEWORK
6OCT95
S
**
13NOV95 18OCT95
: :
: :
::
::
::
CONSTRUCTION EQUIPMENT SETTING
16FEB96
*CCCCCCCCCCCCCCCCCCCCCCC
26JUL96
:
:
:
:
:
PIPING
16FEB96
********
CCCCCCCCCCCCCCCCCCCCCCCCCCM
8OCT96
:
:
:
:
:
CIVIL
18OCT95
********----CCCCCCCCCCCC ********
31MAY96
:
:
:
:
:
BUILDINGS
22JAN96
*****************
16MAY96
:
:
:
:
:
STEELWORK
12FEB96
************
29APR96
:
:
:
:
:
INSTRUMENTATION
21MAR96
*******************
23JUL96
:
:
:
:
:
ELECTRICAL
18OCT95
*---****---------***-**************----**
25JUL96
:
:
:
:
:
INSULATION & PAINTING 6AUG96
*****
CCCCCCCCC
4NOV96
:
:
:
:
:
PIPING
DETAIL
NJIT
8t 15=
15
5300+-8+22=30
Foundations
+ 8 +
25
Install Piping
Erect TWR
10600
8 + 22 = 60
0
-
u-l
In
II
II
Erect Bldg.
=
60
7000
+ 8 +
22 = 40
106OOt8+22=60
Erect Steel
. 7000
t 8 t 22
Set Exch.
Pipe Up
7000+8+22=40
= -3500
40 + 8
f 20 = 20
Set + Pipe Up Compr.
.
10600+8+22=60
- .
10
+ 25 = 20
.
Painting
4000t8t 16=30
Manpower Chart
(Most Probable)
Manpower Chart
(Theoretical)
Catender Days
*__.*
r
..
NJIT
Construction
Manpower
Developing Country
Work Force
66
67
CRAFT
CODE
51
53
54
56
57
59
60
62
63
64
66
67
69
70
71
72
74
75
77
78
79
81
83
84
86
87
89
98
99
PIPEFITTER
PIPE WELDER
CRAFT
MANHOURS
LABORER
MILLWRIGHT
RIGGER
LIGHT VEHICLE DRIVER
HEAVY VEHICLE DRIVER
OILER
MECHANIC
LIGHT EQUIPMENT OPER
MEDIUM EQUIP OPER
HEAVY EQUIPMENT OPER
PIPEFITTER
PIPE WELDER
CEMENT FINISHER
CARPENTER
BRICKLAYER
IRONWORKER - REBAR
IRONWORKER - STRUCT
WELDER - STRUCTURAL
WELDER - SPECIAL
WELDER - FABRICATOR
BOILERMAKER
INSTRUMENT FITTER
ELECTRICIAN - LINE
ELECTRICIAN - WIRING
SHEETMETAL WORKER
INSULATOR
PAINTER
CRAFT HELPER
FOREMAN
149771
59231
2.70
2.70
DIRECT
COST
-$-/MH
58335
14653
24340
1906
10409
1499
265
5945
7924
21412
149771
59231
9812
27607
0
3906
12514
700
0
0
1753
14956
2381
51283
7108
20447
30927
0
57472
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
2.70
157503.
39563.
65717.
5147.
28103.
4047.
715.
16053.
21394.
57811.
404380.
159923.
26491.
74539.
0.
10546.
33788.
1889.
0.
0.
4733.
40382.
6429.
138463.
19191.
55206.
83504.
0.
155158.
596556
2.70
1610675.
404380.
159923.
OVERTIME PREMIUM
TOTAL ADJUSTED FIELD MANPOWER
CRAFT
RATE
80534.
596556
1691209.
-$-
Reporting Progress
Prepare reports that show actual progress on
scheduled activities(Engrg./Procure./Const.)
Retain baseline schedule / Revise after review
Show critical path items and communicate cost
impact on improvements in schedule
Develop S curve to show cummulative
progress vs. plan
NJIT
Progress Report
JAN
Description
Tank Design
FEB
MAR
APR
MAY
JUN
DESIGN
DELAY
START UP
NJIT
NJIT
Phase III
Process Design and Scope Definition and Strategic Procurement
Phase VII
Key
Project
Activities:
Finalize
Project Execution Plan
Project
Closeout
Closeout
-Engineering/Construction Plan
Project Team Building Efforts Commences
Phase VI
Master Schedule
Commissioning
(Eng.,Procurement,Constr.,Start-Up)
Commissioning
And Start-Up
And Start-Up
Detailed Project Scope
Hazop Review-Preliminary
Phase V
Outside Partnerships Involvement
Functional Reviews Completed
Construction
Construction
Procurement Packages Submitted and Major
Vendors Selected
Phase IV
AR or Advance Spending Preparation
Project
Project
Finalize Financial and Business Analysis
Detailed
Detailed
Design and
Design Value Engineering. Review, Cycle
Design and
Procurement
Time Reduction Analysis and Project
Procurement
Phase III
Execution Plan Review
Design
Execute Permitting and Environmental Plan Process
Process Design
And Scope
Phase II
Rev. 0 2/9/95
SPLCC.PPT-16
Phase I
Project
Project
Concept
Concept
Development
Development
And
And
Alternatives
Alternatives
Analysis
Analysis
And Scope
Definition And
Definition And
Strategic
Strategic
Procurement
Procurement
Capital
Capital
Strategic And
Strategic And
Operational
Operational
Planning
Planning
Time
Key Activities:
Finalize Project Execution Plan
-Engineering/Construction Plan
Project Team Building Efforts
Commences
Master Schedule
(Eng.,Procurement,Constr.,Start-Up)
Detailed Project Scope
Hazop Review-Preliminary
Outside Partnerships Involvement
Functional Reviews Completed
Procurement Packages Submitted and
Major Vendors Selected
AR or Advance Spending Preparation
Finalize Financial and Business
Analysis
NJIT
NJIT
..
I;:
\
/
\
/
FOUNDATIONS
& U/G
ERECT
BLDG'S
SET EQUIPMENT
& PIPE-UP
INSTRUMENTATION &
ELECTRICAL INSTALL'N
- -
e!!r
con
I, ,I \I
TEST'
CALIBRATE
INSULATE I
START
UP
ABC INC.
PROJECT:
CONSTRUCTION & START-UP CPM
(PARTIAL)
Ill
,,yju,
Starting
Event
6 5
6 6
676
4 3
805
6 1
4 7
806
807
808
8 1
813
641
6 8
8 1
655.
684
8 1
9
7
-
1
-
3
1
-
.
2
-
0
4
.5
,,,cr,l-uuy~ UI
Ending
Event
801
803
804
805
812
812
806
807
812
812
813
814
814
815
815
815
999
999
IIUUIJ
)JEI
u a y .
UGG I
MH
Activity
U/G Piping
600
12,000
Foundations
Erect Bldg.
7,000
Erect Twr. pi
5,300
10,600
Install Piping
10,600
Erect Str. Steel
Erect Steel
7,000
Set. Exch.
3,500
Pipe up
7,000
Set & Pipe up Compr. 10,600
Press. Test
1,000
Equipment Run
1,000
Instr. Install
12,000
Insulate
3,200
Calibrate
2,000
Electr. Instal I
21,000
Painting
4,000
Commission ng
4,000
lYUlG3
Work Crew
Work Days
15
25
22
5
60
40
30
60
60
40
20
40
60
5
5
60
20
10
65
30
20
22,
2
2
22
22
22
22
25
25
25
20
25
40
16
25
Figure 12-2 combines the above data into a theoretical bar chart, This
chart will show the major activities, indicating theoretical manpower for
each, and adding this into a combined manpower loading.
The reader should be well aware that this is a theoretical example and
c,
:
;
-_(
AT JOB SITE
FROM ENGINEERING
>
>
>
r,
-
>
cu
Third, the schedule is the base for the project status report. The planner will update his schedule on a delivery basis. The percent complete is
compared with the cost to date, then the remaining work is re-estimated in
light of costs to date. This is the reason for the simuftaneous updating of
project cost and schedule.
Early Finish
Late Finish - The latest date at which an activity can finish without
jeopardizing the overall schedule.
IFloat
It may be helpful to the reader who is not too familiar with scheduling to
have a brief description of terms used in this chapter.
l
Critical Path - If the float is zero, or the early start and late start
are the same, then the activity is critical. The critical path itself
runs through the string of activities with zero float. Note that a
project could have more than one critical path.
Positive or Negative Float - If the late start is later than the early
start, then the activity has a positive float equal to this difference.
If, on the other hand, the late start is past and the activity has not
started, the float is negative. If this slippage cannot be eliminated,
then the completion of the project will be delayed by the days of
the negative float.
Restraint - This is a dummy activity, like 813-680 on Figure 12-l.
indicating that insulation cannot start before event 813 is complete.
Floating or Dangling Activity - An activity that is not connected to
a successor event.
Loop -A string of activity where the finish of one will be connected
to a start event of a predecessor event - forming a loop. A
computer will stop computing a network which has a loop.
Milestone - A significant completion point, such as 812 in Figure
12-j. The piping is complete so that pressure testing can start.
Preparing a Network
A milestone network should be prepared before the cost estimate, but it
should only be expanded after the estimate is completed. This way the
schedule activities parallel those of the estimate. Again, Figure 12-3 could
be used to illustrate this point. Assuming that the project consists only of
pumps A and B, vessel B, column C valves and piping. This is,
of course, incomplete but it will help illustrate the point. This data is taken
from the estimate. Using the milestone network, it is expanded to show the
activities and the time required to purchase and deliver to the site the
required equipment. Similarly, Figure 12-1 is developed for the construc-
2d
205
Ending
Activity
Event
801 U/G Piping
803 Foundations
804 Erect Bldg.
805 Erect Twr.
812 Install Piping
812 Erect Str. Steel
806 Erect Steel
807 Set. Exch.
81 2 PIk)e up
812 Set & Pipe up Compr.
Press. Tpst
813
Equll)ment Run
814
Insrr. Install.
814
815 Insulate
815 Calibrate
875 Electr. Install
999 Paintin!]
999 Conirnlssioning
MH
Work Crew
600
12,000
7,000
5,300
10,600
10,600
7,000
3,500
7,000
10,600
1,000
1,000
12,000
3,200
2,000
21,000
4,000
4,000
15
25
22
22
22
22
22
22
22
22
25
25
25
20
25
40
16
25
Work Days
5
60
40
30
60
60
40
20
40
60
5
5
60
20
10
65
30
20
Flgure 12-2 combines the above data into a theoretical bar chart. This
chart will show the major activities, indicating theoretical manpower for
each. and adding this into a combined manpower loading.
The reader should be well aware that this is a theoretical example and
that 111 real life all foundations do not have to be complete before equipment
,lnd butldlng erection start. Detailing the bar chart in Figure 12-2 shortens
the overall construction span considerably by phasing activities for the most
logical and economical sequence of construction.
Second, examine equipment deliveries. Figures 12-1 and 12-3 show the
scheduled delivery for equipment and when it is required at the site. For
long deliveries. this schedule helps calculate escalation, indicates if
equtpment delivery must be expedited, and shows what will happen if the
dellvery IS late This will help management decide if additional money
should be expended to accelerate delivery. If float or delay time is available,
dellvery of equipment could be delayed without affecting the overall
schedule
Figure 12-1
208
Third, the schedule is the base for the project status report. The planner will update his schedule on a delivery basis. The percent complete is
compared wrth the cost to date, then the remaining work is re-estimated in
lrght of costs to date. This is the reason for the simultaneous updating of
project cost and schedule.
209
I I may be helpful to the reader who is not too familiar with scheduling to
have a brief descriptron of terms used in this chapter.
l
. Early Start
l
Late Start - The latest date at which an activity can start without
Jeopardizing the overall schedule.
Critical Path - If the float is zero, or the early start and late start
are the same, then the activity is critical. The critical path itself
runs through the string of activities with zero float. Note that a
project could have more than one critical path.
Positive or Negative Float - If the late start is later than the early
start, then the activity has a positive float equal to this difference.
If, on the other hand, the late start is past and the activity has not
started, the float is negative. If this slippage cannot be eliminated,
then the completion of the project will be delayed by the days of
the negative float.
Restraint - This is a dummy activity, like 813-680 on Figure 12-1.
indicating that insulation cannot start before event 813 is complete.
Floating or Dangling Activity - An activity that is not connected to
a successor event.
Loop-A string of activity where the finish of one will be connected
to a start event of a predecessor event - forming a loop. A
computer will stop computing a network which has a loop.
Milestone - A significant completion point, such as 812 in Figure
12-l. The piping is complete so that pressure testing can start.
Preparing a Network
A milestone network should be prepared before the cost estimate, but it
should only be expanded after the estimate is completed. This way the
schedule activities parallel those of the estimate. Again, Figure 12-3 could
be used to illustrate this point. Assuming that the project consists only of
pumps A and B, vessel B, column C valves and piping. This is,
of course, incomplete but it will help illustrate the point. This data is taken
from the estimate. Using the milestone network, it is expanded to show the
activities and the time required to purchase and deliver to the site the
required equipment. Similarly, Figure 12-1 is developed for the construc-
ad
tion phase. Note that Figure 12-1 and 12-3 are not really related since they
are only partial.
It 1s important to cover all the important activities shown in the estimate.
It was seen above how one calculates the durations for the activities
shown. If a Pert/Cost network is used, thecost of the corresponding activity
IS included in the network and the computer program. This information,
combrned with the percent complete and actual cost to date, is an excellent
tool for forecasting the cost of the project.
Time is Money
Successful engineering and construction firms do not leave for tomorrow
what must be done today. A slippage in issuing engineering specification,
for example, could mean more engineering manhours and a higher cost. It
may also mean a delaved purchase of equipment and thus a higher cost.
Thus could cause other delay in the field and thus create more slippage in
the project schedule. Schedule slippage may require adjustments in staff,
hours worked or completion date - always at higher cost. Delays may push
some work from good weather into bad and result in a tremendous loss of
effrclency Any of the above can make the difference between success or
failure on any project.
Slrppage in the completion date means higher cost for the lump-sum
contractor, unhappy clients, lost revenue for the owner, and inevitably harm
to some good reputations. Everyone in construction should understand how
time and money, cost and schedule, are related.
You should try to find the optimum balance between time and money.
Most projects could be built without errors and without risk, but few owners
cou!d afford the cost or the time. It may be true that there is no problem that
money cannot cure, be it accelerating schedules, or rearranging
construction logic. But no owner can afford the waste required to perform
the impossible. Every project has an ideal mix of cost and schedule. Cost
engtneers arecharged with finding that right combination for management.
Simulation
One of the many advantages of a computerized schedule is that it can be
used for simulation. It was mentioned earlier that Figure 12-1 is only a
theoretlcal network. This is because activities usually follow each other
more smoothly than shown. Manpower mobilization and demobilization do
not follow a straight vertical line, but follow the shape of the datedcurve
Instead In addition, the network as shown in Figure 12-l represents the
longest possible duration for construction and thus is the most expensive.
211
272
physical completionis 50% and cost is 75% of budget, you are going to have
a cost report that forecasts an overrun for the particular activity. The
average for all theactivities shows the total percent complete, the cost, and
is the basis for the new forecast. You may alS0 Want to Cakukde the cost Of
crash schedules: What will the cost be if overtime scheduling, shorter
ttme duration or more people are used for a particular activity or group of
actlvlties?
Your schedule of manpower requirements is the primary scheduling
tool. It should show the total manpower required for the construction by
traae ano oy mor~tr,. ~~UIII ~1113 yvu tiaII ucIIvuIuI~ . .,_ w... __... _. __r_. ..-._
requrred, based on established supervision-to-craft ratios. Based on the
total projected manpower, you can calculate what temporary construction
facilities are required and when they are needed. Your manpower schedule
will show when training and hiring must be completed for each trade so you
have men ready for productive work when required.
Make it Simple!
Simptrcity is essential to the work of the scheduler. YO U m u s t
understand that your schedule will be used by many others, including those
_,I.. ___,__
kr. JLII~~~~~?:
rrb~~r(,,lnl hn\rnnn
of the
_. _
wno __.
actually
LVII~~UI1 lLII~
-,,,v,,..u,i+h
..,,,,21. haqip
YI1._blndprq+nndinn
_ ..__._._.. _ __.=
project components should be able to follow the sequence of events depicted
wrthout more than a few minutes of indoctrination on the signs, symbols
and methods you use. Every well-prepared schedule must be simple
enough so that it can be used by those who contribute to the timely
completion of the project. There can not be a successful project without a
general understanding of the schedule.
It is hard to draw a line between simple and complicated. Too many
details will be confusing and time-consuming - too few will not serve the
control purpose. Every scheduler must find the limits which are acceptable
...
to those in line, staff and management posntons.
Types of Schedules
There are m a n y planning and scheduling systems in use. Distinct
systems have been developed in many firms. The basic principles in most Of
-.___ ___
_:_:,__ D*_;.-.,+ *;Tp ,av+nnt n f rlcaeird riptails .qnd end
tnese sysrerr~s
dre ~IIIIII~I rlV,cbL allr, uI\LIIII -a YY_,, _.. __._.._, __._ _.._
use of the schedule dictate the exact system which is most appropriate.
The schedule should ensure that nothing important, or maybe even
nothing less than slightly important, is overlooked. All activities necessary
to meet the established objectives must be clearly visible. Some schedules
. . ~___ _I .L^ :_rl:.,:rl..r, rmrnenrihla fnr ncarh lie+& >p+ivi+v
even snow rne name 01 true IIIUIVIUU~I I=J~uv~~I~~~ IvI ~I, IILIU U.....,
Most schedules have only activities indicated by department code. Dont
213
274
215
Milestones
By float available
Figure 12-4
-.-
START
JOB
OMPR. A
XCHANGERS
'UFPS
:OMPR
VALVES
MECHAN:CAL
INSTR.
cIv!L
iLiCT?!CfiL
._.~
211
219
REQUEST FOR
TIME CONTINGENCY
Engineering
and
Procurement
TRANSFER
Construction
PROJECT NO.
DATE
TRANSFER
1 Year
CALENDAR WORKING
TO
ACTIVITY
Figure 12-6
The first phase cannot take longer than one year without jeopardizing
the schedule for the second phase, as shown in Figure 12-7.
Engineering
and
Procurement
1
I
~~
Construction
~--15Months
9 Months - -
DAYS
DAYS
TO
~.. ~_
2- WOULD NECESSITATE CHANGE IN LOGIC TO
ACTIVITY
,~--------- c
FROM
DAYS
TO
DAYS
4- WOULU CAUSE A DELAY IN PRDJFCT COMPLFTION
Months+
Idelay
OF
DAYS
Figure 12-7
If phase one is expanded, the only alternative is a slippage in phase two.
This could apply to the entire project or t0 any tW0 activities in Series.
The example does not necessarily involve time contingency because
there may not have been any contingency to begin with. It could, however,
be used to demonstrate the principle that no activity should exceed its
allotted time limit without approval. For the type of situation described
above, and for activities with time contingency, a system for controlling
time contingency transfers should be implemented.
The importance of contingency allowances in estimating cost is well
understood and many systems have been designed to calculate amount and
use the funds. Chapter 7 was devoted entirely to this subject. The concept of
time contingency transfer is not so well understood. The form for this
transfer is shown in Figure 12-8. Every major activity has a certain duration
which is shown in the network diagram. Manual or computer calculations
determine each activity float. This float is the amount of time contingency
available for completinp the activity. Another time contingency allowance
.-.--
REQUESTED BY:
DATE
REVIEWED BY-
DATF
APPROVED BY:
DATE
Figure 12-8
220 {
IS
221
222
Updating should cover all project activities that could have an effect on
the schedule:
l
Process engineering
Design engineering
Other purchases
Subcontracting
223
OATE:
PROJECT -
Iam1600-
80 -
loo-
70 -
1*w-
Ooo800.
6M)ON
200
10
,I
10
12
Some payments for equipment and field activities are based on actual
percent complete. An accurate status report will be very valuable.
The schedule engineers one page graphic representation of the status
of the project can be more helpful than a several hundred page report. A
single chart can show the scheduled completion VS . actual completion,
projected manpower vs. actual manpower, projected construction manhours
vs. actual manhours, and other indicators of schedule compliance. A single
chart can summarize the overall project status or that of a selected activity.
One such chart is shown in Figure 12-9.
Schedule updating and projections are as important as cost control and
forecasting. The two functions form the basic control mechanism for the
progress of the project.
Updating Overseas Projects
Updating and controlling the schedule of an overseas project presents
many of the same problems as cost control for a domestic project. The
basic problem will be the coordination of worldwide activities, delays in
communications, problems with expediting, labor productivity and delays in
shipping and handling cargo. Most of those factors are considered in the
Pre-estimating survey and should have been allowed for in the schedule.
Allowing for a coordination problem in the schedule is one thing; measuring
the effect of that problem on performance is another.
Daily communications, constant monitoring and realistic forecasts are
all important in any control mechanism. In overseas projects problems are
magnified by distance, the many control centers, use of several languages,
varying work attitudes and less understanding than at home that time is
money.
Policing Progress Control
Any scheduling system, regardless of how simple, is just another control
system and must survive resistance, discredit and sometimes even attempts
at elimination. Scheduling control is even more difficult to implement than
cost control. Cost is part of financial management and, as such, receives the
direct scrutiny of management and financial departments. In scheduling the
scheduler must tell others what to do, when to do it, ask why it is not done,
and when it will be done. It is direct interference and people will not
voluntarily cooperate in any scheme that imposes outside restraints on
them. Moreover, management may be more willing to let the schedule
224 (
13
Cost Analysis
And Data
DQVQiOpmQnt
Case Study
NJIT
Case Study
Contingency allocation
Project Schedule
Development
Engineering
Procurement
NJIT