Catalyst unloading and loading project

Project Procedure

STEP 01. UNLOADING CATALYST FROM REACTOR


1.

Isolate Reactor by close Manual valve inlet & outlet

2.

Evacuation gas inside Reactor to flare until pressure 0 bar

3.

open top Manhole of Reactor

4.

Install equipment Catalyst unloading machine

5.

Suck out catalyst powder to vacuum drum then drain to big bag

6.

Remove big bag if full and change by new one

7.

Repeat step 5 & 6 until catalyst in the Reactor is empty

8.

Record total big bag catalyst from reactor

STEP 02. SCREENING CATALYST


1.

Separation old catalyst by screen machine and save in the big bag

2.

Record catalyst good size and off spec. size (30 60 %)

3.

Replace off spec size catalyst with new ones, total = 100 %

STEP 03. LOADING CATALYST TO REACTOR


1.

Preparation crane on the site, man power on the Manhole top reactor

2.

Lift up big bag of catalyst by crane to top Reactor then pouring into Manhole

3.

Arrangement catalyst in the reactor until all big bag are complete pouring

Ref. No. :

TECHNICAL PROPOSAL

Issued Date: 03 Sep 2013


Rev. 0

Industrial Cleaning Services Co., Ltd.

Step 01. Unloading Catalyst

Step 02. Screening Catalyst

Page: 2

Ref. No. :

TECHNICAL PROPOSAL

Issued Date: 03 Sep 2013


Rev. 0

Industrial Cleaning Services Co., Ltd.

2.

Equipment and Tool List

Catalyst unloading Machine


Crane 25 Ton
Screen Machine
Hose 3
Lighting 24 VDC
Gas Detector
Electricity Control Panel
Key & tools Box
Wet Suite
Rag
Hand Gloves
Dust masks
Consumable

=
=
=
=
=
=
=
=
=
=
=
=
=

1
1
1
30
1
1
1
1
1
1
1
1
1

Unit
unit
unit
m
Set.
Unit.
Set.
lot
Lot.
Lot.
Lot.
Lot.
Lot.

=
=
=

1
1
6

person
Person
Person

3. Man Power loading


Foreman
Safety Officer
Operator

4. Customer Scope of supply


-

Electricity 3 phase (380 V, 50 Hz)


Plant Air (PA)
Water
Forklift
Pallet