Академический Документы
Профессиональный Документы
Культура Документы
Project Report
On
Goregaon, Mumbai.
In Partial Fulfillment of
By
“Dr. M. S. Kadam”
2008-2010
ACKNOWLEDGEMENT
Last but not the least, I would like to forward my gratitude to my friends &
other faculty members who always endured me and stood with me and
without whom I could not have completed the project.
DECLARATION
2
CONTENTS
page
Sr. no. Topic no.
ACKNOWLEDGEMENT
EXECUTIVE SUMMARY
1 Chapter 1: INTRODUCTION
1. A Concept & context of the study
1. B Objectives of the study
1. C Scope & limitation of the study
BIBLIOGRAPHY 81
ANNEXURE 83
COLLEGE
4
CERTIFICATE
COMPANY
5
CERTIFICATE
EXECUTIVE SUMMARY
Summer training is an integral part of the course curriculum for the degree of
MASTER OF BUSINESS ADMINISTRATION. It provides valuable
The knowledge I have gained has been presented in the form of report has
been made in a manner such that it is easy for the reader to know maximum
details in minimum time.
Chapter 1
INTRODUCTION
Maintenance
1) Safety:
3) Economic Losses:
1) Corrective Maintenance
10
2) Preventive Maintenance
2) Preventive Maintenance:
OBJECTIVES
PRIMARY OBJECTIVES:
SECONDARY OBJECTIVES:
12
13
Due to the following unavoidable and uncontrollable factors, the result might
not be accurate. Some of the problems faced while are as follows:-
of the individual.
14
Chapter 2
PROFILE OF THE
ORGANIZATION
15
Handling of fly ash and slag are done from closed bunkers to silos directly.
Separate weigh-batchers are provided for each ingredient like cement, water,
admixtures and aggregates.
Processes are in place for effective and periodic maintenance and calibration
of all critical components. Laser sensor and moisture control are used for a
stringent quality assurance.
17
Well trained and experienced engineers are available at every plant to take
care of the quality of concrete.
Vision
Mission
Values
Integrity
Commitment
Passion
Seamlessness
Speed
18
HISTORICAL BACKGROUND
19
Development in India
In India RMC plant arrived in 1950’s and use was
restricted to only major construction projects such as, Bhakra dam was the
first projects were RMC was used. Later on RMC was used for other large
projects such as construction of long span bridges, industrial complexes etc.
The first RMC plant was set up in Pune in 1993.
20
and consumers. The ingredients of good and bad concrete are the same. The
difference lies in the technology used for production, transportation and
placement. The making of concrete is an art as well as a science. Science
because all the ingredients are proportioned as per the standard codes of
practice to get the targeted strength & durability, and an art because in
addition to accurate proportioning, quality of concrete depends on the way it
is mixed, placed, compacted, finished, cured and protected. Ready mix
Concrete (RMC) technology results in a perfect blend of the Art and
Science.
21
ORGANIZATIONAL CHART
PLANT
INCHARGE
22
Ordinary M15 PCC e.g. Leveling course, bedding for footing, concrete
roads, etc.
M20 RCC (Reinforced Cement Concrete) e.g. Slabs, beams,
columns, footings, etc. (for mild exposure)
M25 RCC (Reinforced Cement Concrete) e.g. Slabs, beams,
columns, footings, etc.
M30 RCC e.g. Slabs, beams, columns, footings, etc.
M35 RCC e.g. Slabs, beams, columns, footings, etc.
M40 RCC e.g. Pre-stressed concrete, slabs, beams, columns,
Standard
footings, etc.
M45 RCC e.g. Runways, Concrete Roads (PQC), Prestressed
Concrete Girders, RCC Columns, Prestressed beams
M50 RCC e.g. Runways, Concrete Roads (PQC), Prestressed
Concrete Girders, RCC Columns, Prestressed beams
M55 RCC e.g..Prestressed Concrete Girders and Piers
23
24
25
AWARDS
Clients have consistently endorsed UltraTech's highest quality standards. The
list of awards it has won is testimony to UltraTech's uncompromising
standards on product quality.
National awards
26
Chapter 3
RESEARCH DESIGN
&
METHODOLOGY
RESEARCH DESIGN
27
A research design is a framework for conducting the research project. It details the
procedure necessary for obtaining the required information, and its purpose is to design a
study that will test the hypothesis of interest, determine possible answers to research
questions and provide the information needed for decision making.
Formulating the research design involves the following steps:-
Primary data is the first hand information obtained by investigator. Primary data can be
collected by observation, by interviews, by face to face questioning, by using
questionnaire, when the needed data does not exist or are out-dated, inaccurate,
incomplete, or unreliable.
28
Secondary data is collected by others already and the researcher is using that information
for his own research purpose. Secondary data can be collected from published reports,
newspaper, websites, and journals, publications of national and international organization.
It was obtained from:
3. Sample Description
The sample includes 8 elements viz., the compressor, mixer & other
components of RMC plant etc.
29
Chapter 4
CONCEPTUAL
BACKGROUND
THEORETICAL BACKGROUND
DEFINITION:
30
Θ Maintenance encompasses all those activities that maintain facilities & equipment
in good working order so that a system can perform as intended.
Θ Maintenance can also be termed as asset management system which keeps them in
optimum operating condition.
THEORY:
Because such items and other devices are common at ready mix
operations, manufacturers may not provide specific maintenance instructions for them. It
is necessary, therefore, to determine the best schedule for these components based on
experience and other recommendations. It should be kept in mind that safety is crucial
when maintenance is being performed. Employees should be instructed to lock out
equipment that is being worked on, tag it, and notify other employees in the work area
that maintenance is under way. Many accidents can be prevented if all employees at the
plant is made aware of maintenance procedures being done.
31
Preventive Maintenance
The care and servicing by personnel for the purpose of maintaining equipment and
facilities in satisfactory operating condition by providing for systematic inspection,
detection, and correction of incipient failures either before they occur or before they
develop into major defects.
To make it simple:
• Preventive maintenance is conducted to keep equipment working and/or extend the life of
the equipment.
• Corrective maintenance, sometimes called "repair", is conducted to get equipment
working again.
CONCEPTUAL DESCRIPTION
To keep the plant in excellent working order at minimal cost decision makers have two
options: - CORRECTIVE or PREVENTIVE MAINTENANCE.
The best approach is to seek a balance between preventive maintenance and breakdown
maintenance as shown.
33
TOTAL PREVENTIVE
COST MAINTENANCE
COST
DEMAN
D
CORRECTIVE
MAINTENANCE
COST
OPTIMU
M
AMOUNT OF PREVENTIVE
MAINTENANCE
Long-term effects and cost comparisons usually favor preventive maintenance over
performing maintenance actions only when the system fails.
Preventive maintenance is a logical choice if, and only if, the following two conditions
are met:
• Condition #1: The component in question has an increasing failure rate. In other
words, the failure rate of the component increases with time, thus implying wear-
out. Preventive maintenance of a component that is assumed to have an
exponential distribution (which implies a constant failure rate) does not make
sense!
• Condition #2: The overall cost of the preventive maintenance action must be less
than the overall cost of a corrective action. (Note: In the overall cost for a
corrective action, one should include ancillary tangible and/or intangible costs,
such as downtime costs, loss of production costs, lawsuits over the failure of a
safety-critical item, loss of goodwill, etc.)
If both of these conditions are met, then preventive maintenance makes sense.
Additionally, based on the costs ratios, an optimum time for such action can be easily
computed for a single component.
35
36
Chapter 5
DATA PRESENTATION
& ANALYSIS
MIXER
CHECKS TO BE DONE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Check all hydraulic lines
& cylinder
Discharge gate & chute
to be cleaned
37
(i) On the 1st three days one of the arm protector rubbers was found to be damaged &
was brought to notice on the 1st day itself. Although it was not repaired the plant
functioned accurately.
(ii) On the 4th day the mixer seal was found damaged & was brought to notice on the
1st day itself. Although it was not replaced the plant functioned accurately.
(iii) One of the showels was found damaged on the 4th day & was brought to notice
on the 1st day itself. Although it was not replaced the plant functioned accurately.
COMPRESSOR
CHECKS TO BE DONE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Check the condition
of V-belts
38
(i) On the 10th day a cut was found on one of the V-belts & was brought
(ii) The oil level was found to be below normal on the 11th day & was
(iii) No other problems were encountered with the compressor during the
15 days.
ADDMIXITURE
CHECKS TO BE DONE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Check connection of
threaded union for leaks
Cleaning of pipes, motor &
jars with fresh water
Checking of foot valves
39
(i) Addmixture pipe was found to be damaged on the 2nd day, which
leaded to slow charging of addmixture. It was repaired on the same
day.
(ii) On the 9th day the motor pipe was found to be leaking & was brought
to notice. It was repaired on the same day.
SKIP BUCKET
CHECKS TO BE DONE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Check wire rope condition
& apply compound
Check for wear & tear
& proper working
40
discharge gates
(i) The ready mix discharge gate was found to be damaged on the
12th day & was brought to notice. Although it was not replaced the
plant functioned accurately.
(ii) The Gear-Box oil level was found to be below normal on the
14th day & was brought to notice. The correct oil level was
maintained.
WATER PUMP
CHECKS TO BE DONE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
42
(i) Overflow pipe was found to be damaged & was brought to notice.
(ii) Cement hopper was found to be damaged & was brought to notice.
AGGREGATE
CHECKS TO BE DONE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Check wear & tear of bins
if any
Check vibrators in
aggregate hopper
Check if load is evenly
distributed on load cell
Cleaning & checking of
aggregate holding hopper
Check aggregates gates
for smooth working
Check pneumatic cylinder
for leaks
43
(i) Load cell stud was found broken on the 8th day. It
was brought to notice & repaired.
(ii)On the 10th day the CRUSH SAND GATE was found
to be broken. It was removed & welded.
SAFETY
CHECKS TO BE DONE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Check limit switches
44
(i) The mixture was not working on the 10th day as the limit switch stopped
functioning. The problem was conveyed & was solved on the same day
itself.
(ii) All the labors & the workmen were equipped with safety helmets, safety
shoes & safety jackets on all the 15 days.
(iii) The motors were protected with safety covers & functioned well with
intermediate preventive maintenance.
Chapter 6
FINDINGS,
SUGGESTIONS &
CONCLUSION
45
FINDINGS
1. Most of the equipments at the Goregaon RMC plant are well maintained
& function to the desired level.
3. Except for the arm protector rubber & over flow pipe no major
maintenance problems were recorded.
5. Unsafe conditions are eliminated through planned & regular inspection &
lubrication procedures.
46
SUGGESTIONS
1. The arm protector rubber & the overflow pipe require immediate
attention or if these defects not corrected on time may cause
malfunctioning of the equipment or result in the breakdown of the plant,
or be a reason for hazards.
2. Although the absence of foot valves did not make any difference it would
be tolerable to have them.
47
CONCLUSION
Today’s plants are regarded as high technology plants. These plants, compared to plants
of past years are bigger in capacity involve high speed machinery, complex & precise
designs, more automation & therefore pose difficulties in maintenance.
In lieu of large capital investment, downtime cost of these plants is enormous. Since
machinery & its arrangement are engineered for continuous production, stoppage /
malfunctioning / breakdown of a single machine can cause stoppage of the whole plant.
With the advancement of technology, production function is getting simplified day by day
due to built-in automated controls, while maintenance function is getting complex,
increasingly difficult & important for survival.
All machines tend to deteriorate in performance with use over the period due to the
process of wear & tear. A number of factors contribute to the functional degradation of
the machines of which typical ones are: temperature rise, vibrations, looseness, seasoning
of parts, accumulation of dust, rusting of parts etc.
48
Systematic maintenance though can’t eliminate the process of wear & tear yet it can
significantly lower it. A good maintenance system is therefore not a luxury but a
necessity.
BIBLIOGRAPHY
Books
New Delhi
Websites
49
1. www.adityabirla.com
2. www.ultratechconcrete.com
3. www.wikipedia.com
50