Академический Документы
Профессиональный Документы
Культура Документы
DATE
REV.
DOC. No.
P 0520
SPEC AC 01
1 OF 16
PREPD Angga
CHKD
SULISTYONO
APPD
SERVICE AREA
TECHNICAL SPECIFICATION
FOR JET FAN
PROJECT
SHOW ROOM PORCHE
M&E CONSULTANT
PT. COMETINDO MITRA INTI
REV.
DATE
PAGE
DESCRIPTION
PREPD
CHKD
APPD
03 AUG 2007
ALL
BAHAR
SULISTYO
TRI
JOB No.
DOC. No.
P 0520
SPEC AC 01
REV.
SHEET 2 OF 716
TABLE OF CONTENT
15010
15015
DOCUMENTATION
15020
WORK INCLUDED
15054
10
15724
VENTILATING FANS
14
9910
PRODUCT SPECIFICATION
16
FAN WORK
SECTION 15010:
JOB No.
P 0520
DOC. No.
SPEC AC 01
REV.
SHEET 3 OF 716
PART 1 GENERAL
1.0
GENERAL CONDITIONS:
A. All sections under this Division shall be subject to the requirements of the conditions of
contract for fan works and sSection 15010 of these specifications.
B. The term Supplier" shall mean the Ventilation Works Supplier who shall enter into a contract
with the Owner in respect of the Fan Contract Works.
C. The term "Engineer" shall mean the Engineering Consulting firm hired for the project, which
is, PT. Skemanusa Consultama Teknik.
1.1
GENERAL DESCRIPTION:
2.1
The work to be done under this Division of the Specifications consist of the fabrication.
2.2
The Supplier before submitting this proposal, shall examine all technical specification
and equipment schedule to his work and verify all governing conditions at site and shall
become fully informed as to the extent and character of the work required. No
consideration will be granted for any alleged misunderstanding of the materials to be
furnished or work to be done, it being understood that the submission of a proposal is
an agreement to all items and conditions referred to herein or indicated on the
accompanying drawings and actual site conditions. If specified equipment/instruments
are not locally available, Supplier must immediately place an order as soon as project is
awarded. Any exceptions, omission or substitutions shall be presented in writing with
the Supplier's bid.
C. The Supplier, before commencing work, shall examine all adjoining areas on which this work
is in any way dependent for perfect workmanship according to the intent of this specification
and shall report to the Owner's representative any condition which will prevent this Supplier
from performing first class work. No waiver of responsibility for defective work will be
considered unless notice has been filed at the time this Supplier submits his proposal.
D. It is the intention of these Specifications to call for furnished work tested and ready for
operation. Whenever the word "provide" is used, it shall mean "furnish and install, complete
and ready to use". Certain terms such as "shall, provide, install, complete, start-up" are
occasionally not used in some parts of these specifications. This does not indicate that the
items shall be less than completely installed or that systems shall be less than complete.
Minor details not usually shown or specified, but necessary for the proper installation and
operation, shall be included in the work, the same as if herein specified or shown.
1.2.
REFERENCE
A. The work under this contract is to be installed according to the latest requirements of the
following:
1. Peraturan daerah (local regulation)
2. Dept. PU (Departemen Pekerjaan Umum)
Nothing contained in these Specifications or shown on the drawings shall be constred as to
JOB No.
P 0520
DOC. No.
SPEC AC 01
REV.
SHEET 4 OF 716
conflict with National and Local Ordinances or Laws governing the installation of Fan Work,
and all such laws and ordinances are hereby made part of these specifications. The Supplier
is required to meet the requirements thereof.
B. Codes and standards of the following organizations other than mentioned above are
referenced in this Divison. The Supplier shall comply with these codes without additional cost
or compensation:
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
1.11
1.3.
QUALITY ASSURANCE
A. Surveys and Measurements:
The Supplier shall base all measurements, both horizontal and vertical, from established
bench marks. All work shall agree with these established lines and levels. Verify all
measurements at site and check the correctness of same as related to the work.
Should the Supplier discover any discrepancy between actual measurements and those
indicated, which prevents following good practice or intent of the drawings and specifications,
he shall notify the Owner's representative and shall not proceed with his work until he has
received instructions from the Owner's representative upon referring the matter to the
Engineer.
1.4.
SUBMITTALS
A. Submit materials and equipment by manufacturer, trade name and model number. Include
copies of applicable brochure or catalog material. Do not assume applicable catalog are
available in the Engineer's office. Maintenance and operating manuals are not suitable
substitutes for shop drawings.
B. Identify each sheet of printed submittal pages (using arrows, underlining or circling) to show
applicable sizes, types model numbers, ratings, capacities and options actually being
proposed. Cross out non-applicable information. Note specified features such as special
tank linings, pump seals, materials or painting.
C. If submittals differ from the Contract Document requirements, make specific mention of such
difference in a letter of transmittal, with request for substitution, together with reasons for
same.
1.5.
COORDINATION
JOB No.
P 0520
DOC. No.
SPEC AC 01
REV.
SHEET 5 OF 716
1.6.
A.
Certain materials will be provided by other trades. Examine the Contract Documents to
ascertain these requirements.
B.
Carefully check space requirements with other trades to insure that materials can be
installed in the spaces alloted including finished suspended ceilings.
GUARANTEE
a. This Supplier shall guarantee that the Fan is free from all defective workmanship and
materials and will remain so for a period of one (1) year from date of final acceptance as
certified by the Owner's representative.
Any defects, appearing within the aforesaid period shall be promptly remedied by the Supplier
his own expense.
b. The Supplier shall indemnify and save harmless the Owner, and the Engineer from and
against all liability for damages arising from injuries or disabilities to persons or damage to
property occasioned by any act or omissions of the Supplier including any and all expenses,
legal or otherwise which may be incurred by the Owner, or the Engineer, in defense of any
claim, action or suit.
PART 2 PRODUCTS
2.1.
2.2.
JOB No.
P 0520
DOC. No.
SPEC AC 01
REV.
SHEET 6 OF 716
DESIGN CONDITIONS
A. Jet Fan
a. System without duct required
b. Material Fan :
Casing
Impeller
Shaft
c. Fan completed with bell mouth accessories (inlet cone) & Jet Nozzle (oulet).
PART 3 EXECUTION
3.1.
Fans are capable of operation with alarm controls functional and automatic controls in
operation, generally.
JOB No.
DOC. No.
P 0520
SPEC AC 01
REV.
SHEET 7 OF 716
certificates obtained.
Noise and vibration control devices including flexible connections and written report
submitted.
B. Prior to this inspection, provide complete list of items which are not finished or deficient at the
time of the scheduled inspection.
C. Prior to the final inspection, provide in writing that previously identified deficiences and the
following items have been completed.
1.
2.
3.
4.
3.2.
START-UP
a. Properly lubricate pieces of equipment.
b. Prepare each piece of equipment in accordance with manufacturer's installation instructions
and have a copy at the equipment.
c.. Check rotation on each motor.
d. Have representatives of each manufacturer present when hereinafter specified, so that
equipment will be started up by manufacturer.
e. Test requirements under section on Tests shall be performed prior to approval of the work.
SECTION 15015:
DOCUMENTATION
PART 1 GENERAL
1.1.
SCOPE OF WORK
A. Work Included
1. Operating and Maintenance Manuals
JOB No.
P 0520
DOC. No.
REV.
SPEC AC 01
SHEET 8 OF 716
1.2
SUBMITTALS
A. Submit two copies of draft for operating and maintenance manuals for review and approval
prior to final issuance at least one month prior to turn over seminar .
B. Submit documents to the Engineer for approval prior to transmitting to the Owner
1.3
TURNOVER SEMINAR
A. Organize and conduct a seminar to instruct the Owner and his representatives in the
operation and general preventive maintenance of equipment and systems provided at the
completion of the project.
B. Instruct Owner's operating personnel in proper starting sequence, operation, shutdown, and
maintenance procedures, including normal and emergency procedures.
C. Make arrangements to give instructions by system and not by building areas.
D. Provide services of qualified personnel, including each sub-trade, each major equipment
supplier and design Engineer to attend seminars and instruct on his equipment or system.
Seminar shall be chaired and conducted by the Contractor.
E. Submit agenda schedule and list of representatives to the Engineer for approval thirty (30)
days prior to seminar. Confirm attendance of seminar by written notification to participants.
F. At seminar, submit final copies of record drawings and operating and maintenance manuals
to Owner.
G. Submit a written record of the seminar, complete with an attendance list to the Engineer.
JOB No.
P 0520
DOC. No.
SPEC AC 01
REV.
SHEET 9 OF 716
SCOPE OF WORK
Under this Division of the Specifications, provide all materials and equipment and perform all the
work necessary for the complete execution of all the Fan as shown on the equipment schedule
as herein specified or both, except as otherwise excluded, and which without excluding the
generality of the foregoing, shall include but not be limited to the following principal items of work.
A. Work Included
A. Supply Fan
B. If anything has been omitted in any item of work or materials usually furnished, which are
necessary for the completion of the Fan as outlined herein before, then such items must
be and are hereby included in this Division of the Work. The Supplier shall prepare all
plans, applications, etc. and shall complete all tests, forms, etc. required by all rules,
regulations, etc. of all the Government Authorities having jurisdiction and such shall be
completed by personnel of proper caliber, in particular, engineers, where so required.
B. Work Excluded
1. Installation of access doors in plaster or metal frames in finished construction (By AR).
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
SCOPE OF WORK
JOB No.
DOC. No.
P 0520
SPEC AC 01
REV.
SHEET 10 OF 716
A. Work Included:
1. Installation supervise.
2. Adjust and balance systems as specified.
3. Provide data register as required
4. Provide System Report.
1.2.
SUBMITTALS:
A. Outline of methods proposed for testing and balancing.
B. List of instruments proposed for use in testing and balancing.
C. Reports:
1. Submit draft copies of final report for review prior to final acceptance of the Project. Provide
final copies for the Owner's Representative and Contractor for inclusion in operating and
maintenance manuals.
2. Include diagrams when required to clarify location of components readings within a
system. See section 15015 for other requirements.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
3.1.
3.2.
PREPARATION WORK:
Before starting balancing the Supplier shall make sure that each operation listed below has been
satisfactorily completed.
Pressure and leak testing of air systems as specified. All testing will be witnessed by the
Owners Project Representative.
Prime movers such as fans have been operated, at specified loads and checked for
misalignment, imbalance, excess vibration, improper rotation or motor overload. Correct all
deficiencies prior to balancing.
BALANCING WORK:
JOB No.
P 0520
DOC. No.
SPEC AC 01
REV.
SHEET 11 OF 716
A. Calibration:
1. Provide verification of the accuracy of the instruments, meters and devices used for
balancing. Show date and method of calibration.
2. Verification of permanently installed meters and devices may be by calculation and
calibration, or by independent measurement of the same flowing medium with calibrated
devices.
B. General Balancing Procedures:
1. Test and balance the air systems with maximum attainable internal load (lights and
equipment).
2. Test and balance the air systems before the water systems.
3. Use only direct flow measurement. Do not use indirect calculations such as heat balance
or pressure drop.
4. Adjust systems and equipment to specified installation tolerances.
5. Except for air outlets and inlets, where actual measurements recorded for the final
balance show deviation of more than 5 percent from the design and the deviation cannot
be corrected by balancing with the installed layout and elements, note this deviation in the
final report, with recommendations for corrective action.
6. On fan system controlled by static pressure, ensure by testing and recording, that devices
are calibrated to perform in accordance with contract documents and provide design
static pressure at the most demanding location. Furnish and coordinate static pressure
set point of controls.
7. Verify that thermostats and the devices they control, operate as intended and in the
sequence specified.
8. Establish correct fan RPM.
3.3.
INSTALLATION TOLERANCE:
A. Adjust air systems to 5 percent from figures indicated.
B. Adjust air terminal units to within the following tolerances from schedule air flows.
C. Adjust air terminal units for minimum leakage at design close off.
D. Adjust air terminal devices (outlet and inlets) to 5 percent between rooms except that multiple
devices on the same system branch within each room may be adjusted to 10 percent.
3.4.
ADJUSTING:
A. Recorded data shall represent actually measured, or observed condition.
B. Permanently mark settings of valves, dampers and other adjustment devices allowing
JOB No.
P 0520
DOC. No.
SPEC AC 01
REV.
SHEET 12 OF 716
3.6.
DATA:
A. Obtain and provide data for following:
1. Supply air fans.
2. Return air fans.
3. Exhaust fans.
B. Data Required:
1. Location Data:
a. Building and floor.
b. Unit number.
c. unit service.
JOB No.
DOC. No.
P 0520
SPEC AC 01
REV.
SHEET 13 OF 716
2. Design Requirements:
a. cfm.
b. Static pressure across fan.
c. RPM.
d. Motor brake HP.
3. Nameplate Data:
a. Manufacturer.
b. Model and Size.
c. Arrangement, discharge and class.
d. Motor HP, volts, phase, cycles, and full load amps.
4. Field Test:
A.
Fan CFM.
B.
Inlet static pressure.
C.
Discharge static pressure.
D.
Total static pressure.
E.
Total Air Pressure.
F.
Air horse power.
G.
Fan RPM.
H.
Motor rpm.
I. Motor volts and amps
J.
Motor horsepower.
K.
Damper position.
C. Record data and transmit to Owner's Project Representative.
3.7.
3.8.
JOB No.
P 0520
DOC. No.
SPEC AC 01
REV.
SHEET 14 OF 716
SCOPE WORK
A. Work Included
General: Provide ventilating fans in accordance with the Contract Documents.
B. Related Section:
Section 15010: Ventilation and Air Conditioning General Provisions
Section 15170: Electric Motors
1.2.
REFERENCE
1. Safety Provisions and Regulations by Local Labour Codes.
2. Regulations issued by Ditjen Bina Lindung (Depnaker)
1.3.
QUALITY ASSURANCE:
A. Manufacturer: Firm regularly engaged in manufacture of ventilating fans of types and sizes
required, whose products have been in satisfactory use in similar service for not less than 5
years.
B. Installer: Firm with at least 5 years of successful installation experience on AC work projects
similar to this project.
1.4.
SUBMITTALS:
A. Product Data: Submit manufacturer's product data and installation instructions for each
product specified for ventilating fans.
B. Submit brochures/catalogs of centrifugal fans and accessories for approval, before they are
released to order.
1.5.
COORDINATION
A. The Supplier shall coordinate the work with all appropriate sections of the specifications as
necessary to insure proper provisions for the work of this section.
B. Coordinate installation of centrifugal fans.
1.6.
GUARANTEE
A. All equipment, materials and workmanship shall be guaranteed by the Supplier for a period of
one year from the date of final acceptance. Upon receipt of notice from the Owner's Project
Representative of any failure during the guaranteed period, the affected part of work shall be
replaced promptly by the Supplier at his expense.
B. The guarantee shall not extend to damages incurred through improper operation and
maintenance by the Owner. The Owner shall assume full responsibility for proper operation
JOB No.
P 0520
DOC. No.
SPEC AC 01
REV.
SHEET 15 OF 716
ACCEPTABLE MANUFACTURERS
See Outline Specification attached.
2.2
CERTIFICATION
All fans shall carry the Air Moving and Conditioning Association (AMCA), JIS or Equal
performance and construction seal for air and sound.
PART 3 - EXECUTION
Refer to the equipment schedules for fan type and selection information and confirm exact
installation requirements for each fan system with the plans and details.
JOB No.
P 0520
DOC. No.
SPEC AC 01
REV.
SHEET 16 OF 716
1.1.
GENERAL
Material and equipments should fulfill the specification. Contractor allows suggest other similar
and equal alternative within the specification. Contractor allows changing if there is any formal and
written approval.
NO
A
1
DESCRIPTION
Main Equipment
Fan
Jet Fan Type
SPECIFICATION
Ecta, Pro-Jet, TLT