Академический Документы
Профессиональный Документы
Культура Документы
Chart of accounts.
Work breakdown structure.
Universal accounting standard.
Standard accounting practices.
Team member.
Customer.
Stakeholder.
Supporter.
236
End of Year
Cash Flow In
1
2
3
4
5
0
300,000
400,000
100,000
50,000
500,000
90,000
100,000
175,000
35,000
50,000
-50,000
850,000
100,000
6. If the net present value for each of the cash ows were calculated at a
10% interest rate, the net present value cash ow at the end of ve
years would be:
a. Greater than the total cash ow without the net present value applied.
b. Less than the total cash ow without the net present value applied.
c. The same as the total cash ow without the net present value applied.
d. Cannot be calculated with the information supplied.
7. A group of related projects that are managed in a coordinated way that
usually include an element of ongoing activity is called a:
a.
b.
c.
d.
Major project.
Project ofce.
Program.
Group of projects.
8. During the full life cycle of the project, a plot of the projects expected
expenditures will usually follow a characteristic S shape. This indicates that:
a. There is a cyclic nature to all projects.
b. Problems will always occur in the execution
phase. c. There are high expenditures during
closeout.
d. The bulk of the project budget will be spent in the execution phase.
9. A temporary endeavor undertaken to create a new product or service is
called a:
a.
b.
c.
d.
10. A project manager makes a narrative description of the work that must
be done for her project. This is called a:
a.
b.
c.
d.
Project plan.
Control chart.
Statement of work.
Project objective.
Strategic planning.
Contingency planning.
Detailed planning.
Management by objectives.
15. A project manager is creating a work breakdown structure for her project. In the breakdown structure the lowest level of the breakdown for
the project manager is called the:
a.
b.
c.
d.
Activity.
Task.
Work package.
Cost account.
16. A project manager is reviewing the scope of the project and the scope
baseline of the project. This includes which of the following?
a. The original project schedule, budget, and scope
b. The original project description and the project charter
c. The original scope of the project plus or minus any scope
changes d. The current budget of the project
17. A project manager has just become the manager of a project. The
docu- ment that recognizes the existence of the project is called:
a.
b.
c.
d.
18. A project manager is reviewing the work breakdown structure for her
project. The WBS for the project represents:
a.
b.
c.
d.
Project manager.
Project expediter.
Program coordinator.
Program manager.
20. A new project has begun. The project charter has been written and the
project manager has been assigned. The project manager is preparing
the work breakdown structure for the project. The WBS is typically
used for:
a.
b.
c.
d.
21. During the life of a project, the project will go through several phases
initiating, planning, execution, and closeout. Which phase of the project is likely to have the greatest amount of its funding spent?
a.
b.
c.
d.
Initiating
Executing
Planning
Closeout
22. During the course of the project it is important that the stakeholders be
informed of the progress of the project. One of the reports that is frequently used is a progress report. Which of the following is true about
progress reports?
a. They allow stakeholders to judge the performance of the project
according to its plan.
Project charter.
Project.
Set of project objectives.
Program.
The
The
The
The
project plan.
project goals and objectives.
project charter.
project denition.
Projectized organization.
Strong matrix organization.
Weak matrix organization.
Balanced matrix.
26. A project manager has been asked by the client to meet the promise
date of the project. The project manager analyzes the schedule before
promising a date to the customer. The project manager uses the program evaluation and review technique to evaluate the project schedule.
She decides that based on the results of the PERT calculations she can
promise a delivery date of June 30. The expected value of the project
completion date is May 30. If the project manager is willing to accept
a
5% probability that the project will be delivered later than June 30,
what is the standard deviation of the durations of the activities on the
critical path? Assume a ve day work week.
a.
b.
c.
d.
Ten days
Fifteen days
One-half month
One month
27. A project is proposed to a customer. Price and schedule for delivery are
agreed upon. The work breakdown structure is agreed to as well. The
customer requests that one of the milestones of the project be
completed by a certain date. The project schedule is reviewed, and it is
found that the expected completion date for this milestone is
considerably earlier than the date requested by the customer. The date
for this milestone is which of the following?
a.
b.
c.
d.
Consideration
Summary activity
Constraint
Suggestion
$100,000
$114,500
$117,000
$119,500
29. In a very large project having a budget of $5 million and a project team
of over one hundred persons, the project manager constructs a work
breakdown structure. The project manager will do the WBS to the
detail level of which of the following?
a.
b.
c.
d.
Task
Activity
WBS element
Work package
30. A project manager is managing a project that has reached the end of
the planning phase. The work scope has been agreed to and denitive
cost estimates have been completed for the project. The total estimated
cost of the project is $100,000. It is reasonable to expect that the
project will not cost over which of the following values?
a.
b.
c.
d.
$100,000
$110,000
$125,000
$175,000
31. The change management plan should be included in which of the following?
a.
b.
c.
d.
32. A project team has made up the work breakdown structure for a project.
Senior management for the company and all of the stakeholders including the client have approved the WBS. The client later requests that a
change be made in the project, which will cost a considerable amount
of money. The client says that the companys salesman promised this
feature prior to sign off on the WBS. Who should pay for the change?
a.
b.
c.
d.
Scope Management
243
c.
$45,555 d.
$91,110
34. A project manager is managing a project during the planning phase.
She chooses to use a precedence network diagram as a graphic
planning tool to assist in making the project schedule. The most
important reason for using the network diagram as a graphic planning
tool is that it makes it easier to see which aspect of the project plan
better than the other tools available?
a.
b.
c.
d.
The
The
The
The