Академический Документы
Профессиональный Документы
Культура Документы
Pre-construction Preparation
4.1 Review Plans
Record Keeping
13
In The Field
14
Staking
15
Curve Data
20
22
24
Reference Points
27
30
32
Pre-Construction Preparation
Section 4.1
Review Plans
Bridge Plans
January, 2013
Pre-Construction Preparation
Section 4.1
January, 2013
Pre-Construction Preparation
Section 4.1
Contract Documents
Include:
Plans
Standard Specifications
Supplemental Specifications
Special Provisions
Change Orders
January, 2013
Pre-Construction Preparation
Section 4.1
___
Project Plans
___
Standard Drawings
___
___
___
Special Provisions
___
Supplemental Specifications
___
___
___
January, 2013
Pre-Construction Preparation
Section 4.1
January, 2013
Pre-Construction Preparation
Section 4.1
Field Testing
(00540.16)
Sample &
Test Per
MFTP
January, 2013
DESCRIPTION
OF
TEST
TEST METHOD
ODOT
SECTION
EXCAVATION AND BACKFILL
SECTION 00510
00540 - STRUCTURE
CONCRETE BRIDGES
Aggregate Production
Sampling
(1)
Reducing
QAE may waive
(2)(3)(4)
after 5 sublots/shifts
Sieve Analysis
(4)
Fineness Modulus
(2)
(1)(3)
TM 225
Perform a minimum of 3 tests
Wood Particles
(4)
Sand Equivalent
(3)
Coarse Aggregate
(See Section 02690.20)
Soundness
Abrasion
(4)
Degradation
TM 208
Fine Aggregate
(See Section 02690.30)
Lightweight Pieces
Organics
(3)
(3)(4)
Bulk Specific
Gravity & Absorption
Portland Cement
Fly Ash
Admixtures
(C)
WAQTC
FORM
734-
Contractor
Quality
Control
AASHTO
1792
T 176
1792
T 104
T 96
4000
1/Sublot
&
Start of Production
See Section 4A
T 113
T 21
T 19
T 84 &
T 85
Compliance
Compliance
Compliance
4000
1825
1825C
1825
Start of production
and when changes
in aggregate occurs
4000
(C)
4000
Not required if
on QPL
Mixing Water
QUALITY ASSURANCE
Independent Assurance/Verification
Project
Region
Materials
Quality
Laboratory
Manager
Assurance
Compliance
Page 17
10 % of
Required QC
Submit To Lab
See Section
4A
DESCRIPTION
OF
TEST
TEST METHOD
ODOT
WAQTC
FORM
734-
AASHTO
Contractor
Quality
Control
SECTION
EXCAVATION
AND BACKFILL
SECTION 00510
00540 - STRUCTURE
CONCRETE BRIDGES
(CONTINUED)
Portland Cement Concrete
Sampling
Air Content
Slump
Concrete Temperature
Density (Unit Weight)
Yield
Water/Cement Ratio
Strength
(S)
(M)
TM 2
T 152
T 119
T 309
T 121
T121
T 121
T22/23
3573WS
or
4000C
(M) (S)
Test at
minimum
frequencies
according to table
00540-1. Review
specs.
4000C
QUALITY ASSURANCE
Independent Assurance/Verification
Project
Region
Materials
Quality
Laboratory
Manager
Assurance
QA Testing Metric
Projects under 100 m all classes
1/Project representing all classes of PCC
Projects over 100 m all classes
1/400 m per class minimum 1/class
QA Testing English
Projects under 100 yd all classes
1/Project representing all classes of PCC
Projects over 100 yd all classes
1/500 yd per class minimum 1/class
Page 18
Pre-Construction Preparation
Section 4.1
QC Testing Frequency
January, 2013
Pre-Construction Preparation
Section 4.1
QA Testing Frequency
January, 2013
Pre-Construction Preparation
Section 4.1
January, 2013
The most current version of this guide is available by printing from the web address listed below. This
document is to be used as a guide for documentation required for acceptance of materials on ODOT
Construction projects and does not relieve the user of requirements specified in the Construction Project
Documents. Please notify the Contract Administration Unit, In the Construction Section at the ODOT
Materials Laboratory, of any changes in Standard Drawings, Special Provisions, or Specifications, etc.,
which would require additions to, deletions from, or changes to this listing.
Internet Address: http://egov.oregon.gov/ODOT/HWY/CONSTRUCTION/docs/NFTMAG2008.pdf
ACCEPTANCE DOCUMENTS
SECTION
TYPE OF CONSTRUCTION
MATERIALS
SUBSECTION
FURNISHED BY
CONTRACTOR
TO
LAB
BY
MATERIALS
LAB
REMARKS
BY
FIELD
PM
This Guide provides a summary of acceptance documents for frequently used items. New materials or materials which are infrequently used may
not be listed in this Guide. Consult the Contract Documents for acceptance documentation for these items.
This Guide does not have precedence over the Special Provisions, Contract Plans, or Standard Specifications.
E - Equipment Lists and Drawings / Procedures
L - ODOT Materials Laboratory or Inspection Report
W - Warranty (Manufacture or Workmanship)
ACCEPTANCE DOCUMENTS
SECTION
TYPE OF CONSTRUCTION
MATERIALS
SUBSECTION
FURNISHED BY
CONTRACTOR
TO
LAB
00520
00530
Driven piles
BY
MATERIALS
LAB
REMARKS
BY
FIELD
PM
00512.14(a)
00512.14(b)
00512.14(c)
Steel piling
02520.10
T,O
Splices
00520.43g
02520.10(e)
Q,O
02520.10(e)
T,O
02120.20,
02190
02120.30
Q,O
02520.20
Concrete reinforcement
00520.10
Bar reinforcement
(From Approved Manufacturer
on QPL)
02510.10
Q,O
L*
10 of 34
ACCEPTANCE DOCUMENTS
SECTION
TYPE OF CONSTRUCTION
MATERIALS
SUBSECTION
FURNISHED BY
CONTRACTOR
TO
LAB
Manufacturer on QPL)
REMARKS
BY
FIELD
PM
T,O
02510.11
BY
MATERIALS
LAB
Q,O
T, Q,
O
00530.42
02510.20
Q,O
Welded Splices
00532.42(d)
Note: A maximum of 30 yd of each size of welded wire fabric used for guardrail anchors, culvert end slopes, and misc. small structures may be accepted as
Small Quantity. O and F is required for acceptance.
Welded wire fabric (except slope
paving)
02510.40
11 of 34
Q,O
NFTMAG Exercise
Determine Required Acceptance Documents
Situation: You are the inspector on a bridge project which will be placing
cast in place footings, columns and deck. The reinforcement required
includes uncoated black reinforcement and coated reinforcement.
_________________________________
While checking the deck reinforcement you have determined the contractor
is short of the required number of uncoated black reinforcing bars. Two
days later the required black reinforcement bars arrive on site but are NOT
on the ODOT QPL. What Acceptance Documents are required in this case?
_________________________________
Pre-Construction Preparation
Section 4.1
Pre-construction Conference
Hold pre-construction conference prior to
any work beginning.
Should be held within 30 days of the
notice to proceed.
January, 2013
10
Pre-Construction Preparation
Section 4.1
Contractor Submittals
Work schedules
Traffic control plans
Subcontractor approvals
January, 2013
11
Pre-Construction Preparation
Section 4.1
Working Drawings
Approved submittals required for the
following:
Shoring, cribbing, or cofferdams
Falsework and load bearing forms
Prefabricated items
Post-tensioning
Fabricated steel items, and
Reinforcing steel
Plans
Keeping up with the latest information . . . .
BID PLANS
WORKING PLANS (SHOP
DRAWINGS & SUBMITTALS)
AS-BUILT PLANS
January, 2013
12
Pre-Construction Preparation
Section 4.1
Record Keeping
January, 2013
13
Pre-Construction Preparation
Section 4.1
In the Field
On-Site Familiarization
Determine the locations of existing utilities.
Note any features or circumstances that
may require special attention such as
wetlands or endangered species habitat.
Ensure the proper implementation of the
traffic control plan.
January, 2013
14
Pre-Construction Preparation
Section 4.1
Staking
Staking Responsibilities
Determined by Contract
Agency provided
construction stakes, lines
and grades
Contractor provided
construction stakes, lines
and grades
January, 2013
15
Pre-Construction Preparation
Section 4.1
January, 2013
16
Pre-Construction Preparation
Section 4.1
Staking
Horizontal alignment
Centerline stakes
Reference points
Vertical alignment
Benchmarks
TBMs
Grade stakes
January, 2013
17
Pre-Construction Preparation
Section 4.1
Horizontal Alignment
Start with running in centerline
Set control points
(Curve points, POTs, etc.)
Set abutment and bent centerlines
where possible
Set reference points
For abutment and bents where
possible
January, 2013
18
Pre-Construction Preparation
Section 4.1
Distances
Lengths are divided into 100 foot long sections
called stations.
Interval stakes along an established line are
ordinarily laid down at 100 foot intervals called
full stations.
If a marker stake is placed elsewhere along the
line, it is called a plus station.
January, 2013
19
Pre-Construction Preparation
Section 4.1
Curve Data
January, 2013
20
PI
T
L
M
C
PT
PC
Radius Point
Figure 48
R=
5729.578
D
5729.578
R
T = R*Tan 2
C = 2R*Sin 2
M = R(1-Cos 2 )
100 R
L = D = 180
R
E = ( Cos /2 )-R
13-4
D=
Pre-Construction Preparation
Section 4.1
Staking Checks
Measure Chord Distances
(Bent Checks)
Measure Middle Ordinates
(Edge of Deck Checks)
Curve Data
/ L = D / 100ft
= The Subtended Angle Of The Curve
D = Degree Of Curve
(Subtended Angle Of 100 Of Arc)
L = Length Of Curve
R = Radius Of Curve
= D(L) / 100ft
R = 5,729.578 / D
January, 2013
21
Pre-Construction Preparation
Section 4.1
Trig Functions
O
Sin = O / H
Cos = A / H
Tan = O / A
January, 2013
22
Pre-Construction Preparation
Section 4.1
Chord Distance
C
Sin( ) = C / R
R Sin( ) = C
2R Sin( ) = C
Bent 1 @ 10+00
Bent 2 @ 12+00
What is the chord distance between Bents 1&2?
L = (12+00)-(10+00) = 200ft
= D(L)/100ft = 10o(200ft)/100ft = 20o
R= 5,729.578 / D = 5,729.578 / 10o = 572.958ft
C = 2R Sin(1/2 )
C = 2(572.958ft)Sin(1/2(20o)) = 198.99ft
January, 2013
23
Pre-Construction Preparation
Section 4.1
January, 2013
24
PI
T
L
M
C
PT
PC
Radius Point
Figure 48
R=
5729.578
D
5729.578
R
T = R*Tan 2
C = 2R*Sin 2
M = R(1-Cos 2 )
100 R
L = D = 180
R
E = ( Cos /2 )-R
13-4
D=
Pre-Construction Preparation
Section 4.1
Cos( ) = A / R
A = R(Cos( ))
C
R
M=R-A
M = R - R(Cos( ))
Middle Ordinate = R(1 - Cos( ))
D = 10o
January, 2013
25
Pre-Construction Preparation
Section 4.1
Reference Points
January, 2013
26
Pre-Construction Preparation
Section 4.1
Reference Points
Reference points or offset stakes are
usually 2x2x14 wood stakes (hubs)
driven flush with ground surface
A tack or small nail on the top of the wood
stake marks the exact reference point
At least two permanent points should be
set for each abutment
January, 2013
27
Pre-Construction Preparation
January, 2013
Section 4.1
28
Pre-Construction Preparation
January, 2013
Section 4.1
29
Pre-Construction Preparation
Section 4.1
January, 2013
30
Pre-Construction Preparation
Section 4.1
January, 2013
31