S.NO

NAME OF WORK
1 External clearance
2 Texture
3 plumbing ducts incl. primer
4 Electrical, communication & Fire shafts incl. white wash
5 Lift shafts
6 other shafts
7 UPVC windows
8 2nd coat putty in flats
9 Balance tile works
10 Kitchen granite & dado
11 Staircase and corridor 1st coat putty
12 Staircase and corridor tiling

NOTE: The above scheduled can be achieved only when the man power of civil contractors

ESTIMATED DATE
C-BLOCK
D BLOCK
25-Mar-16
31-Mar-16
8-Mar-16
12-Mar-16
9-Mar-16
31-Mar-16
20-Mar-16
30-Mar-16
12-Mar-16
20-Mar-16
15-Mar-16

Remarks

31-Mar-16
5-Apr-16
15-Mar-16
7-Mar-16
18-Mar-16
31-Mar-16 Staging materials required
30-Mar-16 Material reqd at site
- D block POP work very slow
25-Mar-16
20-Mar-16 Granite required at site
15-Mar-16
Staircase tile material reqd at site

n the man power of civil contractors should be increased