Вы находитесь на странице: 1из 36

Eurocodes:

Background & Applications


GEOTECHNICAL DESIGN with worked examples

13-14 June 2013, Dublin

Worked examples
HYD and
d UPL li
limit
it
states
Dr. Bernd Schuppener
German Federal Waterways Engineering and
Research Institute, Karlsruhe
Past Chairman of CEN TC250/SC 7

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Worked example:
Verification of uplift of a base slab
in an excavation

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Example: verification of failure by uplift UPL


H=10
H
10 m
LSPW =15 m
D = 1,0
10m

Uk
a = 10 m; b = 5 m

k = 32,5

conrete = 24,0 kN/m

= 10 kN/m

Steel d = 2,34 kN/m

Waterpressure: Uk = H w b a = 5000 kN
3

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

EN 1997-1: 2.4.7.4 Verification of uplift


(1)P Verification for uplift (UPL) shall be carried out by checking
that the design value of the combination of destabilising
permanentt and
d variable
i bl vertical
ti l actions
ti
(Vdst;d) iis lless th
than or
equal to the sum of the design value of the stabilising
permanent vertical actions (Gstb;d) and of the design value of any
additional resistance to uplift (Rd):

Vdst,d Gstb;d + Rd

(2.8)

where

Vdst,d = Gdst;d +Qdst;d


(2) Additional resistance to uplift may also be treated as a
stabilising permanent vertical action (Gstb;d).
)
4

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

UPL partial factors and model factor


Factor type

Factor

EN 1997-1 German NA
and DIN
1054

Irish NA

Permanent unfavourable
action

G;dst

1.0

1.0

1.0

Permanent favourable action

G;stb

09
0.9

09
0.9

09
0.9

Variable unfavourable action

Q;dst

1.5

1.5

1.5

Angle of shearing resistance

1.25

1.25

1.25

Pile tensile resistance

s;t

1.4

1.4

2.0

Model factor on wall


resistance

0.8

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

UPL- verification with the weight of the structure only


For the verifications the following quantities are needed:
Self-weight
g base-slab:
Base-slab: d = 1,0 m, concrete = 24,0 kN/m:
Base-area A = a b = 10,0 5,0 = 50,00 m
Gconcrete = A d concrete
Gconcrete = 50 1,0 24,0 = 1200 kN.
S lf weight
Self
i ht sheet-pile-wall:
h t il
ll dSPW = 0,03
0 03 m, Steel = 78,0
78 0 kN/m
kN/
Weight per unit area: g = 78,0 0,03 = 2,34 kN/m,
GSPW = LSPW 2
2 (a +b) g
g = 15302,34
15 30 2 34 = 1053 kN
Total characteristic weight of the structure:
Gk = Gconcrete + GSPW = 1200 + 1053 = 2253 kN
6

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

UPL-verification with the weight of the structure only


G

U
Required: Vdst,d Gstb;d + Rd

eq (2.8)
eq.
(2 8)

Vdst,d = Ud Gd
Uk G,dst Gk G,stb
But: 5000 1,00 = 5000 kN > 2253 0,90 = 2028 kN
H
Hence
UPL requirement
i
t nott satisfied!
ti fi d!
7

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

UPL-verification including wall frictional resistance R

U
Vdst,d Gstb;d + Rd
Ud Gd + Rd
Uk G,dst
G dst (Gk + Rk) G,stb
G stb
8

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Verification of failure by uplift UPL frictional resistance R


The characteristic value of the wall frictional resistance Rk will be
treated as a stabilising action determined as the vertical
component of the characteristic active earth pressure reduced by
a model factor of = 0,80:
Rk = Eah,k tan a
Th wallll ffriction
The
i ti angle
l iis assumed
d tto b
be k = 2/3 k. For
F
horizontal surface area and vertical wall the earth pressure
coefficient is Kah,k
, = 0,25 (from Fig. C 1.1 of EN 1997-1 for k=
32.5) and tan a = 0,397. The earth pressure is assumed to act
only on the outer surface of the sheet pile wall:
Eah,k
(a + b)) 0,5
, LSPW Kah,k
ah k = 2 (
ah k
Eah,k = 30 0,5 15 10 0,25 = 8437 kN
Rk = Eaah,k
, tan k
Rk = 8437 0,397 0,8 = 2680 kN
9

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

UPL - including wall frictional resistance


G
R
U
Require: Ud Gd + Rd
Uk G,dst
G dst (Gk + Rk) G,stb
G stb
But: 5000 1,00 = 5000 > (2253+2680) 0,90 = 4400 kN
Hence UPL requirement is not satisfied
10

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Example: Irish verification of uplift failure for UPL


Calculation of Rd
Using k,inf = 32,5
32 5o, i.e.
i e the inferior characteristic value
value, and applying
UPL = 1,25 to the tan(k,inf ) to obtain to d and d, gives a design
wall frictional resistance Rd value that is slightly greater than the
characteristic value Rk, which is not acceptable.
Hence a superior characteristic value k,sup is needs to be used. This is
obtained,
bt i d after
ft B
Bond
d and
dH
Harris
i (2008)
(2008), b
by assuming
i a normall
distribution for and a standard deviation of 3o so that k,sup = 32,5o + 2
1.624 3,0
, = 42.4o. Then applying
pp y g the p
partial factor of 1.25 as a
multiplier to tan(k,sup) gives d,sup = 48.8o and hence an Rd value of
2580 kN with a margin of safety of 1.33 on the characteristic value.
11

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Example: Irish verification of failure by uplift UPL


G

U
Require:

Ud Gd + Rd

Uk G,dst Gk G,stb + Rk G,stb


i.e. 5000 1,00 = 5000 > 2253 0,90 + 2580 = 4608 kN
Hence ULP requirement is not satisfied and tensile piles are required
12

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

GEO partial factors and model factor

13

Factor type

Factor

Irish NA
DA1.C1

Irish NA
DA1.C2

German NA
DA2 + DIN
1054

Permanentt unfavourable
P
f
bl
action, transient situation

G;dst

1 35
1.35

10
1.0

12
1.2

Permanent favourable
action

G;stb

1.0

1.0

1.0

Variable unfavourable
action

Q;dst

1.5

1.3

1.5

Angle of shearing
resistance

1.0

1.25

1.0

Pile tensile resistance

s;t

1.25

1.6

1.4

Model factor on wall


resistance

0.8

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Irish design for GEO verification

Ed Rd

As explained previously,
Rd is obtained using the
superior value so that
for:
= 1,0, Rd = 3440 kN
= 1,25, Rd = 2580 kN

Ed = UkG - Gk G,inf = 5000 G 2253 G;inf


DA1 C1 Ed = 5000 1,35
DA1.C1:
1 35 2253 1,0
1 0 = 4497 kN > Rd = 3440 kN
DA1.C2: Ed = 5000 1,0 2253 1,0 = 2747 kN < Rd = 2580 kN
Hence GEO ULS is not satisfied
14

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Uplift
p - verification with tension p
piles
EN 1997-1
7.6.3 Piles - ground tensile resistance
(3)P For tension piles, two failure mechanisms

shall be considered:
pull-out of the piles from the ground mass;
uplift of the structure and the block of ground
containing the piles.
15

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

GEO - verification with tension piles

LP

Uk
Determination of the
t
tensile
il action
ti F from
f
the structure on the
pile using
p
g ultimate
limit state GEO (DA2)
16

Rt

Ft,d
t d = Ud (Rd + Gd)

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Pile design (GEO) for verification of failure by uplift

Ft,d:
G =
17

F
Ft,d = Uk G - (Gk+ Rk) G,inf

design value of the action on the piles


1.20 for unfavourable actions (according to DIN 1054 for
transient situations: construction period)
G,inf = 1.00 for favourable effects of actions
2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Pile design (GEO) for verification of failure by uplift

U
E1

Ed = UkG - (Gk+ Rk) G,inf

Ft,d = 5000 1,20 - (2253 + 2680) 1,00


Ft,d = 6000 4933
Ft,d = 1067 kN
18

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Pile design (GEO) for verification of failure by uplift


Ed

L
U

Rt,d

19

Driven piles: Ltot = n L, D = 0,5 m, qs,k


kN/m
s k= 35 kN/m
P = 1,40 (DIN 1054)
Rt,d = Ltot qs,k D / P
Rt,d = 39,25 Ltot
2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Pile design (GEO) for verification of failure by uplift


Ft

Uk

Rt
Ft,d Rt,d

eq. (7.12)
(7 12)

1067 39,25 Ltot Ltot 27,2 m


20

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Pile design (GEO) for verification of failure by uplift


1,66 m
la=3,33
3,33 m

3,33 m

la=3,33
3 33 m

10,0 m

3,33 m

x
2,50 m

la=3,33 m
1,66 m
2,50 m

5,0 m
21

Selected:
3 Piles L = 10 m

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Irish pile design for GEO verification of uplift failure

Ed Rd eq.
eq (2.5)
(2 5)

As explained previously,
Rd is obtained using the
superior value so that
for:
= 1,0, Rd = 3440 kN
= 1,25, Rd = 2580 kN

Rt

Ed = UkG - Gk G,inf = 5000 G 2253 G;inf


Rt,d = Rt,k / s;t + Rd = Ltot qs,k D / s;t + Rd
= Ltot 35 0.5 / s;t + Rd = Ltot 54.98 / s;t + Rd
Hence require: Ltot s;t (5000 G 2253 G;inf Rd) / 54.98
22

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Irish pile design for GEO verification of uplift failure

DA1 C1
DA1.C1
U

Ltot

Rt
1.25(5000
5 (5000 1.35
35 2253
53 1.0
03
3440)
0) / 54.98
5 98

Ltot = 24.0
Hence, for 3 piles, each should be 8 m long
23

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Irish pile design for verification of GEO uplift failure

DA1.C2
U
Rt
Ltot 1.6(5000 1,0 2253 1.0 2580) / 54,98 = 4.9m,
Ltot = 4.9m, i.e. for 3 piles, each should be 1.6 m long. Hence design length is 8 m
NOTE:
O
DA1.C1
C controls
co t o s tthe
e des
design
g not
ot DA1.C2
C due to large
a ge balancing
ba a c g forces
o ces
24

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Verification of uplift of structure + ground


bl k containing
block
t i i th
the piles
il
G

Vdst,d Gstb;d + Rd

Ud Gd + Gsoil,d + Rd

Uk G,dst (Gk+ Gsoil,k+ Rk) G,stb

Gsoil

25

(2.8)

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Determination of Gsoil,k according to DIN 1054, 8.5.4

[ (

)]

Gsoil,k = n la lb L 1/ 3 la2 + lb2 cot


N: number
b off piles,
il L = length
l
h off piles
il
la = 5,0 m greater grid distance piles,
lb = 3,33
3 33 m smaller grid distance piles,
piles
= 10,0 kN/m submerged weight soil
= 0,80
, model factor for the weight.
g
Gsoil,k = 3{5,03,33(10
1/3 5,02 + 3,33 2 cot 32,5)}0,810
Gsoil,k = 2740 kN
Model factor: = 0,80
according to DIN 1054!
26

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Verification of uplift of structure + ground


bl k containing
block
t i i th
the piles
il
G

U
Gsoil

27

Ud Gd + Rd + Gsoil,d
soil d
Uk G,dst (Gk+ Rk+ Gsoil,k) G,stb
5000 6906 kN
2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Worked example:
failure by hydraulic heave HYD

28

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

2.4.7.5 Verification of failure by heave


(1)P When considering a limit state of failure due to heave
by seepage of water in the ground (HYD
(HYD, see 10
10.3),
3) it shall
be verified, for every relevant soil column, that the design
value of the destabilising total pore water pressure (udst;d )
at the bottom of the column, or the design value of the
seepage force (Sdst;d) in the column is less than or equal to
th stabilising
the
t bili i ttotal
t l vertical
ti l stress
t
((stb;d) att the
th bottom
b tt
off
the column, or the submerged weight (Gstb;d) of the same
column:

udst;d stb;d
Sdst;d
Gstb;d
d td G
tb d

29

2013 Bernd Schuppener. All rights reserved

(2.9a)
(2 9b)
(2.9b)

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Verification of safety against hydraulic heave


NN - 1,0 m

Sdst,d Gstb,d

NN - 4,0 m
NN - 5,4 m

Medium dense
Sand:
= 10 kN/m

t
NN - 12,0 m

30

b=t/2

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Verification of safety against hydraulic heave


using
i
formula
f
l by
b EAU
h = 4,4 m
h= 1,4 m

hr =

h
hr =
h
3
1+
+1
t
4,4

1,4
1+ 3
+1
6,60

= 2,13 m

t = 6,60 m

i = hr / t = 0,32
u = (t + hr) w
31

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Verification of safety against hydraulic heave


Seepage force Sk:

NN - 1,0 m

Sk = i W V
Effective self weight of
the soil column Gk:
Gk = V

NN - 4,0 m
NN - 5,4 m

Gk
G
NN - 12,0 m

32

HYD Ulimate limit state:


Sk dst Gk G,stb

Sk
2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Verification of safety against hydraulic heave


Table A.17 - Partial factors on actions
(F) Symbol
Action
Value
permanent
unfavourablea
favourableb

G;dst
G;stb

1.35
1
35
0.90

variable
unfavourablea

G;stb

1.50

a
b

33

destabilising;
stabilising

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Verification of safety against hydraulic heave


NN - 1,0 m

Seepage force Sk:


Sk = i W V
Effective self weight of
the soil column Gk:
Gk = V

NN - 4,0 m
NN - 5,4
54m

Gk
G
NN - 12,0 m

34

Sk
S

HYD Ulimate limit state:


Sk dst Gk G,stb
0.32 10 1.35 10 0.90
4.32 9.0

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with
ith worked
k d examples
l

13 14 June,
13-14
J
Dublin
D bli

Safety against hydraulic heave: eq. 2.9b


udst;d stb;d

NN - 1,0 m

NN - 4,0 m
NN - 5,4
5 4 mh= 1,4 m

t = 6,60 m
NN - 12,0 m

stb;d
udst;d
d td

35

uk = (t + hr) w
hr = 2,13m
uk = ((6.60+2.13)10
)
uk = 87.3 kN/m
stb;k = t(+w)
stb;k = 6.60 20
stb;k = 132 kN/m
ukG,dst stb;kG,stb
87.31.35 1320.90
117 9 118.8
117.9
118 8

2013 Bernd Schuppener. All rights reserved

Eurocodes:
Background & Applications
GEOTECHNICAL DESIGN with worked examples

13-14 June 2013, Dublin

Geotechnical design
with
ith worked
k d
examples
eurocodes.jrc.ec.europa.eu

Вам также может понравиться