Академический Документы
Профессиональный Документы
Культура Документы
Title:
Engineering Change
Management Procedure
Unique Identifier:
240-53114002
Alternative Reference
Number:
N/A
Area of Applicability:
Documentation Type:
Procedure
Revision:
Total Pages:
33
January 2016
Disclosure Classification:
CONTROLLED
DISCLOSURE
Compiled by
Functional Responsibility
Authorised by
..
..
..
S. Jagjiwan
W. Majola
M. Koko
Integration Engineer:
Systems Integration (B2B
Assistant Process
Champion)
Date:
Date:
Date:
Unique Identifier:
Revision:
Page:
240-53114002
2
2 of 33
CONTENTS
Page
1. INTRODUCTION ...................................................................................................................................................... 3
2. SUPPORTING CLAUSES ........................................................................................................................................ 3
2.1 SCOPE .............................................................................................................................................................. 3
2.2 NORMATIVE/INFORMATIVE REFERENCES .................................................................................................. 3
2.3 DEFINITIONS .................................................................................................................................................... 5
2.4 ABBREVIATIONS .............................................................................................................................................. 6
2.5 ROLES AND RESPONSIBILITIES .................................................................................................................... 7
2.6 PROCESS FOR MONITORING ...................................................................................................................... 10
2.7 RELATED/SUPPORTING DOCUMENTS ....................................................................................................... 10
3. ENGINEERING CHANGE MANAGEMENT PROCEDURE .................................................................................. 10
3.1 OBJECTIVES .................................................................................................................................................. 10
3.2 ENGINEERING CHANGE MANAGEMENT (ECM) PROCESS ...................................................................... 11
3.3 ECM PROCEDURE ......................................................................................................................................... 14
3.4 DECISION CRITERIA ..................................................................................................................................... 26
4. AUTHORISATION .................................................................................................................................................. 29
5. REVISIONS ............................................................................................................................................................ 29
6. DEVELOPMENT TEAM ......................................................................................................................................... 29
7. ACKNOWLEDGEMENTS ...................................................................................................................................... 30
APPENDIX A : TEMPORARY ECM DOCUMENTATION ......................................................................................... 31
APPENDIX B : EXECUTION ROUTE DECISION CRITERIA ................................................................................... 32
FIGURES
Figure 1 Engineering Change Management Procedure (Overview) ................................................................. 12
Figure 2 Originate Engineering Change .............................................................................................................. 15
Figure 3 Process Engineering Change................................................................................................................ 19
Figure 4 Implement Engineering Change............................................................................................................ 22
Figure 5 Close Engineering Change .................................................................................................................... 24
Figure 6 Close out Engineering Change ............................................................................................................. 25
TABLES
Table 1 CCCC Members .......................................................................................................................................... 9
Table 2 SCCC Members .......................................................................................................................................... 9
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
3 of 33
1. INTRODUCTION
The control and execution of engineering changes on existing assets is critical in ensuring sustainable
performance. All engineering changes must be correctly prepared, motivated, reviewed, approved and
controlled.
This procedure defines a standardised process for all Eskom Generation and Transmission operational
assets that shall be followed for the review, classification and implementation of an engineering change
to existing Eskom assets.
2. SUPPORTING CLAUSES
2.1 SCOPE
The need for an engineering change on an existing Eskom asset must be captured through SAP ECM
(Engineering Change Management) and follow due process for resolution. This procedure provides for
the registration of engineering changes and for reporting on the status of engineering changes while the
actual engineering design work is processed outside of SAP ECM using Eskom engineering governance
practices.
The approach for design reviews shall provide assurance that the systematic evaluation of proposed
solutions adhere to project, regulatory, client, and quality standards and requirements as stipulated in the
Design Review Procedure [4].
2.1.1 Purpose
The overriding purpose for this procedure is to ensure that Eskom assets shall be managed in such a
way as to enable sustainable achievement of its business goals. It must be adopted in order to provide
an effective process for controlling changes to plant, plant structures or technical documentation, and to
manage any changes to a baseline in a controlled manner. Any proposed changes shall be traced
thereby controlling the integrity of the configuration and demonstrate compliance with auditable
traceability.
2.1.2 Applicability
This procedure shall apply to all personnel involved in engineering changes executed on existing Eskom
operational assets within the Generation and Transmission environment, where the design is not
performed using SmartPlant Owner Operator (SPO). All parties interfacing with or working on Eskom
Holdings SOC Limited assets are required to comply.
Note:
This procedure has been developed based on the principles of the automated Control Configuration
Changes PCM that will be rolled out at a later stage. When SPO becomes available, this procedure will
be updated to show the interface between SPO and SAP ECM.
The Eskom Project Lifecycle Model (PLCM) stage gates apply in conjunction with this procedure for all
projects.
2.2 NORMATIVE/INFORMATIVE REFERENCES
Parties using this document shall apply the most recent edition of the documents listed in the following
paragraphs.
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
4 of 33
2.2.1 Normative
[1]
[2]
[3]
[4]
[5]
2.2.2 Informative
[6]
[7]
[8]
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
5 of 33
2.3 DEFINITIONS
2.3.1 Approve: The functional responsible person determines if the document is fit for purpose and
approves the document content and therefore takes responsibility and accountability for the
document content.
2.3.2 Asset/Plant: Machinery, property, buildings, vehicles and other items and related systems that
have a distinct and quantifiable business function or service.
2.3.3 Authorise: The document authoriser authorises the release and application of the document and
is accountable for document implementation.
2.3.4 Baseline: A baseline is a consistent set of plant configuration information or documentation at an
established point in time. This would have been formally reviewed and agreed upon and that would
henceforth serve as the basis for further development that can only be changed through formal
change control procedures (engineering change management)
2.3.5 Design Base: The Design Base of an Asset is the combination of those key design outputs that
define the functions, capabilities, capacities, physical sizes and dimensions (Physical Base), limits
and set points, shutdown and start-up sequences, normal and out of normal operations (Operating
Technical Specification) and maintenance elements (Maintenance Base); that are required for the
asset to meet its required performance, reliability and availability within the limits of the external
constraints.
2.3.6 Emergency Change: Any permanent or temporary change that needs to be evaluated or
assessed and requires immediate response. The change must be implemented immediately (<1
week) in order to prevent imminent system failure, safety, environmental or regulatory risk and
needs to be introduced to prevent system disruption.
2.3.7 Engineering Change: Any permanent or temporary change, deletion or addition to any system,
equipment, structure including permanent changes to operating/protection/control set points,
software and technical documentation which will result in any deviation from the established
Design Base. This includes the replacement of SSC components with equivalent components of a
different make or type.
2.3.8 Engineering Change Classification: The categorisation of an engineering change is dependent
on the level to which it affects safety, the environment, reliability, availability and costs.
2.3.9 Engineering Change Management: Engineering Change Management ensures all engineering
changes are correctly prepared, motivated, reviewed, approved, controlled and recorded.
2.3.10 Engineering Change Prioritisation: Selection criteria as part of the Engineering Change
process that will guide the engineer and the change control committees on the priority of the
engineering change into different levels.
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
6 of 33
2.4 ABBREVIATIONS
Abbreviation
Description
CC
Change Coordinator
CCCC
CRA
DMS
DRA
DRC
EC
Engineering Change
ECM
ECN
ECO
ECR
EDWL
ERA
EWRF
FRA
MoM
Minutes of Meeting
PCM
PECA
PLCM
PM
Plant Maintenance
PRE
Pre-Project Approval
PTE
RACI
ROC
SCCC
SE
SEM
SM
Senior Manager
SPO
SRD
SSC
ToR
Terms of Reference
WAC
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
7 of 33
Change Coordinator
(CC)
Plant Engineering
Change Authority
(PECA)
Design Review
Committee (DRC)
Responsibility
A committee/individual appointed by the Senior General Manager
Engineering. Their responsibilities include:
Authorising the proposed design for Level 1 and Level 2
engineering changes
Authorising the engineering change based on the principles, use of
technologies, and alignment to the process and procedure
Confirming the engineering change impact (change classification,
environmental assessment, risk ranking, priority and technical
content, etc.)
Performing change level classifications
Periodical reviews of audit reports on Level 3 changes from SCCC
The person(s) in charge of managing the permanent or temporary
configuration changes to structures, systems, components or technical
content of prescriptive or descriptive documentation that form part of
the design and/or asset base and updating SAP ECM to reflect the
latest status of an EC. The CC must ensure the minutes/decisions
made by the SCCC and CCCC are recorded on the system and stored
in a central location. All decision documents should be linked to the
ECR on SAP ECM.
The ECSA professionally registered person (engineer/technologist)
with the authority to authorise emergency change requests that arise
outside the normal Engineering Change process. This person ensures
that proper engineering practices and technical governance,
irrespective of the discipline, are followed in this process. This
authority may be delegated to the Site Engineering Manager (SEM)
who will authorise the engineering change but may further delegate
the responsibility to another individual in certain instances (e.g. if the
SEM is not registered or is unable to perform this role)
The members of this Committee responsibilities include:
Concurrence with the design review procedure and processes
applied to the engineering design or engineering change
Ensuring that all design input has been adequately considered. In
particular to ensure that the engineering change has been
adequately reviewed with regard to interface issues between
various disciplines, contractors etc.
Ensuring that all review cycles have been complied to
Making recommendations regarding EC approval
The nomination of additional independent reviewers if considered
necessary
*The COE manager ensures that his/her respective Design Review
Committee (DRC) is in place, properly constituted and representative of all
relevant COE stakeholders as required per End-of-Phase design review and
ensures implementation and compliance to the Design Review Procedure [4].
Engineering Design
Work Lead (EDWL)
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
8 of 33
System Engineer /
Plant Engineer
Engineering Work
Delivery Unit
(Work Allocation Centre)
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
9 of 33
Role
Chairperson
Member
Member
Member
Member
Member
Member
Member
Committee Secretary
Role
Chairperson
Member
Member
Maintenance Representative
Member
Finance Representative
Member
Member
Environmental Representative
Member
Member
Safety Representative
Member
Committee Secretary
Note: This table shows the minimum members for the SCCC, additional members can be included.
The Engineering Design Work Lead (EDWL) will ensure the Design Review Committee (DRC) is formed
with relevant members at the end of each design phase. The DRC members will be appointed based on
the subject matter and disciplines affected. The Work Allocation Centre will assist with the appointment
of the EDWL; however the identification of the resources for DRC will be the responsibility of the relevant
COE Manager Design Review Procedure [4]. The DRC must comply with the Design Review Procedure
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
10 of 33
[4] and include the relevant SE, as well as the site project engineer(s) who will be responsible for the
implementation.
Note: All Committees must operate in accordance with the Terms of Reference (ToR) applicable to them
[2][3].
2.6 PROCESS FOR MONITORING
Compliance to SAP ECM process will be compulsory for all Eskom Generation and Transmission
sites/plants.
All engineering changes will originate and be tracked through SAP ECM. The responsibility to update
status changes on SAP ECM will be plant specific.
Each plant needs to provide and maintain an engineering change folder in an approved document
management database (Hyperwave or legacy DMS) that contains the engineering change
notification/request to be reviewed locally and centrally. All relevant documentation will be linked to
the ECR on SAP ECM.
A report of all Level 1 and 2 engineering changes shall be visible to and managed by the Central
Control Change Committee (CCCC) to facilitate the exchange of information.
Periodically, Level 3 changes authorized by the Site Change Control Committee (SCCC) will be
reviewed by the CCCC.
All designs shall be executed and reviewed according to the responsibility matrix as stipulated in the
Design Review Procedure [4]
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
11 of 33
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
12 of 33
CC CCCC ECN ECO ECR EWR EDWL PTE ROC SCCC SE SRD WAC -
Create ECN
Route ECN
Evaluate ECN
SE Prioritises Change
and Performs Root Cause
Analysis/Investigation/
Assessment
5
Concept Design
Review
(Approve)
5
Create ECR
CC Registers ECR
Change Coordinator
Central Change Control Committee
Engineering Change Notice
Engineering Change Order
Engineering Change Request
Engineering Work Request
Engineering Design Work Lead
Plan Technical Effort
Required Operational Capability
Site Change Control Committee
System Engineer
Stakeholder Requirements Definition
Work Allocation Centre
Concept Design
SE Formalises ROC
6
Review ECR
CCCC: Authorise
Design - Level 1, 2
Design Review
Committee
SCCC: Authorise
Design - Level 3
Approve
DRA
ERA
8
7
Basic Design
SE/EDWL
Completes Design
HOA
7
Basic Design
Review
(Approve)
Design Review
Committee
Detailed Design
SE/EDWL
Completes Design
Detailed Design
Review
10
9
Implement
Design Review
Committee Approve
design
Configuration
Information is
updated
CCCC: Authorise
Design - Level 1, 2
The change is
Implemented and
Commissioned
SCCC: Authorise
Design - Level 3
Approve for Site
Implementation
Level 1, 2, 3
FRA
Finalise
Training is completed
Handover completed
SCCC approves close of
the Engineering Change
Engineering Change is
Closed
Note:
The DRC is made up of the multi-discipline team that is completing the design
and other required members as per design review procedure
The design work can be completed by an external party, however these will
need to be reviewed by Eskom DRC
SAP STATUS UPDATES
Unique Identifier:
Revision:
Page:
240-53114002
2
13 of 33
Any authorised Eskom employee with SAP ECM access can create an Engineering Change
Notification (ECN) (Normal or Emergency). Typically the ECN is created by an operator or
maintenance personnel. There are two types of engineering changes.
1) Normal Engineering Change - Follows the process as illustrated in Figure 1.
2) Emergency Engineering Change - Implemented once authorised by the Plant Engineering
Change Authority (PECA), after which, it follows the normal engineering change process as
illustrated in Figure 1 to evaluate the impact of the change.
2.
The Change Coordinator (CC) enters the employee number and department of the responsible
person (System/Plant Engineer) by updating the ECN in SAP ECM. The CC then notifies the SE of
the Engineering Change Notification (ECN).
3.
The System/Plant Engineer evaluates the ECN by performing a validity check and completing a root
cause analysis/investigation report/impact assessment report. This may have been completed prior
to the engineering change being loaded on SAP ECM. The System/Plant Engineer will ensure the
information is incorporated on SAP ECM. The ECN is then updated with these findings, priority and
basic ECR information.
4.
The CC registers an ECR by entering the ECR information provided in the ECN (Title, reason for
change, and preliminarily classification i.e. Level 1, 2, or 3 according to plant classification - SAP
ABC indicator).
The System/Plant Engineer then defines and completes the Required Operational Capability (ROC).
The SCCC approve the ECR (Level 1, 2 and 3) by:
5.
The System Engineer (SE) will complete the Engineering Work Request Form (EWRF) for the Level
1 and 2 engineering changes and submit the EWRF and ROC to the Work Allocation Centre (WAC).
An Engineering Design Work Lead (EDWL) will be appointed and he/she compiles the Stakeholder
Requirements Definition (SRD) document. The EDWL also plans and compiles or coordinates the
Concept Design. The Concept Design is presented to the Design Review Committee (DRC) who
then approves the design.
6.
The SCCC (Level 3) and the CCCC (Level 1 and 2) reviews the ECR, Concept design and the
supporting documentation and authorises to proceed to basic/detail design.
7.
The EDWL plans and compiles or coordinates the Basic, and/or Detail Design.
8.
After completion the DRC reviews the Basic and/or Detail Design.
The CCCC authorise the Level 1 and 2 Detail Designs prior to the SCCC authorising Level 1, 2, 3
ECRs for implementation.
9.
Configuration Information is verified and corrected, and the SAP ECM Master Data is updated to
ensure it accurately reflects the existing plant after which the change is Implemented and
Commissioned.
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
14 of 33
10. Operations and maintenance staff are made aware of and trained on the changes to the effected
plant. The SCCC approves the close of the engineering change and the engineering change is
closed.
Note: All manual activities for each phase must be completed in accordance with the Project Life Cycle
Model (PLCM).
3.3 ECM PROCEDURE
The ECM procedure consists of Originating, Processing, Implementing, and Close Engineering
Changes.
3.3.1 Originate Engineering Change
The process for originating an engineering change consists of the following four sub-systems: Create
ECN, Route ECN, Evaluate ECN, and Create ECR, as shown in Figure 2.
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line
with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
15 of 33
Change Control
Committee
(Site / Central)
Additional Information
Additional Action
Approve ECR
Documentation
- Priority
- Classification
- Execution Route
- Temporary Change
- Regulatory Impact
- Environmental Impact
Site Change Control
Committee
`
ISSUE
Reject Emergency
Change Approval
Manual Activities
Emergency
Change Form
Reject
Reject
Create Emergency
Change Approval
Emergency
Change Validation
Maintenance or
Engineering
System Engineer
Perform Root
Cause Analysis/
Investigation/
Assessment
Reject
Validate
Approved
Authorise
Emergency
Change Approval
Emergency
Change
Authorisation
Shift Manager
System Engineer
Execute
Emergency Work
Compile Required
Operational
Capability
Maintenance
Required
Operational
Capability
Emergency
AND
Emergency
Decide on validity
of Engineering
Change
Notification
Approve
Perform Root
Cause Analysis/
Investigation/
Assessment
Reject
System Engineer
System Engineer
Process
Engineering
Change
Report
System Engineer
Close Emergency
ECR and Register
new ECN
Reject
Emergency
Provide Required
ECR Information
Normal
OR
AND
Link Required
Operational Capability
to Engineering
Change Request
Link Emergency
Change Form
Put In
Progress
Input required
information from
Emergency ECN
- Description
- Reason for Change
Emergency
Load Engineering
Change
Notification
Register
Emergency
Engineering
Change Request
SAP ECM
IW 22
SAP ECM
CC 32
Change
Coordinator
SAP ECM
IW 22
System Engineer
Change
Coordinator
SAP ECM
IW 22
System Engineer
Responsibility
Matrix
SAP ECM
IW 22
SAP ECM
IW 21
Create ECN
Route ECN
ECN
ECN
SAP ECM
IW 22
SAP ECM
IW 22
Change Coordinator
ECN
ECN
Input required
information from ECN
Classify according to
Plant Classification - SAP
ABC
Change
Coordinator
Evaluate ECN
Update ECR
System and User
status
User: PREP
System: Approve
ECR
SAP ECM
IW 22
Set Execution
Route (Project or
PM WO)
Register
Engineering
Change Request
Cancelation/
Rejection Form
Change Coordinator
Originator
Close ECN
SAP ECM
CC32
Change
Coordinator
SAP ECM
CC 32
SAP ECM
CC 32
Change
Coordinator
Change
Coordinator
Create ECR
ECR
ECR
ECR
ECR
Unique Identifier:
Revision:
Page:
240-53114002
2
16 of 33
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is
in line with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
17 of 33
User status:
o Status: PRE Pre-Project Approval
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is
in line with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
18 of 33
5. The SE provides the CC with the required ECR information. The CC registers the ECR and
links the relevant documentation.
The normal process will be followed through to finalisation.
3.3.2 Process Engineering Change
The process for processing an engineering change consists of the following three sub-systems:
Concept Design, Review ECR, and Design as shown in Figure 3.
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is
in line with the authorised version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
19 of 33
Additional Action
Documentation
Authorisation of Detail
Design (L3)
Authorisation for Site
Implementation (L1,2,3)
Authorisation of Detail
Design (L1,2)
Central Change
Control Committee
1, 2
Authorise Concept
Design (L3)
AND
AND
1, 2, 3
Level 1, 2
Site` Change
Control Committee
Verify
Classification
Level 3
Central Change
Control Committee
Originate
Engineering
Change
OR
AND
Re-classify
to L1 or L2
Work Allocation
Manual Activities
Confirmed L3
AND
Plan Technical
Effort
OR
DRA*
Engineering Work
Delivery Unit
(System Integration)
L 1, 2, 3
Plan Basic
Design
L 1, 2
L3
OR
AND
OR
Establish
SRD
Plan Concept
Design
Compile
Concept Design
AND
Compile Basic
Design
AND
EDWL
Approve/Accept
Detail Design
OR
EDWL
EDWL
EDWL
Compile Detail
Design
AND
Implement
Engineering
Change
Approve/Accept
Concept Design
Stakeholder
Requirement
Definition
EDWL
ERA*
Plan Detail
Design
Approve/Accept
Basic Design
EDWL
EDWL
EDWL
AND
AND
AND
Update ECR
User status
User: CRA
Update ECR
User status
Update ECR
User status
Change
Coordinator
Set Execution
Route
(Project or PM WO)
SAP ECM
CC 32
SAP ECM
CC 32
Ratify
Classification
Change
Coordinator
Change
Coordinator
SAP ECM
CC 32
Change
Coordinator
Load Works
Order
System: Convert
ECR
User: ERA
User: DRA
SAP ECM
CC 32
Update ECR
System and User
status
Update ECR
User status
Update ECR
User status
SAP ECM
CC 32
SAP ECM
CC 32
SAP ECM
CC 32
Change
Coordinator
Change
Coordinator
SAP ECM
CC 32
Change
Coordinator
Link Documentation
& Configuration
Items to ECR
Change
Coordinator
SAP ECM
IW 22
Change
Coordinator
SAP ECM
CC 32
Change
Coordinator
Concept Design
ECR
ECR
Review ECR
ECR
ECR
Design
ECR
ECR
ECR
ECO
Unique Identifier:
Revision:
Page:
240-53114002
2
20 of 33
The concept design is then compiled and the engineering change is re-evaluated to ensure it
was classified correctly.
User status:
o Baseline Status: CDB Concept Design Baseline
The CC must then link all concept design documentation and Committee Minutes of Meeting
(MoMs) to the ECR.
The SCCC/CCCC also evaluates and may update the execution route; if it changes the CC
must update the execution route on SAP ECM to reflect this decision.
Unique Identifier:
Revision:
Page:
240-53114002
2
21 of 33
3.3.2.3 Design
Based on the complexity of the required design work, and recommendation from the
Committees, the EDWL can progress to Basic Design or straight to Detail Design.
The EDWL will plan the Basic Design and present for DRA.
The CC then updates the ECR statuses as follows:
User status:
o Status: DRA Definition Release Approval
User status:
o Baseline Status: BDB Basic Design Baseline
The EDWL will plan the Detail Design and present for ERA.
The CC then updates the ECR statuses as follows:
User status:
o Status: ERA Execution Release Approval
The EDWL will then complete the Detail Design after which the DRC reviews the design. Once
approved or accepted, the relevant committee will authorise the implementation of the detail
design (CCCC - Level 1 and 2, SCCC Level 3). The SCCC must then authorise Levels 1, 2
and 3 for site implementation. Once authorised, the CC links all design documentation and
updates the ECR statuses as follows:
User status:
o Baseline Status: ARB Acquisition Requirements Baseline
CAB Contract Award Baseline
DFB Design Freeze Baseline
IDB Integrated Design Baseline
Unique Identifier:
Revision:
Page:
240-53114002
2
22 of 33
Manual Activities
Update
Configuration
information
Process
Engineering
Change
AND
EDWL
Close
Engineering
Change
Configuration Manager
Implement Solution
AND
Commissioning
Commissioning
Procedure Template
Safety Clearance
Certificate
EDWL
Procurement
Maintenance
Contractor
Link Documentation
& Configuration
Items to ECR
SAP ECM
CC 32
SAP ECM
CC 32
Change
Coordinator
Change
Coordinator
ECO
ECO
ECO
ECO
ECO
Unique Identifier:
Revision:
Page:
240-53114002
2
23 of 33
User status:
o Baseline Status: ABB As-Built Baseline
ACB As-Commissioned Baseline
Note: During the Implementation stage, it may be determined that the baselined detailed design requires
an engineering change/s. When this occurs, the Project Engineering Change Procedure [5] will be
followed to manage the change.
3.3.4 Finalise Engineering Change
The process for Finalisation an engineering change consists of either the Close (Figure 5) or Close-out
of an engineering change (Figure 6).
CONTROLLED DISCLOSURE
When downloaded from the EDS database, this document is uncontrolled and the responsibility rests with the user to ensure it
is in line with the Authorized Version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
24 of 33
Execute outstanding
Operations &
Maintenance
training
Update
Configuration
information
Approve Close of
Engineering Change
Close Engineering
Change Form
Manual Activities
FRA*
No
EDWL
Configuration Manager
END
Training Officer
Yes
No
Implement
Engineering
Change
Configuration
Verification and
Correction
CM Accurate
Yes
Operations &
Maintenance training
executed?
Final Configuration
Control Sheet
Configuration Manager
Training Manager
Complete ECO
User: HOA
User: FRA
SAP ECM
CC 32
Change
Coordinator
Change ECR to
Inactive
SAP ECM
CC 32
Change
Coordinator
SAP ECM
CC 32
Change
Coordinator
SAP ECM
CC 32
SAP ECM
CC 32
Change
Coordinator
Change
Coordinator
SAP ECM
CC 32
Change
Coordinator
ECO
ECO
ECO
ECN (close)
Unique Identifier:
Revision:
Page:
240-53114002
2
25 of 33
Manual Activities
ECR to be Closed
Close ECN/ECR
Cancelation/
Rejection Form
SAP ECM
CC 32
SAP ECM
CC 32
Change
Coordinator
Change
Coordinator
ECR
ECR
Unique Identifier:
Revision:
Page:
240-53114002
2
26 of 33
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is
in line with the Authorised Version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
27 of 33
Level 1
The impact of a change that results in failure on the plant or has an environmental impact or
compromises personnel safety or major equipment damage
Level 2
The impact of a change that results in a decrease of plant availability and reliability
Level 3
All changes which do not meet the criteria for Level 1 or Level 2.
Components within a system shall be classified with respect to the safety function they fulfil and
these may be different from the overall system or equipment classification. Components with
multiple functions shall be classified according to the function that gives the highest safety
classification.
Level 1 plant shall be subjected to more stringent specifications and processes than Level 2 and
subsequently Level 3 plant to ensure that the processes applied are in line with the plant criticality
level.
3.4.2 Committee Review Criteria
In order to ensure the various committees are consistent in their review of ECRs it is imperative
that the correct information is provided. The committee ensures that proper governance has been
followed and the engineering change package has sufficient data for the informed decision to be
made. As a minimum the package should contain the following:
1. A clearly described summary of the problem/deficiency.
2. Insight into the alternative solutions that were considered and an explanation of the alternative
that was selected.
3. The impact of the modification as well as the risks that were identified.
4. Present evidence that the design was approved and has been reviewed by the DRC according
to the design review procedure [4].
5. All assumptions made during the design, irrespective of the stage of the design.
6. All applicable documentation that was identified and updated or deleted for the purpose of the
Engineering Change.
7. Copies of the decision record that contains the required signatures of the relevant power
station.
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is
in line with the Authorised Version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
28 of 33
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is
in line with the Authorised Version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
29 of 33
4. AUTHORISATION
This document has been seen and accepted by:
Name
Designation
D Odendaal
P Moyo
F Sithole
T Mathe
J Fourie
D Bhimma
E Bierman
M Mthembu
J. Hector
L Fernandez
P Madiba
V Pather
G Dudenska
R Cormack
A Jansen
5. REVISIONS
Date
Rev.
Compiler
Remarks
17 October 2012
G Olukune
First Issue
January 2013
1.1
S. Jagjiwan/ D. Fransman
August 2013
S. Jagjiwan
6. DEVELOPMENT TEAM
The following people were involved in the development of this document:
Shamita Jagjiwan
Dustin Fransman
Pieter Meiring
Alida Engelbrecht
Machiel Viljoen
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is
in line with the Authorised Version on the database.
Danie Louw
Grace Olukune
Unique Identifier:
Revision:
Page:
240-53114002
2
30 of 33
7. ACKNOWLEDGEMENTS
N/A
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is
in line with the Authorised Version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
31 of 33
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is
in line with the Authorised Version on the database.
Unique Identifier:
Revision:
Page:
240-53114002
2
32 of 33
CONTROLLED DISCLOSURE
When downloaded from the EDMS, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the Authorised Version on the
database.
Unique Identifier:
Revision:
Page:
240-53114002
2
33 of 33
CONTROLLED DISCLOSURE