Академический Документы
Профессиональный Документы
Культура Документы
Decision Analysis
AY 2016/2017 Term 1
OPIM101
Decision Analysis
AY 2016/2017 Term 1
Q* = $1,018,233.76
Question: WHAT IF demand quadruples (not D but 4D)?
Answer:
a.
2
OPIM101
Decision Analysis
AY 2016/2017 Term 1
b.
60,000 (12,000)(9)
$168,000;
cf
60,000
(12,000)($25)
$300,000;
vTR
vp
3,750
tiresperyear
p cv
25 9
Z $300,000 168,000 $132,000 peryear
REMEMBER: units!!!
c.
2Co D
Cc
2(80)(21,600)
2.4
OPIM101
b)
TC Cc
Decision Analysis
Q
D
Co
2
Q
AY 2016/2017 Term 1
5. Consider a model in which two products, x and y , are produced. There are 100
pounds of material and 80 hours of labor available. It requires 2 pounds of material
and 1 hour of labor to produce a unit of x , and 4 pounds of material and 5 hours of
labor to produce a unit of y . The profit for x is $30 per unit, and the profit for y is
$50 per unit. If we want to know how many units of x and y to produce to
maximize profit, the model is
OPIM101
Decision Analysis
AY 2016/2017 Term 1
cf
25,000
100,000 lbpermonth
p cv .40 .15
7. EOQ
Suppose a gift shop in Myrtle Beach has an annual demand for 15,000 units for a
souvenir kitchen magnet it buys for $0.50 per unit. Assume it costs $10 to place an
order, and the inventory carrying cost is 25% of the items unit cost. Determine the
optimal order quantity if the company wants to minimize the total cost of procuring
this tem. What is the total cost associated with this order quantity? (Ragsdale, Ch.8,
pg 387, no.14)
Answer:
a.
b.
c.
1549
$7,693
Ordering cost = $96.82, Holding cost = $96.82. Total cost = $96.82*2
8. EOQ
BIM Computers Inc. sells its popular PC-PAL model to distributors at a price
of $1,250 per unit. BIMs profit margin is 20%. Factory orders average 400
units a week. Currently, BIM works in a batch mode and produces a 4-week
supply in each batch. BIMs production process involves three stages:
* cost price = $1250/100*80 = $1000; Q = 4*400 = 1600
When the firm wants to change production from one model to another, it
must shut down its assembly line for half a way. The company estimates that
downtime costs one-half hour of supervisory time and an additional $2,000 in
lost production; and wages paid to workers directly involved in changeover
operations. Salaries for supervisory personnel involved amount to $1,500 a
day.
* setup cost (in manufacturing) = $2000 + ($1500 * / 8) same as order
cost in the purchasing setting
Although BIM products are generally regarded as high quality, intense price
competition in the industry has forced the firm to embark on a cost-cutting
and productivity-improvement campaign. In particular, BIM wants to operate
with leaner inventories but without sacrificing customer service. Releasing
5
OPIM101
Decision Analysis
AY 2016/2017 Term 1
some of the funds tired up in outputs inventory would allow BIM to invest in a
new product development project that is expected to yield a risk-adjusted
return of 20%. Assume 50 workweeks in a year, 5 working days in a week and
8 working hours per day.
* carrying cost = 0.20* cost price = $200
a Determine BIMs total annual cost of production and inventory control.
b Compute the economic batch size and the resulting cost savings.
Answer:
a Q = 4 wks supply = 1,600 units, instead of computing the EOQ, u r given
the batch size Q (which may or may not give the lowest cost)
d = 400 units/wk => D = 400*50= 20,000 units/yr,
Purchase cost per unit C = $l,250(l-20%) = $l,000,
Thus, holding cost H = (r+h)C = $200/unit/yr.
Switch over or setup cost S = $2,000 + 1/2hr $1,500/day 1day/8hr =
$2,093.75.
Thus, # of setups per year D/Q = 20,000 / 1600 = 12.5.
Annual setup cost = (D/Q)S = 12.5 $2,093.75 = $26,172
Annual holding cost= (Q/2)H= 800$200= $160,000
Thus, total annual controllable cost TCC(Q) $26,172 + $160,000 =
$186,172
Q*
2 RS
2 20, 000 2, 093.75
647 units.
H
200
b
Annual setup cost = (R/Q*)S = (20,000/647) $2,093.75 = $64,722
Annual holding cost = (Q*/2)H= 323.5$200 = $64,700
Thus, total annual controllable cost TCC(Q*) = $64,722 + $64,700 =
$129,422
TCC (Q* ) 2 RSH 2 20, 000 2093.75 200= $129,422
Alternatively,
Annual savings = $186,172 - $129,422 = $56,750.