Date: 12-08-2016
2) Roofing
Corrugated sheets required for roofing of various structures.
3) Plant backfilling
Excavator 320 and 120 required for progress in desired time.
Backfill required behind raw water tank (condition alarming).
1/3 tractor can used for backfill due to hydraulic jack problem, which is
not sufficient for total backfill required.
4) Switch yard area
Excavator 320 required for back fill (excavator 400 cannot work due to
less working space).
Small size roller required for compaction of switch yard area due to less
working space.
Hand roller and plate compactor required for the compaction and
levelling of switch yard earth and gravel surface.
Trench covers are not decided, whether cast on site or purchase from
local market.
Metering room exact location and construction drawings are not
available at site.
Pumps required for main cable trench drainage.
Fences required for switch yard.