Академический Документы
Профессиональный Документы
Культура Документы
Memorandum
(Pre-Feasibility Report)
Table of Contents
EXECUTIVE SUMMARY .................................................................................. 4
I.
BACKGROUND........................................................................................ 4
1.
BACKGROUND........................................................................................ 8
2.
3.
4.
5.
6.
ANNEXURES ................................................................................................ 25
1.
2.
3.
LIST OF TABLES
Table
Table
Table
Table
1
2
3
4
GLOSSARY
BTG
CPP
FSA
GoM
GSI
IDC
IDFC
IPP
KWH
MERC
MSETCL
NOC
PGCIL
PLF
PSUs
SLC
SPV
Boiler-Turbine-Generator
Captive Power Plant
Fuel Supply Agreement
Government of Maharashtra
Geological Survey of India
Interest During Construction
Infrastructure Development Finance Company Limited
Independent Power Producer
Kilowatt-hour
Maharashtra Electricity Regulatory Commission
Maharashtra State Electricity Transmission Company Limited
No Objection Certificate
Power Grid Corporation of India Limited
Plant Load Factor
Public Sector Enterprises
Standing Linkage Committee
Special Purpose Vehicle
Executive Summary
I.
Background
I.I
I.II
II.
Regulatory Framework
II.I
The regulatory provisions applicable under Electricity Act 2003 and clearances
are as follows.
Page 4
III.
Preliminary Review
III.I Land
III.I.I The proposed site is about 125 km from the City of Nagpur, near the town of
Bhadrawati, in Chandrapur district in the state of Maharashtra. It is
understood that the land for the proposed power project is ~ 1300 acres and
MIDC is in the possession of the entire land (1300 acres).
III.II Water
III.II.I A letter from Department of Irrigation, Government of Maharashtra regarding
the availability of water and assuring that water would be made available to
the Project from the proposed Dindorra Barrage is available with MIDC.
Various options for construction of Dindorra Barrage are being worked out by
the State Government.
III.III
Fuel
III.III.I An application for long term Coal linkage of 6.29 MTPA was made to the
Standing Linkage Committee on 10th March 2008. The Project has been
recommended by CEA for coal-linkage and the recommendation has been
forwarded to Ministry of Power (MoP). MoP vide an office memorandum has
announced policy for granting coal linkages to the projects to be executed
under 12th Plan, which clearly lays down pre-qualification criteria and
weightages for prioritisation of the fuel linkages. This Project, based on
progress achieved, scores well on the criteria defined and would be amongst
the projects with highest marks for allocation of long term coal linkage. MIDC
has been submitting status update on the Project to Ministry of Power as per
their prescribed format, as required by them from time to time.
III.IV Power Evacuation & Transmission
III.IV.I In view of large capacity addition being planned in the region, MSETCL is
already considering putting up a 765 kV High Voltage Direct Current Line from
Chandrapur to Aurangabad to carry the power to load centres.
Page 5
Commercial Viability
IV.I
Tariff
IV.I.I The complete capital cost of the project is estimated at Rs 6586 Crores
including the Interest During Construction. Considering the estimated capital
cost and Landed Fuel Cost of Rs 2360 per Metric Tonne, the levelised tariff at
80% PLF works out to Rs 3.71 per kWh.
IV.I.II The power generated from the project can be transmitted either through
MSETCL grid or through dedicated transmission lines. Considering MSETCL
transmission charges of Rs 7113 per MW per day & transmission losses of
4.24% and the total landed cost for HT consumer (transmission periphery) is
Rs 3.87 per kWh.
IV.I.III The current HT Industrial Tariff in Maharashtra, at 70% PLF, works out to
Rs 7.40 per kWh and Rs 6.72 per kWh for continuous and non-continuous
process industries respectively. Therefore, for non-continuous and continuous
process industries, the Project offers a Delivered Cost basis advantage of 285
paise per unit1 (73% of the current tariff) and 353 paise per unit (91% of the
current tariff) respectively.
1
Page 6
IV.I.IV In view of the above, Chandrapur Project is found to be, prima facie,
commercially viable with improved viability in case a captive coal block is
available.
V.
Implementation Structure
V.I
Page 7
1.
Background
1.1
Introduction
1.1.1 In view of the impending deficit of power availability, MIDC has conceived a
power project that shall encourage capacity addition for supply of power to
industries / licensees to meet their requirements of reliable power, under the
applicable laws.
1.1.2 The state of Maharashtra has been experiencing a deficit of 22.1% in peak
demand and 16.7% in energy (from April 2011 to March 2012). While the
availability is at 9,144 MW, the demand is at 10,981 MW. Going forward in
the 12th plan, the requirement of capacity is estimated to be is ~18000 MW.
This requires an additional capacity of almost 9000 MW in the next four years.
1.1.3 In order to augment the capacity in the state, as well as provide reliable
power industrial consumers and licensees in the state of Maharashtra, MIDC
has contemplated developing the Power Project.
1.2
Page 8
1.3
Pre-Feasibility Study
1.3.1 In order to proceed further on the project, a pre-feasibility study has been
carried out. This report outlines the following.
Page 9
2.
Regulatory Overview
2.1
Page 10
The Regulatory Commissions are quasi judicial bodies constituted under the
Electricity Act, 2003 in order to promote co-ordinated development and
regulation of the power sector, both at the central and State Level. While
the Central Electricity Regulatory Commission is primarily responsible for
overseeing the Central sector utilities, each State Commission is responsible
for regulating the utilities in the State.
2.1.2.3 The Generating Company is not subject to an regulatory oversight on its
costs and tariffs except in cases where:
Power is sold to Distribution Licensees based on a cost-plus arrangement
and not based on competitive bidding
National Tariff Policy
2.1.2.4 The Policy, as issued by Ministry of Power (MoP), Government of India the
apex policy making body in the power sector requires that Distribution
Licensees procure all long term power through transparent competitive
bidding process2. In line with the above, MoP has developed the
Guidelines for Competitive Bidding and the related standardised bid
documents for the same, which are to be followed for such process. Any
deviation in the same needs to be approved by the Appropriate Commission.
A detailed summary of the National Tariff Policy and the Competitive Bidding
Guidelines is outlined at Annexure 1 and 2 respectively.
NTP provides that, All future requirement of power should be procured competitively by
distribution licensees except in cases of expansion of existing projects or where there is a
State controlled/owned company as an identified developer and where regulators will
need to resort to tariff determination based on norms provided that expansion of generating
capacity by private developers for this purpose would be restricted to one time addition of not more
than 50% of the existing capacity. Even for the Public Sector projects, tariff of all new
generation and transmission projects should be decided on the basis of competitive
bidding after a period of five years or when the Regulatory Commission is satisfied that the
situation is ripe to introduce such competition.
Bhadrawati Power Project
Page 11
2.1.2.5 Distribution licensees can also set up their own generating stations to
arrange power for supply to their license area or for sale outside3. However,
the tariff for sale of power from such a plant for consumption within their
license area is regulated by the State Electricity Regulatory Commission in
accordance with the Terms and Conditions of Tariff for Generating
Stations.
2.1.3 Provisions applicable to Consumers
2.1.3.1 The Electricity Act, 2003 aims at increasing competition in the power sector
and providing greater choices to the consumers. Other than buying power
from the Power Project, the consumers have the choice to procure power
from the incumbent licensee or an independent trader. The consumer
may also set up a captive power plant.
2.1.3.2 The Unit can procure power from the incumbent Distribution Licensee
or Power Project, both of which shall be governed by the State Electricity
Regulatory Commission. The Unit will also have a choice can also procure
power from a trader by availing open access to the Licensees network. A
captive power plant set up by the consumers can avail open access on
payment of open access charges only (cross-subsidy surcharge shall not be
applicable for wheeling of power for own consumption).
2.2
A Distribution Licensee is a deemed Trading Licensee and therefore, can sell power to other
licensees, trading companies and consumers in other license areas through open access.
Page 12
Page 13
3.
3.1
3.1.1 The proposed site is about 125 km from the City of Nagpur, near the town of
Bhadrawati, in Chandrapur district in the state of Maharashtra.
3.2
Page 14
Page 15
Site
Wardha
River
Page 16
3.4.1 The site is well-connected in terms of vicinity to transmission lines and substations. Two major 400 kV transmission lines pass through the site and a
PGCIL 400 kV sub-station is located about 3-4 kilometres from the site.
Another 400 kV sub-station owned by MSETCL, the utility responsible for
transmission in the state, is located in Chandrapur. In addition, MSETCLs 220
kV substation is about 10 kilometres from the site towards Nagpur on the
Nagpur-Chandrapur State Highway.
3.4.2 Power evacuation of
a 1320 MW plant is
generally done at
voltage levels of
400 kV and above.
In case the power
from the plant is to
be utilised within
the state, the plant
would
need
to
connect to the State
transmission
network rather than
the
regional
network of PGCIL4.
PGCIL Line
The PGCIL sub-station or the MSETCL 220 kV sub-station can, however, be utilized to draw start up
and construction power.
Page 17
3.4.3 Considering the above, evacuation should not be an issue. However, there is
merit in starting discussions for evacuation arrangements for the Power
Project as well. This will facilitate an integrated system study and therefore,
save on planning and implementation time.
3.5
Environmental Factors
3.5.1 A power plant in itself does have an impact on the nearby environment but
the technology currently available does provide solutions to mitigate any
adverse impact on the environment. The site is currently at a remote location
with hardly any habitation in the vicinity. Also the fact that the nearest
reserved forest is about 50 kms away from the site augurs well for the
project. The site is currently covered with shrubs with not much agricultural
production. Prima facie the site does not provide any major environment
issues.
3.5.2 Terms of Reference (ToR) for Environment Impact Assessment (EIA) Study
were approved by Ministry of Environment & Forest (MoEF) on 10th day of
February 2009. The EIA Study based on the approved ToR has been
completed. The Application for final EIA clearance along with the EIA report
has been submitted to MoEF.
3.6
3.6.1 The site in itself is under minimal habitation and agriculture production. There
is habitation present on both sides of the site but at a distance of around 3
km. The Rehabilitation and Resettlement issues, therefore, are negligible. An
ordnance factory is present at about 4-5 km from the site, and it provides
employment opportunity for the locals.
3.6.2 A power plant in that area would, in fact, greatly benefit the locals there since
it would provide them with employment on a sustainable basis, during the
construction period and the operation period. Considering all those a power
plant should have a positive impact on the socio economic situation of that
area.
Page 18
Land acquired for the site in adequate and sufficient for the project
Water Availability Letter from Irrigation Department available;
Evacuation of power through the MSETCL network is possible;
Environmental Clearance is not seen as a major issue;
Page 19
4.
Commercial Viability
4.1
Capital Cost
4.1.1 The technical study indicates the various aspects of the project and does not
indicate any major deviation required for the project configuration. The broad
level industry norm for completed cost (Capital cost including IDC) of a
conventional thermal power plant of this size is around Rs. 5 Crores per MW.
4.1.2 Based on the pre-feasibility study, an indicative capital cost of the plant has
been worked out.
Table 1 Indicative Capital Cost of Chandrapur Project
Item Description
BTG & Auxiliaries
Balance of Plant
Preliminary Expenses
Contingencies
Total (Rs Crores)
Interest during construction
Margin for Working Capital
Total
Total per MW
Rs. Crores
3696
1584
329
132
5741
559
287
6586
4.1.3 While the total capital cost as indicated above is Rs 5741 Crores, the
completed cost shall be Rs 6586 Crores on account of addition of Interest
During Construction at about 10% of capital cost for a project to be
completed over a period of ~ 4 years.
Page 20
4.2
4.2.1 Capacity Charge: The capacity charge has been computed based on the
completed cost stated in section 4.1 above.
Table 2 Assumption for Capacity Charge
Assumption for Capacity Charge
Capital Costs
Rs Cr per MW
O&M Expenses (2014)
Rs Lakhs per MW
Debt Tenure
Years
Rate of Interest
%
Interest on working capital
%
Return on Equity
%
Debt component
%
5.0
22.74
10.0
13.0%
13.5%
16.0%
70.0%
4.2.2 Energy Charge: The fuel costs for generation will depend significantly on
the coal-block. However, for the viability determination a base year cost of
Rs. 2360 per tonne including transportation (50 km from coalmine) has been
considered with an inflation of 5% per annum.
Table 3 Assumptions for Energy Charge
Base Year Energy Charge Calculation
Item
Unit
Amount
Gross Generation
MU
9251
Gross Station Heat Rate
kCal/kWh
2346
Specific Oil Consumption
ml / kWh
1.0
Calorific Value of Oil
Kcal / Litre
10,400
Calorific Value of Coal
Kcal / kg
5,000
Cost of Oil per KL
Rs / KL
30,000
cost of Coal per MT
Rs / MT
2,360
Auxilary consumption
%
8.50%
4.2.3 Levelised Tariff: As per the above assumptions, the levelised tariff at 80%
PLF works out to Rs 3.71 per kWh for the IPP.
4.3
4.3.1 Using the State Transmission: Using the MSETCL Network, the buyer will
have to bear the open access charges, that is, long term transmission open
access charges, cross subsidy surcharge and transmission losses of the
MSETCL system. The current long term open access charges and transmission
Bhadrawati Power Project
Page 21
losses for the MSETCL network are Rs 7113 per MW per day and 4.24%.
Therefore, the above tariffs will have to be adjusted for transmission open
access charges and transmission losses.
4.3.2 The resultant landed tariffs for an power project would be Rs. 3.87 per unit
4.4
4.4.1 The current HT industrial tariff in the state, as determined by MERC on the
16th August 2012, is:
Table 4 Industrial Tariff in Maharashtra
S No
1
2
3
4
Charge
Demand Charge
Energy Charge
Load Factor
Net Tariff
HTP-I
Continuous
Rs 190/KVA/month
Rs 7.01 / kWh
70%
Rs. 7.40 / kWh
HTP-I
Non-Continuous
Rs 190/KVA/month
6.33/kWh
70%
Rs 6.72 / kWh
4.4.2 Based on the current industrial tariff in Maharashtra, this Power Project offers
a Delivered Cost basis advantage ranging from 285 paise per unit (73% of the
current tariff) to 353 paise per unit (91% of the current tariff) as against noncontinuous and continuous HT Power tariff.
Page 22
5.
Value Proposition
5.1
5.2.1 The project offers all the inputs water, land, environmental clearance to
set up the project. The value proposition will be further enhanced as the
power sale arrangements and fuel tie up is finalised. Further, to the private
participants who already have coal blocks allocated, this project offers a great
opportunity to tie up all the other inputs and monetise the asset.
Page 23
6.
Way Forward
6.1
6.2.1 Water Availability Letter from Irrigation Department is available and firm
allocation of water for the project would be needed.
6.3
Environment Clearance
6.3.1 As the ToR for the project has already been approved and application for final
EIA has been submitted, environment clearance from MoEF would need to be
followed up.
6.4
Implementation Plan
6.4.1 The Bid Process would be initiated with the issues of NIT in national and
regional newspapers for commencement of issue of RFQ documents.
6.4.2 Bidders will have to manage necessary processes for fuel tie up, water
allocation and environmental clearance.
6.4.3 The bidders shall be provided a period of 2 months to prepare their bids.
Page 24
Annexures
Page 25
1.
1.1
Introduction
1.1.1 The National Tariff Policy was notified on January 5, 2006 by the Ministry of
Power, Government of India in compliance with section 3 of the Electricity
Act, 2003.
1.1.2 The National Tariff Policy was prepared in consonance with the National
Electricity Policy notified on February 12, 2005 by MoP. The National
Electricity Policy has set the following goals
Generation Capacity Addition of more than one lakh MW during the
10th and 11th Plan periods
Per capita availability of over 1000 units of electricity per year
Eliminate energy and peaking shortages; also have a spinning reserve
of 5% in the system.
Providing access for electricity to all households in next five years.
1.1.3 The tariff policy recognises that it is essential to attract investments to the
power sector as state and central budgetary resources cannot support such
huge plans.
1.2
1.3
1.3.1 Tariff policy lays stress on introducing competition in power market besides
encouraging procurement of power through competitive bidding route by
distribution licensees. It lays down framework for performance-based cost of
Bhadrawati Power Project
Page 26
Page 27
Generation
Page 28
Transmission
1.5.1 The transmission system in the country consists of the regional networks, the
inter-regional connections that carry electricity across the five regions, and
the State networks. The national transmission network in India is presently
under development. Development of the State networks has not been uniform
and capacity in such networks needs to be augmented. These networks will
play an important role in intra-State power flows and also in the regional and
national flows. The tariff policy, in so far as transmission is concerned, seeks
to achieve the following objectives:
1. Ensuring optimal development of the transmission network to promote
efficient utilization of generation and transmission assets in the country.
2. Attracting the required investments in the transmission sector and
providing adequate returns.
1.6
Distribution
1.6.3 Linkage of tariffs to cost of service: It has been widely recognised that
rational and economic pricing of electricity can be one of the major tools for
Bhadrawati Power Project
Page 29
Page 30
2.
2.1
Objectives
2.2
2.3.1 To expedite the bid process, the following conditions has to be met by the
procurer:
Bhadrawati Power Project
Page 31
2.4
Environmental clearance
Water linkage
Bidding Process
2.4.1 For long-term procurement, two-stage process featuring separate Request for
Qualification (RFQ) and Request for Proposal (RFP) has to be adopted for the
bid process under these guidelines. The procurer may, at his option, adopt a
single stage tender process for medium term procurement, combining the
RFP and RFQ processes. Procurer or authorized representative has to prepare
bid documents including the RFQ and RFP in line with these guidelines and
standard bid documents.
Page 32
3.
Page 33