Site ID:
3143
Site Name:
NAKITOMA
Structure:
3-Legged
Angular
60 m
JTS Uganda
Kampala/UGANDA
Phone: +256 772381740
+256 752712665
www.jarlso.com
INTRODUCTION
Eaton Towers is in the process of upgrading several towers, In line with this, Jarlso Telecom Solutions
UGANDA was requested to survey the site at the location site 3143 with an aim of doing the following:
-
Measurement of all Tower elements to confirm that the tower on site is the same as the one
indicated on the Tower Key plan in the High-level Engineering Design provided by LEADCOM
Prepare and Provide shop drawings according to the LEADCOM report
Prepare and provide a survey report, including a detailed Bill of quantities and the
methodology.
Prepare and provide a draft tower reinforcement planning.
Site Information
General condition of the tower,
Existing Steel tower angle measurement.
Bill of quantities of the parts to be installed on the tower.
Project planning.
Conclusion.
JTS Uganda
Kampala/UGANDA
Phone: +256 772381740
+256 752712665
www.jarlso.com
1. SITE INFORMATIONS
Survey Date:
Site ID:
Site Name:
Site Address:
3143
----
NAKITOMA
City:
Region:
Latitude (N/S):
N 01.50614
Longitude (E/W):
E 32.09877
Site Direction:
Elevation (m):
Tower type :
3 Legged
Supplier:
LE BLANC
---
60
TIA 222 G
Site Access:
Structure Class:
By road using 4x4 vehicle to
Reach the Site
Topographic Category:
Exposure Category:
Survey Attendees
Name
Function
Tel.:
JTS Uganda
Kampala/UGANDA
Phone: +256 772381740
+256 752712665
www.jarlso.com
SITE LOCATION
JTS Uganda
Kampala/UGANDA
Phone: +256 772381740
+256 752712665
www.jarlso.com
2.2 Pictures
JTS Uganda
Kampala/UGANDA
Phone: +256 772381740
+256 752712665
www.jarlso.com
3.
TITLE
NAKITOMA
SITE ID : 3143
TOWER UPGRADE
Rev
Drawn by :
Alain TSHILUNGU
Checked by :
Taty MUKINAYI
Approved by :
Draw. No.
H T A -
00
Scale NTS
Sht
Of
3143NAKITOMA
4.DETAILLEDBOQ
REGION
TOWERTYPE:
SITEID.
SITENAME:
PROJECT:
Item
Section
60m
3143
NAKITOMA
TOWERUPGRADDE
LISTOFMATERIALSREQUIRED
length
Description
Profile
(mm)
Hiphorizontal
L50x50x5
Horizontal
L60x60x5
Horizontalconnector
L50x50x5
Horizontal
L60x60x5
L50x50x5
Horizontal
L60x60x5
TopGirt
Topgirtplates
1.
L50x50x5
TopGirt
Topgirtplates
Innerbracing
Hiphorizontal
TopGirt
Topgirtplates
Innerbracing
Diagonal
Hiphorizontal
7
Diagonal
8
Bolts
2
BoltM12x60/8.8grade
BoltM16x60/8.8grade
1280
3
6
5835
3
6
300x250x12
L70x70x5
Hiphorizontal
5
L80x80x5
Innerbracing
Horizontalconnector
TopGirt
Topgirtplates
Horizontal
Innerbracing
1530
1530
5800
210x60x12
Hiphorizontal
Horizontal
1710
1710
5800
1390
210x60x12
Hiphorizontal
Horizontalconnector
3
3
3
3
3
6
3
3
3
3
6
3
3
3
210x60x12
Hiphorizontal
Horizontalconnector
Pieces
1830
7871
1740
2020
5800
4000
1830
1855
5760
NA
3
3
3
3
210x60x12
6
L80x80x5
5230
3
6
300x250x12
L60x60x5
5760
3
L70x70x5
4000
3
1720
3
L50x50x5
1660
3
L80x80x5
4460
3
6
300x250x12
L70x70x5
4000
3
1440
3
L50x50x5
1410
3
L80x80x5
3700
3
6
300x250x12
L70x70x5
4000
3
3595
3
4130
3
L65x65x5
3595
3
4130
3
890
3
L50x50x5
3
890
3360
3
1869
3
3360
3
1869
3
L65x65x5
4000
3
3730
3
4000
3
3730
3
TotalQuantity
561
L60x60x5
228
RECAPUTILATION
Profile
Section
Description
Profile
length
(mm)
Pieces
1,2,3,4,5,6,7
Hiphorizontal
L50x50x5
6000
Topgirt
InnerBracing
Diagonal
Topgirtplates
Horizontalconnector
Horizontal
L80x80x5
L70x70x5
L65x65x5
6000
6000
6000
4
3
7
24
18
5
3,4,5,6
68
3,4,5,6
1,2,3
1,2,3
Bolts
300x250x12
210x60x12
L60x60x5
6000
TotalQuantity
BoltM12x60/8.8grade
BoltM16x60/8.8grade
561
228
5.PROJECTPLANNING
GREENFIELD
3143
NAKITOMA
Jarlso Telecom Solutions
Site Number
Site Name
Contractor
Activity
Duration
Tower Upgrade
Actual
Start
Finish
20
Day 1
Day 20
Day 1
Day 2
Resource Mobilization
Materials for Tower Works, Angles Parts and Bolts Supply on Site
Tower Work
Torquing of the Tower before Upgrade
Day 5
Day 9
Materials sorting
Day 9
Day 10
Materials Preparation
Day 10
Day 14
Day 12
Day 16
Day 15
Day 17
Day 18
Day 20
Day 20
Day 20
Acceptance
29047BIWEWE
Start
Finish
JTS Uganda
Kampala/UGANDA
Phone: +256 772381740
+256 752712665
www.jarlso.com
CONCLUSION
From the tower upgrade survey, we have made the Following conclusions:
The work must be done carefully, the new pieces must be galvanized and should fulfill the quality
required, the replacement will be done while removing the existing and the others pieces must remain in
place to consolidate. The work must proceed piece by piece; face by face and section by section.
JTS Uganda
Kampala/UGANDA
Phone: +256 772381740
+256 752712665
www.jarlso.com
ANNEX
SHOP DRAWING
&
METHOD STATEMENT
TITLE
NAKITOMA
SITE ID : 3143
Taty MUKINAYI
Alain TSHILUNGU
TOWER UPGRADE
Checked by :
H T A- -
Drawn by :
Approved by :
Draw. No.
Rev
00
Of
Scale NTS
Sht
TITLE
NAKITOMA
SITE ID : 3143
Taty MUKINAYI
Alain TSHILUNGU
TOWER UPGRADE
Checked by :
H T A -
Drawn by :
Approved by :
Draw. No.
Rev
00
Of
Scale NTS
Sht
TITLE
NAKITOMA
SITE ID : 3143
Taty MUKINAYI
Alain TSHILUNGU
TOWER UPGRADE
Checked by :
H T A --
Drawn by :
Approved by :
Draw. No.
Rev
00
Of
Scale NTS
Sht
JTS Uganda
Kampala/UGANDA
Phone: +256 772381740
+256 752712665
www.jarlso.com
Hardhats
Safety Boots
Protective Eye Wear
Protective Clothing
Heat Absorbent Gloves
Anemometer
Full Body Harness Double Lanyard (Scaffold
Hook Type)
HSE File
Certified Personnel
Torque Wrench x 3 (>200>500>1200)
Deep Reach Impact Sockets
Generator (5kva)
Extension Cord (SABS Approved)
MAG Drill
Titanium Drill Bits
Chop Saw with Relevant Blades
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
FABRICATION
Fabrication is the preparation of the required member to be fitted, retrofitted on the tower /structure.
WHEN FABRICATING MEMBERS
1. Certification of design must be provided by suitable qualified person (P E Practicing Engineer)
2. All manufacturing must be completed on site so it complies with on site design Documentation and clients
Requirement.
3. Manufacturing of member must be supervised by competent person registered with DOSH (Department of
Occupational Safety and Health)
JTS Uganda
Kampala/UGANDA
Phone: +256 772381740
+256 752712665
www.jarlso.com
PREPARATORY WORKS
I.
II.
III.
IV.
V.
VI.
VII.
VIII.
IX.
X.
XI.
XII.
XIII.
XIV.
All construction workers engaged in the manufacturing and fitment of manufactured and redundant parts
on the
structure shall be inducted into the jobspecific JSA.
Manufacturing of the tower / structure members shall be supervised by a competent rigger in accordance
with PEs design.
All materials supplied must be HDG and specified in the BOQ approved by the client.
Inspect and ensure all supplied steel of specified type and size in good condition free from defects.
Spot check the sizes on the shop drawings vs. actuals again on site to ensure correct measurements are
depicted on shop drawings. Should it be found that there is an error on the shop drawing, redline the
drawing and proceed on correct measurement. Redline drawing should them be sent to PE and rectified
as REVX for As Built and certification. Implement the measure twice cut once approach Steel is
expensive and cannot be wasted.
Once all is verified, set out tools needed to complete the SOW. Emory Oak Projects MSHRPREV2
Approved EO Operations DIV VII. Layout all the steel and in number sequence measure and mark, insert
a marking string according to the BOQ for identification purposes. Punch or Permanent Marker.
Outline the steel where it needs to be trimmed / cur / drilled with a permanent marker.
Fabricate steel members according to outlined markings.
All cut edges to be smoothed.
All cut / drilled edges and holes to be treated with rust prevention immediately after. Gold Galv.
All members to be color coded to match existing structure.
Members to be packed in order of reinforcement / fitment.
Two riggers to scale tower using climbing gear and approved methods as describes by the WAH Act. They
should in work pouches carry all needed tools.
Area at bottom to be cleared of all personnel not involved in SOW of fitting members, therefore on line
and hook man at bottom of tower. Rope pullers to be stationed outside of drop zone.
JTS Uganda
Kampala/UGANDA
Phone: +256 772381740
+256 752712665
www.jarlso.com
XV.
i.
XVI.
XVII.
XVIII.
XIX.
XX.
XXI.
XXII.
XXIII.
Not more than one member at a time should be replaced, IE, do not loosen and take down all
replacement members before replacing and fitting.
ii. One member at a time should be loosened, taken down, fit new member and tightened to spec,
not torqued as complete tower torque should be done after completion of fitment of all new
and redundant tower members.
iii. Should tower retorqued not be part of the SOW, all members replaced or redundant members
fitted must be torques down when all members are fitted, not per member.
iv. Care should be taken when loosening a bolt as the tower might be under tension. If this is
realized a support should be fitted keeping the tension the same to avoid tension release which
will cause the new member not fitting correctly, and subsequently causing the rigger to have to
MAKE A PLAN. A structure is either correct and true, or incorrect and not true with the latter
having the risk of failure.
Should additional holes needed to be drilled into tower legs or static members to fit redundant members,
the tools needed for this will be pulled up first to complete static preparation on tower.
Once all members are fitted, the members will be torqued down to specification of the supplier.
Tower Plumb to be measured with a calibrated Theodolite and results documented in the final report.
Variation degrees of plumb needs to be documented.
All fitted bolts and nuts will then be treated with an approved rust prevention agent as prescribed by the
manufacturer.
On completion of the member fitment, tower completes to be retorqued to spec.
On completion of the scope the site will be SOW rehabilitated.
The Supervisor will once all is complete and all tools and redundant materials (SOW related) loaded, take
pictures of all members place / replaced and site in general.
All information will be sent thru to the client for their As Build documentation.
Client will sign FAC.