Академический Документы
Профессиональный Документы
Культура Документы
(MCB4623)
ANALYSIS OF TRIGENERATION SYSTEM WITH GAS
TURBINE GENERATOR, HRSG AND ABSORPTION CHILLER
PREPARED BY:
AFTHAB AFRATHIM - 17741
ARMAN TALE 17718
MOHAMED AYOUB MOHAMED BAHI EL DIN - 12278
SUPERVISOR:
IR. DR. MOHD AMIN BIN ABD MAJID
SEMESTER:
MAY 2015
ABSTRACT
Analysis of a trigeneration system that has a gas turbine generator, a HRSG and
an absorption chiller is carried out in this project. The trigeneration system is
based on the one that is located in Universiti Teknologi PETRONAS. All the
analysis performed neglected irreversibilities which play an important role in
lowering the efficiency of any given system. However, this form of analysis is
sufficient for preliminary decision making with regards to system design.
TABLE OF CONTENT
ABSTRACT ................................................................................... i
CHAPTER ONE: INTRODUCTION
1.0 Background ................................................................................................ 1
1.1 Problem Statement ..................................................................................... 3
1.2 Objective .................................................................................................... 3
ii
LIST OF FIGURES
Figure 1.1: The power output ranges for each of the gas turbine generators (Willis,
2000, p.176). ..............................................................................................................1
Figure 2.1: Schematic of gas turbine with HRSG ......................................................4
Figure 2.2: The pressure-specific volume and temperature-entropy diagrams for
idealized Joule-Brayton cycle... .................................................................................5
Figure 2.3: Thermodynamic model of the compressor ..............................................6
Figure 2.4: Thermodynamic model of the combustion chamber ...............................7
Figure 2.5: Thermodynamic model of the turbine. ....................................................8
Figure 2.6: Typical temperature profile of single pressure HRSG... .........................10
Figure 3.1: Thermal efficiency of the ideal Joule-Brayton cycle as a function of the
pressure ratio. .............................................................................................................16
Figure 3.2: Temperature profile of the HRSG. ..........................................................26
Figure 3.3: Single effect lithium bromide cycle.........................................................27
LIST OF TABLES
Table 3.1: Ideal Gas Properties of Air .......................................................................15
Table 3.2: Properties of Substances ...........................................................................23
Table 3.4: Specific Heat Capacity of Gasses at 480K ...............................................24
iii
CHAPTER 1: INTRODUCTION
1.0
Background
Cogeneration is the use of waste heat from power generation or heat engines for
various purposes such as space heating, drying or for HRSG. Trigeneration is the
combined production of electricity, heat and cooling. A trigeneration plant is
analysed in this project in which a gas turbine generator produces electrical energy
and waste heat; the latter is subsequently used in a HRSG to produce high pressure
(and temperature) steam. This steam is then used in the generator of an absorption
chiller to produce chilled water. A brief overview of a gas turbine generator, a HRSG,
and an absorption chiller will be described below.
A gas turbine generator produces mechanical shaft work through the use of a turbine
that is rotated by high pressure combustion gases. The turbine shaft work is then used
to drive the compressor and an electric generator that generates power for distributed
generation. The redundant energy that is not used for shaft work comes out as
exhaust gasses that are of high temperature. An air compressor, combustion chamber,
expansion turbine, and an exhaust outlet are vital components in a typical gas turbine
generator. There are three classes of gas turbine generators and each has its own
unique capacity, design and operating characteristics (e.g. rotational speed); they
however work on the same principle. The three classes are micro, mini, and utility; in
ascending order of power output. The power output ranges for each of the classes
are shown below in figure 1.1.
Figure 1.1: The power output ranges for each of the gas turbine generators (Willis,
2000, p.176).
1
Only utility gas turbine generators are catered specifically for electric power
generation, while mini and micro gas turbine generators are modified version of gas
turbines originally designed for other applications (Willis, 2000). Furthermore, mini
gas turbine generators are based gas turbines used in designs for small aircraft,
coastal and military patrol ships; while micro gas turbine generators are based on gas
turbines that are used for vehicular application.
Heat Recovery Steam Generator (HRSG) uses the exhaust gas flow of gas turbine
generator in order to produce steam. HRSG are common equipment in chemical
plants, refineries, power plants, and process systems. Heat Recovery Steam
Generators classifies as follow:
Application
Boiler configuration
Whether the flue gas is used for process or mainly energy recovery
The main classification is based on whether the HRSG is used for process or mainly
for energy recovery. Process waste heat boilers are used to cool down waste gas
streams from a given inlet temperature to a desired exit temperatures for further
processing purposes whereas in energy recovery applications, the gas is cooled as
much as possible while avoiding low temperature corrosion. More detail about
HRSG can be found in chapter 2.
Absorption chillers are a form of refrigeration system that is economical when there
a source of inexpensive thermal energy (i.e. heat from cogeneration). However, the
waste heat has to be within the range of 100 to 200 for it to be effective. The
absorption refrigeration system like its name suggest, involves the absorption of
a refrigerant by a transport medium. The absorption refrigeration system is
different from other refrigeration system due to the replacement of the
compressor with a pump, absorber, generator and heat exchanger. This is done
in order to increase efficiency.
The most widely used absorption refrigeration system is the ammonia-water system,
where ammonia serves as the refrigerant and water as the transport medium. This
type of system can be used to achieve much lower temperatures than compared to
water-lithium bromide system. The latter system is limited to applications such as
air conditioning due to water being the refrigerant and thus minimum temperature
has to be above the freezing point of water (engel & Boles, 2006). The workings of
the absorption chillers are as described in more detail in chapter 2.
1.1
Problem Statement
A trigeneration plant is to be analysed. The plant contains a gas turbine generator that
produces a net output of 5 MW of power with a thermal efficiency of 35%. The
waste heat from the exhaust of the turbine is then used in a HRSG to produce high
pressure steam of 1.4 MPa. The HRSG is without a superheater and thus only has an
economizer and evaporator. The high pressure steam generated is subsequently used
in the generator of a single effect lithium bromide absorption chiller. The cooling
medium is water and the ambient temperature, refrigerated space temperature and the
exit temperature of the cooling medium is known to be 30 , 13 and 7
respectively. The aforementioned data are based on the gas district cooling plant used
in Universiti Teknologi PETRONAS (UTP).
1.2
Objective
A HRSG (Heat Recovery Steam Generator) system that utilizes the exhaust
gas from the gas turbine generator to generate high pressure steam (1.4 MPa).
A single effect lithium bromide absorption chiller system that utilizes the heat
from the steam generated from the HRSG system to produce chilled water.
The ambient is known to be 30 and the refrigerated space is 13 with the
chilled water leaving at 7 .
The schematic for a gas turbine generator with HRSG is as shown in figure 2.1
below. Ambient air is drawn in the inlet of the compressor and compressed. It is then
heated in a combustion chamber by the addition of fuel e.g. methane. The flue gas
(combustion exhaust gas) is subsequently, directed towards the turbine where it
converts the energy of the compressed gas into mechanical work. A portion of this
work is used to drive the compressor while the net mechanical work is used to drive
an electric generator.
However, in this project a variation of the simple air standard assumption (alongside
the Joule-Brayton cycle) is used in order to yield more accurate results. The
following general assumptions are used for the analysis of the gas turbine generator:
The pressure ratio is constant for both the compressor and the turbine.
All the processes in the power cycles are internally reversible (isentropic) and
adiabatic.
The flue gas mass flow rate is equivalent to the sum of the air mass flow rate
and the fuel mass flow rate.
The combustion process takes place with theoretical air and the water produced
is assumed to be in its vapor state.
The enthalpies at various temperatures of the flue gas are assumed to be the
same as the enthalpies of air at their respective temperatures. This is done as
the flue gas consists mainly of air.
Compressor
(1.1)
(1.2)
Where1 , 1 and2 , 2 are the pressure and relative pressure of the air at inlet and
after compression respectively, and is the pressure ratio.
Combustion Chamber
(1.3)
(1.4)
Where, is the air mass flow rate and is the mass flow rate of the flue gas. The
energy balance for the combustion chamber is shown in equation 1.5.
+ 2 = 3
(1.5)
Where, is the efficiency of the combustion process and 3 is the enthalpy of the
flue gas at the exit of the combustion chamber. The above formula is used to
calculate the temperature that the flue gas exits at.
Gas Turbine
(1.6)
Where, is the work done by the turbine and 4 is the enthalpy of the flue
gas exiting the turbine. The enthalpy can then be used to find the temperature exiting
the turbine (TET). To find 4 , a variation of the pressure ratio and relative pressure
ratio relation that was used in the compressor section is used. Equation 1.7 shows the
pressure ratio relation.
3 3
=
=
4 4
(1.7)
The net work ( ) that is done by the gas turbine generator is found by using
equation 1.8.
=
(1.8)
The backward ratio, which is the ratio of the compressor work to the turbine work, is
found by using equation 1.9.
=
(1.9)
The thermal efficiency ( ) of the gas turbine generator is found by using equation
1.10.
=
(1.10)
2.1
HRSG Theory
Temperature
Tg2
PP
Ts
Tg3
AP
Tw2
Evaporator
Economizer
Heat transfer
Tw1
(1.11)
The pinch point temperature is the difference between evaporator steam outlet
temperature and the exhaust gas temperature at that physical location in HRSG.
= 2
10
(1.12)
(1.13)
The mass fraction of each substance is calculated by multiplying the molar mass by
number of moles of each substance divided by the total mass of the chemical product:
= =
(1.14)
The total mass of the reactions product is the summation of molar mass multiplied
by number of moles for each substance, therefore:
= ( )
11
(1.15)
Steam Generation
The mass of the steam generated in HRSG is calculated by finding the evaporators
duty divided by the absorbed enthalpy by the steam:
(1.16)
Evaporator duty is basically the amount of heat transfer from evaporator to the water
and it can be calculated by using equation 1.17. The amount of enthalpy absorbed by
the steam in evaporator is shown in equation 1.18.
= , (1 2 )( )
(1.17)
( 2 ) + [ ( 2 )] (1.18)
HRSG Flue Gas
In order to be able to depict the temperature profile of HRSG, the flue gas
temperature of the system (Tg3) should be determined. The heat transfer equation at
economizer (economizer duty) can be written as follow:
, (2 3 ) ( )
(1.19)
The economizer duty can be obtained by another equation which is illustrated below:
(1 + ) (2 1 )
(1.20)
(1 + ) (2 1 )
, ( )
12
(1.21)
The temperature difference of the gas entering the economizer and leaving the
system can be referred as Tg 2-3. Hence the flue gas temperature can be computed as
below followed by constructing the temperature profile of the HRSG.
3 = 2 23
13
(1.22)
2.2
(1 2 )
1 (2 )
(1.23)
Where is the temperature of the space that has been refrigerated, 1 is the
temperature of the generated steam, and 2 is the ambient temperature. The COP can
also be written as:
=
( )
=
( )
(1.24)
Where the mass flow rate of the steam from the HRSG and is the
enthalpy of that steam. is the mass flow rate of the cooling medium
and is the inlet enthalpy of the cooling medium while is the outlet
enthalpy of the cooling medium. is the energy lost by the cooling
medium and is the energy lost by the steam. Various parameters can be
found by rearranging equation 1.23 and 1.24. It should be noted that all the
temperatures should be converted from degrees Celsius to Kelvin in order to do any
of the calculations.
14
CHAPTER 3: CALCULATION
3.0
The required net power output of the gas turbine generator is to be 5 MW under the
assumptions stated in the chapter 1 (under problem statement). In addition, the
thermal efficiency is stated to be 35%. Below are some additional data that were
assumed in order to analyse the gas turbine generator.
I.
15
II.
The pressure ratio ( ) is 5 and is found using figure 3.1 at 35% efficiency.
IV.
V.
VI.
= 0.35
=
= .
It is known from equation 1.3 that is also equivalent to the mass flow
rate of the fuel multiplied by the lower heating value. Hence the mass flow rate of the
fuel can be found by rearranging equation 1.3.
16
=
=
14.29
=
50050
= .
Since, the fuel supplied is around 0.2855 kg/s and as stated in the assumptions above,
an air fuel ratio of 70 is used. Thus, mass flow rate of air is calculated as shown
below.
= . = .
Once the mass flow rate of the air has been established, the compressor can be
analysed. The following parameters are known based the pressure ratio and relative
pressure ratio relation (equation 1.2).
P1 = 1 atm
P2= 5 atm
T1 = 298 K
= 20 /
Rp = 5
The work input required for the compressor can be found by using equation 1.1.
= (2 1 )
However, 1 and 2 requires to be found.
At T1 = 298 K the following parameters can be found from table 3.1 above.
1 = 298.18 KJ/Kg
1 = 1.3543
Using pressure ratio relation with relative pressure ratio,
2 2
=
=
1 1
2
=5
1.3543
2 = 6.7715
17
From table 3.1 above, at Pr2= 6.7715, the following parameters can be found via
interpolation.
2 = 472.81 KJ/Kg
T2 = 470.56 K
Thus, the work input required to run the compressor is calculated as shown below.
= (. . ) = .
Once the compressor work input has been identified, the combustion chamber is
analysed next.
The total amount of gas exiting the combustion chamber is found by using equation
1.4.
+ =
20 + 0.2855 = 20.2855
The total amount of energy that is added during the combustion process is
determined as shown below.
= 0.2855(50050)(1) = 14.29
Thus, in order to find the temperature of the flue gas exiting the combustion chamber,
a rearranged version of equation 1.5 is used to find the enthalpy (3 ).
+ 2 = 3
Rearranging and solving for h3,
3 =
3 =
+ 2
= 1170.56
20.2855
18
Due to the majority of the gas being air, the following parameters (including the
temperature) can be found from table 3.1 at 3 = 1170.56 KJ/kg, via interpolation.
T3 = 1108.18 K
3 = 172.25
The work done by the turbine can be found by using equation 1.6 as shown below;
however, the enthalpy of the flue gas at the turbine exhaust exit is required.
= (3 4 )
Hence, by using pressure ratio relation with relative pressure ratio (equation 1.7), 4
can be determined.
3 3
=
=
4 4
172.25
=5
4
4 = 34.45
From table 3.1 above, at 4 = 34.45, 4 and the temperature exiting the turbine can
be found via interpolation.
4 = 750.06 KJ/Kg
TET (Temperature Exiting Turbine) = 744.10 K
Thus, the work done by the turbine is found as shown below.
= (3 4 )
= . (. . ) = .
The net work is found by using equation 1.8.
=
= 8.53 3.49 = 5.04
19
As the net work is almost the same as the one that was originally specified, the
analysis done is acceptable. The back work ratio of the gas turbine generator can be
determined by using equation 1.9.
=
.
=
= . %
.
Below is the summary of important parameters that were found by analysing the gas
turbine generator.
. %
20
3.1
HRSG Calculations
The assumptions and given parameters that are required in order to analyze the
HRSG are as follows:
As the flu gas of the gas turbine is the input to the HRSG at atmospheric pressure, its
temperature and mass flow rate was obtained:
1 = 1
1 = 744.101
= 20.2855 /
Since the saturated steam pressure is 1.4 MPa, the saturated temperature of the steam
is:
= @ 1.4 = 195 = 468
According to pinch point and approach point temperatures (equations 1.11 and 1.12
respectively), the gas temperature leaving evaporator and water temperature entering
evaporator is obtained.
2 = = 468 8 = 460
2 = + = 468 + 12 = 480
21
As the air-fuel ratio of the combustion was found to be approximately 70 (see gas
turbine generator calculation), there will be 8 moles of air during the combustion
process. Hence the chemical reaction will be:
4 + 8(2 + 3.762 ) 2 + 2 + 2 + 2
Equating the chemical reaction:
C:
1==1
H:
4 = 2 = 2
O:
16 = 2 + + 2 = 6
N2:
8(3.76) = = 30.08
Substituting values:
4 + 8(2 + 3.762 ) 2 + 22 + 62 + 30.08 2
From the above chemical equation, it can be observed that there are 4 different
substances in the flue gas (CO2, H2O, O2 and N2) mixed with (excess) air. The molar
mass of each substance is shown in table 3.2 on the next page. The total mass of
product substances was computed by using equation 1.15.
= ( )
) (1 ) + (18.01
) (2 )
+ (32
) (6 ) + (28.02
) (30.08 )
= (44.01
= .
The mass fraction of each substance was calculated by equation 1.14 and tabulated in
mass fraction column of table 3.2.
22
Molar Mass
Number of moles
Mass Fraction
(Kg/Kmol)
(Kmol)
CO2
44.01
0.0395
H2 O
18.01
0.0323
O2
32
0.1722
N2
28.02
30.08
0.756
Mass Fraction
CP @ 744 K (kJ/kgK)
mf Cp
CO2
0.0395
1.145
0.0452
H2 O
0.0323
2.109
0.0681
O2
0.1722
1.041
0.1793
N2
0.756
1.108
0.8376
23
According to equation 1.13, the specific heat capacity at the evaporator is calculated
as follow:
, = ( ) = 0.0452 + 0.0681 + 0.1793 + 0.8376
, = . /
Economizer Specific Heat Capacity (CPeconomizer)
The flue gas reaches the economizer at 480 K, hence the specific heat capacity of
each substance at economizers temperature (480 K) with the mass fraction is
tabulated in table 3.4.
Table 3.4: Specific Heat Capacity of Gasses at 480K
Substance
Mass Fraction
CP @ 480 K (kJ/kgK)
mf Cp
CO2
0.0395
0.0395
H2 O
0.0323
1.943
0.0628
O2
0.1722
0.965
0.1662
N2
0.756
1.053
0.7961
In order to find the amount of steam generated in HRSG, the evaporators duty
should be calculated according to equation 1.17:
24
= , (1 2 )( )
. = (20.2855
) (1.1303
) (744.101 480 ) (0.99)
= .
According to equation 1.18 for finding the enthalpy absorbed the steam in the
evaporator, there are some enthalpy values which are interpolated and obtained from
the table 3.1. The values are as follow:
= @468 = 2788.8
2 = @460 = 794.086
= @468 = 829.78
=
= .
25
According to equation 1.21, the difference in gas temperature leaving the evaporator
and leaving the economizer is computed. In this equation, the enthalpy of feed water
is required which is interpolated and obtained from saturated steam table (table 3.1)
as follow:
1 = @380 = 448.736
23
=
= .
(20.2855 ) (1.0645
) (0.99)
Flue gas temperature leaving the HRSG would be the subtraction of temperature
difference of gas temperature leaving the evaporator and leaving the economizer
from the temperature of gas leaving the evaporator; equation 1.22:
3 = 2 23 = 480 50.94 = .
The temperature profile of the HRSG that was obtained by the analysis can be
constructed according to the obtained temperatures of feed water and gas turbine flue
gas. The temperature profile of the system is illustrated in figure 3.2.
Tg1= 744.101 K
Temperature
Tg2= 480 K
Tg3= 429.06 K
Tsat = 468 K
Tw2= 4600 K
Tw1= 380 K
Economizer
Evaporator
Heat transfer
26
3.2
A simple diagram of a single effect lithium bromide (LiBr) cycle is shown in figure
3.3 below.
The temperature and the properties of the steam used in the generator is the
same as the one that is generated in the HRSG, hence:
1 = 468
= 3
= 829.78
The inlet temperature of the cooling medium is 13 (286K) and the outlet
temperature is 7 (280K). This information is based on the absorption
chiller in Universiti Teknologi PETRONAS.
In order to analyse the effectiveness of the absorption chiller, the COP needs to be
found. This is done by using equation 1.23.
=
(1 2 )
1 (2 )
( )
= .
( )
The calculated value above is the maximum COP that the system can have; however
the actual COP is much lower. According to engel & Boles (2006), the nominal
COP of a single effect absorption chiller at an input temperature of 116 is 0.65 to
0.70. Thus for a system with 195, we use ratios to find the COP.
116 0.65
195
=
.
= .
Hence, the actual COP can be estimated to be 1.093 and thus the system has an
efficiency of 18.43%. In order to find the mass flow rate or rate of cooling, equation
1.24 is used.
=
( )
=
( )
( )
( )
(. ) .
= .
(. . )
28
Hence, the analysis of the lithium bromide absorption chiller yields the following
important parameters:
29
CHAPTER 4: DISCUSSION
4.0
The thermodynamic model that was used to analyse the gas turbine cycle was
adequate as the net work output that was achieved was approximately the same as the
required net work output. From the calculations, it can be seen that almost 41% of
the work done by the turbine is used to run the compressor. Thus, the back work ratio
is high for gas turbine cycles; however the opposite is true for steam power plants.
As liquid is compressed in steam power plants instead of a gas, and the steady-flow
work is proportional to the specific volume of the working fluid, the work input
required to run the compressor is much lower (engel & Boles, 2006).
A simplistic model (ideal Joule-Brayton cycle) was used to analyse the gas turbine
generator. In reality however, the actual gas turbine cycle varies from the ideal JouleBrayton cycle. Firstly, there are pressure drops during the heat addition process.
Secondly, the work input to the compressor is greater and the actual work output of
the turbine is lower; this is due to irreversibilities. In order to include irreversibilities
in the model, the isentropic efficiencies of the turbine and compressor is required.
Irreversibilities also contribute to increasing the back work ratio as more compressor
work is required while lower turbine work is produced. Finally, the heat addition
process is not adiabatic and hence some energy losses are to be expected in the
combustion chamber. These are other variations between the actual gas turbine cycle
and the idealized one; however, these are the main ones.
Gas turbines generators in general have low efficiencies; however there are various
approaches that can be used to improve the cycles efficiency. These approaches are
concentrated in three areas:
I.
II.
Increasing the turbine inlet temperature (while air cooling is present) can be
done by increasing the combustion temperature to be higher to compensate
for the cooling effect of the cooling air. However, an increase in the
combustion temperature increases the amount of NO2 which is harmful to the
environment.
30
In lieu, steam can be used as a coolant instead of air, which allows for the
turbine inlet temperature to increase by 110 without an increase in the
combustion temperature (engel & Boles, 2006).
In addition, steam is also known to be a more effective heat transfer medium
than air. Other thoughts such as the maximum temperature that the turbine
blades can withstand should be taken into consideration.
III.
4.1
HRSG Discussion
In HRSG system, the gas temperature leaving the system, determines the amount of
energy recovered from the flue gas stream, in other words, it indicates the efficiency
of the system. Hence a lot of effort is made in order to lower this temperature as
much as possible whilst taking into consideration, the cost effectiveness and low
temperature corrosion concerns.
Pinch point and approach point temperatures are two main criteria in HRSG
design. Having a lower pinch point and approach point temperature, increases the
efficiency due to the larger surface area exposed in the evaporator and economizer;
however this also increases the cost. On the other hand, a large value for the
aforesaid variables decreases the amount of energy recovered.
There are a few options to improve the efficiency of a HRSG. The ideal option varies
from case to case based on plant operating period, cost of fuel, electricity and initial
investment cost. These options are as follows:
Auxiliary firing.
Using low pinch and approach points for the HRSG evaporator.
31
4.2
As only a simple temperature analysis was done on the lithium bromide absorption
chiller, the results may deviate a lot from the actual. This is especially true when
irreversibilities
are
taken
into
account.
When
comparing
the
of the absorption chiller to the one in UTP, the results are somewhat similar.
However, the aforesaid statement is based on the theoretical coefficient of
performance and hence does not include irreversibilities. More information about the
absorption chiller in UTP is required to carry out a thorough calculation to obtain
accurate results. In addition, the additional information can also be used to confirm
the validity of the results that was obtained by using ratios. Generally speaking, the
coefficient of performance should be less than unity.
Absorption chillers perform best when the heat source can supply heat at high
temperatures. The cooling capacity is decreases drastically with lower source
temperatures, about 12.5% for each 6 drop in the source temperature (engel &
Boles, 2006). To increase the efficiency of absorption chillers, a double effect or
a triple effect (under development) absorption chiller can be used. They double
effect chiller differs from the single effect chiller in that there are two
condensers and two generators to allow for greater refrigerant to vaporize from
the absorbent solution.
32
CHAPTER 5: CONCLUSION
5.0
Conclusion
33
6.0
REFERENCES
Retrieved
July
24,
2015,
from
Bright
Hub
Engineering:
http://www.brighthubengineering.com/power-plants/42020-how-is-the-hrsgdifferent-from-a-fossil-fuel-fired-boiler/
Zactruba., J. (2010, September 20). What are the types of HRSG's? Retrieved July
25,
2015,
from
Bright
Hub
Engineering:
http://www.brighthubengineering.com/power-plants/42019-what-are-the-types-ofhrsgs/
engel, Y. A., & Boles, M. A. (2006). Thermodynamics: an engineering approach.
McGraw-Hill Higher Education. Retrieved from
https://books.google.com.my/books?id=5-hSAAAAMAAJ
Willis, H. L. (2000). Distributed Power Generation: Planning and Evaluation. CRC
Press. Retrieved from https://books.google.com.my/books?id=tX_OBQAAQBAJ
34