Document Reference: GTGC-DPR-093

DAILY PROJECT REPORT


SITE DESCRIPTION:

Al Wathba Desert Resort

Date:

01.09.2016

Project No. A090

Weather : Temp: 30C to 41C , Humidity: 25%, Dew point 16, Cloud cover:0 %, UV index: 10 , Wind; 13S

PERSONNEL AT SITE:
Project Manager

No. of
Staff
1

Staff Classification

Remarks

Staff Classification
Draughtsman

No. of
Staff
9

Sr. Engineer

Safety Officer

Site Coordinator

Supervisors

10

Document Controller

Formans

MEP Coordinator

Timekeeper

Mechanical Engineer

Storekeeper

Electrical Engineer

Office Boy

Plumbing Engineer

Driver

QA/QC Engineer

HVAC Team

ELV Enginneer

15

Total

Safety Assistance

No. of
Worker
3

Labor Classification

Total
Sub-Cont

Remarks

30

Supervisor

No. of
Worker
1
26

Absents

Plumber

57

Electrician

Electrician

70

Plumber

Ductman

Helper

17

Fitter

20

Fitter

Welder

Safety Asst

Helper

39

Draughtsman

Total

191

Total

1
49

Total Man Power At Site

463

Remarks

SUB CONTRACTORS
Sub Cont. Company Name

No. Staff
/ Lab

GTGC

First Security/GTGC
Rafada
Hanna
Naffco

94
13
10
42

Tornado

11

Cool Moon

Total

178

Remarks

MEP WORKS PLANNED FOR TODAY:


Electrical- 1. LV wire pulling lighting in Speciality Restarant,
2 .Chipping & conduit fixing, GI box fixing in All Day Dining , Desert
camp ,SR roof ,Hotel,BB5,BB2,BB4,BB1

Mechanical - 1. Water Supply work ppr installation in BB5


2. Drainage Pipe aliagnment work in BB6 & Pex elbow fixing in DC
3.Pantry drainage work at H/L in BB6 & RWO installation in BB5

3. Conduiting work in CF GF , Main Hotel,BB1,ADD,TS,SR


4. Threaded rod fixing for cable tray trunking in Main Hotel Basement,SR

4. Chw pipe installation on BB1,Talise spa & Welding work in BB6


5.PPR pipe installation on BB4,CF,Hamam area

5. Lighting protection work in V3 & Talise Spa

6. Marking & support fixing for ppr in Main hotel


7.Water supply pipe insulation in V1-4

6.Cable Tray work in Subsation 1

8.Drainage & Water supply point fixing wall in BB2


External - Drainage pipe fixing in LS to STP & PPR pipe
modification in BB6 & Landscape lighting work in BB3,6,Talise
Spa & Fire fighting pipe laying from Desert Camp to Zone B &
Child water supply laying & Pressure test in Zone C

ELV - 1. ELV Pvc conduting in BB4, BB2, Village Gate


2. BGM conduting in Talise Sap

9. Pressure testing for water supply pipe in BB1


10. Accoustic liner fixing for duct in BB1
11. Pex pipe installation wall in BB2
Design - Coordination drawings:- All Day Dinning, Talise Spa , Main hotel
basement elevation for site purpose,BB1 & HVAC Drawings:- Containment
Drawings:- Main hotel,BB1 & ADDC drawings

WORK COMPLETED YESTERDAY:


Electrical- 1. LV wire pulling lighting in Speciality Restarant,V2-1,2

3. Conduiting work in CF GF , Main Hotel,BB1,V1-6,ADD,TS,SR


4. Threaded rod fixing for cable tray trunking in Main Hotel,SR

Mechanical - 1. Water Supply work ppr installation in BB5


2. Drainage Pipe aliagnment work in BB6 & Pex elbow fixing in DC
3.Pantry drainage work at H/L in BB6 & RWO installation in BB5
4. Chw pipe installation on BB1,Talise spa & Welding work in BB6
5.PPR pipe installation on BB4,CF,Hamam area

5. Lighting protection work in V3 & Talise Spa

6. Marking & support fixing for ppr in Main hotel

2 .Chipping & conduit fixing, GI box fixing in All Day Dining , Desert
camp ,SR roof ,Hotel,BB5,BB2,BB4

6.Cable Tray work in Subsation 1

7.Water supply pipe insulation in V1-4

External - Drainage pipe fixing in LS to STP & PPR pipe modification in


BB6 & Landscape lighting work in BB3,6,Talise Spa & Fire fighting
pipe laying from Desert Camp to Zone B & Child water supply laying in
Zone C

8.Drainage & Water supply point fixing wall in BB2


9. Pressure testing for water supply pipe in BB1
10. Accoustic liner fixing for duct in BB1
11. Pex pipe installation wall in BB2

ELV - 1. ELV Pvc conduting in BB4, BB2, Village Gate


2. BGM conduting in Talise Sap

Design - Coordination drawings:- All Day Dinning, Talise Spa , Main hotel
basement elevation for site purpose,BB2 & Water Supply Shop Drawings :Main Hotel, BB1 & HVAC Drawings:- Containment Drawings:- Main
hotel,BB1 & ADDC drawings

CONTROL / ACKNOWLEDGEMENT / APPROVAL :