Академический Документы
Профессиональный Документы
Культура Документы
AN UNDERGRADUATE THESIS
Presented to
the Mechanical Engineering Department of
School of Engineering and Architecture
Ateneo de Davao University
E. Jacinto St., Davao City
October 2016
TABLE OF CONTENTS
LIST OF FIGURES
LIST OF TABLES
LIST OF EQUATIONS
CHAPTER
1
1.1
1.2
1.3
1.4
1.5
2
Page
iii
iv
v
INTRODUCTION
Background of the Study
Statement of the Problem
Objectives of the Study
Significance of the Study
Scope and Limitation
1
3
3
4
4
Stages of a Project
Mechanical Systems of the
Project Design Phase
Working Principles of
Mechanical Systems
Theoretical Principles in Designing
Mechanical Systems
18
19
19
22
7
8
13
28
28
25
26
26
3.6
3.7
3.8
3.9
3.10
3.11
3.12
28
4.1
4.2
4.3
4.4
BIBLIOGRAPHY
29
29
30
30
31
LIST OF FIGURES
Page
Figure 2.1 Stages of a Project Lifecycle
10
11
17
20
22
22
22
22
LIST OF TABLES
Page
Table 2.1 Psychrometric Processes
12
18
LIST OF EQUATIONS
Page
Equation 2.1: General Heat Rate Formula
13
14
14
15
15
CHAPTER I
INTRODUCTION
This chapter defines Building Information Modeling and a buildings
mechanical system. It also shows the advantages of BIM over the
traditional designing and construction method, the information to be
extracted from BIM, and the present problems with the traditional method.
Furthermore, this chapter presents the objective, scope, and the
significance of this study.
1.1 Background of the Study
Building Information Modelling (BIM), is defined as a digital
representation of physical and functional characteristics of a facility and a
shared knowledge resource for information about a facility forming a
reliable basis for decisions during its life-cycle; defined as existing from
earliest conception to demolition [1]. BIM provides an integrated workflow,
as it is created on coordinated or reliable information about a project from
the design phase, going through construction and into operations. BIM, as
a
collaborative
process,
therefore
makes
designing
and
project
use a common file format for their own 3-D models and share their design
information among members to be subjected to interrogative inquiry.
CHAPTER II
THEORETICAL BACKGROUND AND CONCEPTUAL FRAMEWORK
This chapter presents the different theories behind the topics this
thesis covers, namely, Building Science, HVAC, Fire Protection, Plumbing,
and Building Information Modeling.
2.1 Building Science
Building science is the collection of knowledge and techniques in
the processes involving the construction of a building. This body of
knowledge defines different approaches applied and factors that affect the
completion of a project. It provides engineers and contractors methods to
efficiently implement a building in terms of material cost and time spent
with accordance to different standards provided by different regulatory
bodies.
2.2 Stages of a Project Lifecycle
All buildings, regardless of size, type, or purpose will pass through
sequential stages commonly known as the project lifecycle. The stages
are
generally
referred
to
as
the
concept,
design,
tendering,
to
begin
construction.
Construction
begins
when
site
possession is given to the main contractor and ends when the project
reaches practical completion. Commissioning begins when principal is
given the liability for the facility. During this period the contractor is still
under the defects liability where remaining construction tasks is done,
defects found are dealt with, and service fixtures are properly inspected
[10].
2.3 Mechanical Systems of the Project Design Phase
Effect
decreases the air temperature
increases the air temperature
decreases the air moisture content
increases the air moisture content
decreases the air temperature and
Cooling + Humidification
Heating + Dehumidification
Heating + humidification
Dry pipe
Deluge
Preactio
n
Antifreeze
Characteristics
Has water under pressure at all times in the whole sprinkler
system. Usually used when freezing and special parameters are
not present.
Does not contain water in its sprinkler system. Used when freezing
is possible and activation delay is not a grave concern.
Delivers water to the entire protected area in the least amount of
time possible, usually used on Extra hazards.
Similar to the dry pipe but with more conditions to activate to
prevent accidental activation due to sensitivity of property
protected.
Similar to the wet pipe but has an anti-freeze solution to prevent
freezing in the system. Usually used as a subsystem of a wet pipe
protecting an area exposed to freezing temperatures.
Equation 2.1
The
steady
flow
energy
equation
provides
convenient
Equation 2.2
Equation 2.3
The energy of the fluid can be calculated from the head of the fluid
shown in equation 2.4 [22].
E= V g h
Equation 2.4
Where : V = volume(m3)
h = head(m)
Flow rate through different cross-sectional areas are constant
therefore a decrease in cross sectional area results in an increase in
velocity. This relationship can be expressed by equation 2.5 [23].
Q = A1 c1 = A2 c2 = constant
Where: Q = volume flow rate(m3/s)
A = cross sectional area of passage(m2)
c = velocity of fluid(m/s)
Equation 2.5
set
of
recommended
guidelines
for
design
and
resulting flow rate will be the basis for the designer to determine pipe
diameters according to standards [20].
Table 2.3 Load Values Assigned to fixtures [20].
Fixture
Occupancy
Water Supply
Bathtub
Bidet
Combination fixture
Dishwashing
Private/Public
Private
Private
Private
machine
Drinking Fountain
Kitchen sink
Lavatory
Service Sink
Shower Head
Urinal
Water Closet
Offices, Etc.
Private/Hotel, restaurant
Private/Public
Offices, Etc.
Private/Public
Public
Private/Public
0.25
1.4/4.0
0.7/2.0
3.0
1.4/10.0
3.0
2.2/5.0
operation, fringe benefits, etc. The unit price will then be multiplied to the
parameters for total cost [25]. Cost estimators do the cost estimation. As
they prepare for cost estimates, they digitize the designers drawings and
imported into a cost estimating package, or do manual estimates. This
introduces to human errors [26].
2.8 Construction Planning
Construction planning refers to the time scheduling and sequencing
of a construction project. This considers time as the 4 th dimension in
scheduling. There are methods to do construction planning. However, the
Critical Path Method (CPM) is the most common method [27]. In this
method, the project is divided into individual activities. Each activity is
linked to previous activities which are required for completion before the
linked activity starts. The sequences of events must be undertaken to help
decision makers identify the best sequence for time schedule estimate
[28].
2.9 Building Information Modeling
Building Information Modeling (BIM) is a digital representation of a
facility, attributed with physical and functional characteristics and with
information of the facility necessary for the basis of decision-making
during the life-cycle [4]. It might be confused from a regular 3D
representation of a facility, however the two are entirely different. Regular
3D representations do not contain smart information, but merely itself.
Moreover, BIM is referred to as a process, rather than a tool, of utilizing
the model and information of the facility, called the Building Information
Model, for simulation and critical evaluation necessary for the project [1].
BIM is a platform that allows accurate and efficient collaboration of project
CHAPTER III
REVIEW OF RELATED LITERATURE
This chapter discusses the significant studies and papers regarding
construction projects and Building Information Modeling. These cover
mainly the problems faced in construction, utilization and benefits of
Building Information Modeling in construction.
3.1
Construction
Management
for
Government
Projects
in
Philippines
There are problems that are encountered during construction cycle
in the Philippines. It is stressed out that it is important to improve the
planning and design strategy in construction processes in the Philippine
setting. Environmental analysis as well as sufficient safety and disaster
prevention must be taken into account, since Philippines is a hub of
catastrophes and natural disasters like typhoons and earthquakes. The
limited fund resources for construction, repair maintenance in the country
makes improvement in construction processes vital to avoid economic
disasters down the line [31].
3.2 Case Study: Factors causing delays in project implementation
According to the findings, one factor is that contractors lack
management and organization to handle construction projects. Reasons
for this include lack of organizing training programs and seminars for
Construction Management, and conflicts among different building
engineers that would take time to be resolved, the lack of methodologies
of construction prior to or during the construction phase, lack of technical
skills for effective planning, scheduling and cost estimation of the project,
and outdated methods of construction [32].
3.3 Benefits of BIM in Construction and BIM Based Scheduling
Since the early 1960s, the construction industry faced a steady
decline in its labor efficiency. This is due to the fragmented nature of the
traditional construction method, and use of 2D CAD. This deter the
collaborative participation of project actors. Additionally, it required
additional work hours per contract amount. To further study and
understand BIM in detail, a 3D model of a house was developed under
Revit Architecture 2010 and its time schedule under MS Project in order to
import the 3D files to Synchros 4D BIM tool, where the final product was a
video file of the schedule activities. Furthermore, MIT Koch Center project
was also used to study the application of BIM for 3D coordination,
construction planning, prefabrication, visualization, and record model. In
conclusion, the visualization is the simplest use of BIM. The 3D
coordination was used for clash and conflict detection. Better construction
planning has resulted from BIM based time scheduling which helped in
understanding of the construction mechanisms and scheduling. Although,
setbacks were observed in the house modeling. The software utilized
requires time to add new elements. Interoperability issues surfaced during
the importation of files from a software to another [27].
START
INITIAL DESIGN
Conceptual Design
Schematic Design
Calculations
BIM
3D Mechanical Systems Design
DATA EXTRACTION
Analyses Reports
Drawing Sheets/DPFs
Bill of Materials
Construction Time
Schedule
END
Bibliography
vol. 1, 2009.