LinkCommissioningProcedures

ThefollowingarerecommendedforpropercommissioningofallTrangoSystems
microwavelinks.

1. SiteValidation
Thisprocesswillensurethatthesiteateachsideofthelinkisproperlyreviewed
tomeetallinstallationrequirements.

2. LinkCommissioningChecklist
Thischecklistwillensurethatthelinkisproperlyconfiguredandthereisarecord
whichvalidatesthecorrectinstallationofthelink.

LinkCommissioningProcedureV1.0

MA9001Rev1

SiteValidation
SiteInformation
Customer:
SiteName:
SiteAddress:
SiteCoordinate:
RadioModel:
RadioSerial#
SiteAccessnotes:

AntennaInstallation
Antennamodel

Antennasize
Height
DoesitmeetFresnelzonerequirement?
AntennaMountisproperlysecure
IstheAntennaproperlysecure
IstheMountProperlygrounded?
IstheAntennaProperlygrounded?
IstheAntennasidestrutinstalled?
IstheAntennaweatherproof?
WastheORinginstalled?
Istherangeofmotiononthemountproperlyworking?

INDOORUNIT(IDU)
Isitproperlymountedontherack
Doesithavesufficientspacebetweenotherdevicesontherack
forproperventilation?
IsitproperlygroundedtotheRack?
Areallcablesproperlylabelandsecure?
Isthefanworking?
Isthefanrunning?
IstheFerritecorrectlyinstalled?
Istherackproperlysecuretothefloor?
Istherackproperlygrounded?
PowerSupply
TypeofpowerSupply:
RedundantpowertotheIDU?
MeasureinputvoltageatIDU
Properlygrounded?
IstheDCconnectorsecureviathefastenscrews?
Forredundantpower,isthe+groundonbothpowersupplies
connectedtothecenterpinoftheDCconnectorintheIDU?
(GigaPro/Plus)
Aretheleadsproperlyconnectedtothepowersupplysterminal
block

IFCable
CableType:
CableLength:

LinkCommissioningProcedureV1.0

YesNo
YesNo
YesNo
YesNo
YesNo
YesNo
YesNo
YesNo
YesNo

YesNo
YesNo
YesNo
YesNo
YesNo
YesNo
YesNo
YesNo
YesNo

YesNo
(VDC)
YesNo
YesNo
YesNo

YesNo

MA9001Rev1

ProperconnectiontotheIDU?
ProperconnectiontotheODU?
ProperweatherproofingatallnecessaryPoints?
Pointofshelterentryweatherproofed?
Pointofentryproperlygrounded?
IsthereadriploopattheODU?
Iscableproperlysecure?
Iscabledamaged?(bends,kinks,etc)
Groundingstrapsinstallperspecifications?
Howmanyinlinesurgearrestersinstalled?

OUTDOORUNIT(ODU)
TypeofODU(SP/HP/Apex):
Areallfourlatchesproperlyclosed?
IstheWaveguidetransitionproperlyorientedto
theODUwaveguideopening(SPandApex)
Doesthepolarizationmatchonbothends?
Whatisthepolarization?
IstheODULEDON(SP/Apexonly)?
IstheLEDfunctioningproperly?
DoestheODUlookdamaged?
IstheGorepressureventcapdamaged?

OtherNotes:

Linkvalidationperformby:
Name:
Title:
Company:

Linkapprovedby:
Name:
Title:
Company:

LinkCommissioningProcedureV1.0

YesNo
Remarks:
Yes No
YesNo
YesNo
YesNo
YesNo
Remarks:
YesNo

YesNo
YesNo
YesNo
HV
YesNo
YesNo
YesNo
YesNo

Date:
ContactNumber:
Signature:

Date:
ContactNumber:
Signature:

MA9001Rev1

LinkCommisioning

Step1:CollectProductSetupInformationforeachlink:

NOTES:
A. LinkisbrokendownintosideAandsideB,thegeographicalendpointsofthelink..
B. ForTrangoLINKGigaProDualModem,ODUA1andA2areattachedtoIDUAonSide
AofthelinkandODUB1andODUB2areattachedtoIDUBonsideBofthelink.
Useasecondsheetfor4+0configurations.
C. ForGigaProsinglemodem,GigaorGigaPlusmodels,donotpopulateODUA2andB2
informationfields.
D. ForApexonlyuseODUA1andODUA2anddonotpopulateIDUandIFcable
informationfields.

1) Equipment:
o SiteAName______________________________________________________
o IDUAModel___________SN________________Firmware_____________
ODUA1Model____________SN____________Firmware__________
ODUA2Model____________SN____________Firmware__________
ODUCombinerModel_________SN__________

o SiteBName______________________________________________________
o IDUBModel___________SN________________Firmware_____________
ODUB1Model____________SN____________Firmware__________
ODUB2Model____________SN____________Firmware__________
ODUCombinerModel_____________SN______________

o PowersuppliesmodelIDUA________________IDUB________________

o IFCableTypeIDUAtoODUA1________IFCablelength_______ft
CableLoss(dB):140MHz____350MHz_____915MHz_____
o IFCableTypeIDUAtoODUA2________IFCablelength_______ft
CableLoss(dB):140MHz____350MHz_____915MHz_____
o IFCableTypeIDUBtoODUB1________IFCablelength_______ft
CableLoss(dB):140MHz____350MHz_____915MHz_____
o IFCableTypeIDUBtoODUB2________IFCablelength_______ft
CableLoss(dB):140MHz____350MHz_____915MHz_____

LinkCommissioningProcedureV1.0

MA9001Rev1


2) RecordSystemConfiguration

Sysconfig:1+0____1+1HSB___1+1SD____1+1FD___2+0____2+2_____4+0_____

IDUA

IDUB
LinkDistance:

________miles

TX:
ODU1TXFreq
_______GHz

_______GHz
ODU1TXPower
______dBm

_______dBm
ODU1Speed/Mod
_______

_______
ODU1ACMON?
_______

_______
ODU1ATPCON?
_______

_______
RX:
ODU1ExpectedRSSI: ________dBm

_______dBm
ODU1CurrentRSSI: ________dBm

_______dBm
ODU1CurrentMSE:
________

_______
ODU1LockStatus:________

________

IDUA

IDUB
TX
ODU2TXFreq
_______GHz

_______GHz
ODU2TXPower
______dBm

_______dBm
ODU1Speed/Mod
_______

_______
ODU1ACMON?
_______

_______
ODU1ATPCON?
_______

_______
RX
ODU1ExpectedRSSI: ________dBm

_______dBm
ODU1CurrentRSSI: ________dBm

_______dBm
ODU1CurrentMSE:
________

_______
ODU1LockStatus:________

________

EMC
GroundingEvery75ftonIFcables?
________

________
Ferriteson48VDCinputtoIDUs?
________

________

LinkCommissioningProcedureV1.0

MA9001Rev1


Step2:RecordLinkTestResults(10cycles):

Lock:_______________________
RSSI________________________
MSE:_______________________
BER:________________________

Notes:
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________

Linkcommisioningperformedby:
Name:
Title:
Company:

Date:
ContactNumber:
Signature:

LinkCommissioningProcedureV1.0