1. Cover the
fully compacted and accurately leveled
slab with filter
sheets appropriate to the
size of suction
mat provided.
Overlap indi- The filter sheets of one proprietary vacuum dewatering
vidual
filter system are being laid out and overlapped on this slab. The top
sheets about 40 suction mat, seen rolled in the center of the sheets, is later
rolled out from the center to cover the filter sheets and lap
millimetres (112 onto the adjacent concrete.
inches).
One proprietary vacuopening with strong polyethylum dewater-ing system does not
ene lapped onto the wet conrequire filter sheets because filcrete before the suction mat is
ters are pro-vided in the rigid
placed. This prevents loss of vactop suction mat placed over the
uum through the opening.
area to be dewa-tered in a similar way. Most of the method
notes given here apply to the
flexible suction mat system but
the basic principles of dewatering apply to both systems.
2. When filter sheets are moved to
an adjoining area, place them so as
to abut but not overlap the area just
dewatered.
3. If dewatering equipment with
a flexible top suction mat is being
used, place the rolled-up mat centrally on the area to be dewatered
and then roll it out flat so that it covers the filter sheets and projects an
extra 150 millimetres (6 inches) all
around onto the fresh concrete.
4. Make sure the top suction mat
is lightly bedded onto the concrete
all around.
If there is a small opening in the
area to be dewatered, first fix a
temporary cover flush with the
slab surface. Then cover this
8. After the suction is shut off remove the mat and filters. A man can
stand on this surface immediately.
Start power floating on the dewatered area without delay.
9. Continue with additional placing and leveling of concrete while an
area is being dewatered so that good
construction progress is maintained.
The full power trowel finishing
process can be completed within
two hours after removal of suction mats. When vacuum dewatering is not used, five or more
hours may be needed depending
on the concrete mix and weather.
On rare occasions, when the suction mat is removed the concrete
surface may be stiff even though
the lower part of the slab is still
very soft. This may be due to an
excess of fine particles in the concrete sand which does not allow
the vacuum to penetrate to the
PUBLICATION #C750290