Вы находитесь на странице: 1из 15

MILAHA LOGISTIC CITY

HV CHRONOLOGY
Sl. No

Actual

19-May-15

23-Jul-15

17-Jun-15

-36.00

IFC drawing received from M/s. Ramco

7-Jan-16

17-Jun-15

-204.00

KAHRAMAA Approved drawings from CEG

4-Oct-15

13-Sep-15

-21.00

11kV Switchgears (HV-Panels) Submittal to M/s CEG

16-Nov-15

1-Oct-15

-46.00

Approved Material Submittal of 11KV Switchgear (HV Panels) by M/s CEG

Baseline

Delay

Description
IFT drawing received from M/s. Ramco

18-Oct-15
19-Oct-15

1-Oct-15

-18.00

Wires and HV Cables Submittal to M/s CEG

1-Dec-15

3-Nov-15

-28.00

Approved Material Submittal of HV Cables by M/s CEG

6-Dec-15
19-Oct-15

13-Sep-15

-36.00

MV, Synchronizing, Capacitor Panels Submittal to M/s CEG

11

17-Jan-16

1-Oct-15

-108.00

Approved Material Submittal MV, Synchronizing, Capacitor Panels by M/s


CEG

18-Oct-15
23-Nov-15

1-Oct-15

-53.00

Oil Type Transformers Submittal to M/s CEG

14

22-Dec-15

18-Oct-15

-65.00

Approved Material Submittal of Transformers by M/s CEG

19-Nov-15

Q14-20-MEP-RY-0040
RINF-L1240-2015

Q14-20-MEP-RY-0041
RINF-L1027-201

Approval of MV Panels by Kahramaa

13

15

RINF-L1215-2015

Approval of HV Cables by Kahramaa

10

12

Q14-20-MEP-RY-0051

Approval of HV Panels by Kahramaa

Document Ref.

Q14-20-MEP-RY-0083
RINF-L1265-2015

Approval of Transformer by Kahramaa

16

20-Jan-16

kahramaa forms for HV cables for uploading to CEG

Q14-20-MEP-RY-0234

17

30-Jan-16

Uploading of HV panel HV cable transformers forms on kahramaa website

Q14-20-MEP-RY-0266

18

20-Feb-16

Discrepancy in HV cable loop numbering

Q14-20-MEP-RY-0309

19

21-Feb-16

Discrepancy in HV cable loop numbering (RFI)

SAMKO-MLC-RFI-E-039

20

29-Feb-16

Discrepancy in HV Panels setback from backside (RFI)

SAMKO-MLC-RFI-E-041

21

3-Mar-16

Missing Scheme Drawings (New Scheme Drawing for Milaha Project from
Kahramaa)

Q14-20-MEP-RY-0352
RAMCOQA-TRANSMIT-000628
RINF-L1128-2016

22

3-Mar-16

Discrepancy in HV cable loop numbering

23

10-Mar-16

Material re-submittal for 11KV Switchgear (HV Panels) Alternative

24

13-Mar-16

Discrepancy in HV Panels setback from backside (RFI)

25

23-Feb-16

MV panel document to be stamp & sign by the client & consultant

Q14-20-MEP-RY-0325

26

7-Mar-16

MV panel document to be stamp & sign by the client & consultant

RTC-149-LTR-019-SI
AS/RAM/034/P/5/014/NW

27

17-Mar-16

MV Panel Electrical loads

28

17-Apr-16

Data relocation instruction ( New IFC)

SAMKO-MLC-MS-E-010A
Q14-20-MEP-RY-0360
RAMCOQA-TRANSMIT-000649

Q14-20-MEP-RY-0377
QR-10-0133/SO/RTC5/0416/L00149

Sl. No

Actual

Baseline

Delay

1
2
3

19-May-15
23-Jul-15
7-Jan-16

17-Jun-15
17-Jun-15

-36.00
-204.00

19-Oct-15

13-Sep-15

-36.00

17-Jan-16

1-Oct-15

-108.00

12-Oct-16

18-Oct-15

360.00

22-Feb-16

7-Mar-16

17-Mar-16

10

7th April 2016

16

17-Apr-16

11

30th April 2016

12

10th may 2016

13

14th May 2016

Description
IFT drawing received from M/s. Ramco
IFC drawing received from M/s. Ramco
KAHRAMAA Approved drawings from CEG
MV, Synchronizing, Capacitor Panels Submittal to M/s
CEG
Approved Material Submittal MV, Synchronizing,
Capacitor Panels by M/s CEG
Approval of MV Panels by Kaharmaa
MV panel document to be stamp & sign by the client &
consultant. Drawings of MV panel were submitted to
M/c CEG
CEG stated that since most of the equipments laods are
under discussion i.e. refrigration load, Fire pump load
that is why they are returning the submittal
IFC & Actual load from all sub-contractors were
provided along with the DB detail. Also it was
highlighted which panels will change due to change.
Partail approavl was asked in this regard.
CEG requested to submit actual loads based on materail
submittal for S/s -01 ( qtelBld) & S/S/-WH-B4. - They
said that S/S/-16 load for sewage treatment is not
finalsied. - MV panels S/S/-3,S/S-4 and S/S-9 loads still
not finlised.
Data relocation instruction ( New IFC) due to which
the MV panels for B2 & B3 have changed and require
Kahramaa approavl
SAMKO sent letter stating the status of all the MV
panels based on the revsied IFC and loads they had
revied and ased the client for their advise regarding the
MV panel
Projacs informed which panel to hold and which panels
to submit for approavl & Kahramaa stamping Hold MV
panels for B2 & B3
SAMKO submitted S/S-3 MV-4, S/S/-5, MV 1 & 2 &
S/S-1 MV-1 for CEG to stamp as per the Projacss letter
QR-10-0133/SO/RTC5/0416/L00165 dated 10th May
2016

Document Ref.

Q14-20-MEP-RY-0041
RINF-L1027-201

Q14-20-MEP-RY-0325
RTC-149-LTR-019-SI dated 7th March 2016
AS/RAM/034/P/5/014/NW dated 5th march
2016 from CEG

Q14-20-MEP-RY-0377

QR-10-0133/SO/RTC5/0416/L00140 dated 7th


April 2016
all load were submitted with IFC
-AS/PIQ/11/034/P5/080/Nw dated 6th April
and actual but it seem that it
was not reviewed .

QR-10-0133/SO/RTC5/0416/L00149

Q014-20_MEP-RY-0497 dated 30th April 2016

QR-10-0133/SO/RTC5/0416/L00165 dated 10th


May 2016

Q14-20-MEP-RY-0555 dated 14th May 2016

MILAHA LOGIST
HV CHRONOLOGY
HV-CABLE
Sl. No

Actual

1
2
3

5
6
7
8
9

19-May-15
23-Jul-15
7-Jan-16
19-Oct-15
1-Dec-15
22-May-16
20-Jan-16
30-Jan-16
20-Feb-16
21-Feb-16
29-Feb-16

10

3-Mar-16

11

3-Mar-16

Baseline

Delay

17-Jun-15
17-Jun-15
1-Oct-15
3-Nov-15
6-Dec-15

-36.00
-204.00
-18.00
-28.00
168.00

46.00

MILAHA LOGISTIC CITY


HV CHRONOLOGY - CABLE
HV-CABLE
Description
IFT drawing received from M/s. Ramco
IFC drawing received from M/s. Ramco
KAHRAMAA Approved drawings from CEG
Wires and HV Cables Submittal to M/s CEG
Approved Material Submittal of HV Cables by M/s CEG
Approval of HV Cables by Kahramaa
kahramaa forms for HV cables for uploading to CEG
Uploading of HV panel HV cable transformers forms on kahramaa website
Discrepancy in HV cable loop numbering
Discrepancy in HV cable loop numbering (RFI)
Discrepancy in HV Panels setback from backside (RFI)
Missing Scheme Drawings (New Scheme Drawing for Milaha Project from
Kahramaa)
Discrepancy in HV cable loop numbering

Document Ref.

Q14-20-MEP-RY-0040
RINF-L1240-2015
Q14-20-MEP-RY-0234
Q14-20-MEP-RY-0266
Q14-20-MEP-RY-0309
SAMKO-MLC-RFI-E-039
SAMKO-MLC-RFI-E-041
Q14-20-MEP-RY-0352
RAMCOQA-TRANSMIT-000628
RINF-L1128-2016

MILAHA LOGISTIC
HV PANEL
Sl. No

Actual

Baseline

Delay

1
2
3
4

19-May-15
23-Jul-15
7-Jan-16
4-Oct-15

17-Jun-15
17-Jun-15
13-Sep-15

59.00

-36.00
-204.00
-21.00

16-Nov-15

1-Oct-15

110.00

-46.00

6
7
8
9
10

12-Oct-16
30-Jan-16
20-Feb-16
21-Feb-16
29-Feb-16

18-Oct-15

360.00

11

3-Mar-16

12

10-Mar-16

13

13-Mar-16

MILAHA LOGISTIC CITY


HV CHRONOLOGY
HV PANEL
Description
IFT drawing received from M/s. Ramco
IFC drawing received from M/s. Ramco
KAHRAMAA Approved drawings from CEG
11kV Switchgears (HV-Panels) Submittal to M/s CEG
Approved Material Submittal of 11KV Switchgear (HV Panels) by M/s CEG
Approval of HV Panels by Kahramaa
Uploading of HV panel HV cable transformers forms on kahramaa website
Discrepancy in HV cable loop numbering
Discrepancy in HV cable loop numbering (RFI)
Discrepancy in HV Panels setback from backside (RFI)
Missing Scheme Drawings (New Scheme Drawing for Milaha Project from
Kahramaa)
Material re-submittal for 11KV Switchgear (HV Panels) Alternative
Discrepancy in HV Panels setback from backside (RFI)

Document Ref.

Q14-20-MEP-RY-0051
RINF-L1215-2015
Q14-20-MEP-RY-0266
Q14-20-MEP-RY-0309
SAMKO-MLC-RFI-E-039
SAMKO-MLC-RFI-E-041
Q14-20-MEP-RY-0352
SAMKO-MLC-MS-E-010A
Q14-20-MEP-RY-0360
RAMCOQA-TRANSMIT-000649

MILAHA LOGISTIC

HV-TRANSFORM
Sl. No

Actual

Baseline

Delay

1
2
3
4
5
6

19-May-15
23-Jul-15
7-Jan-16
23-Nov-15
22-Dec-15
12-Oct-16

17-Jun-15
17-Jun-15
1-Oct-15
18-Oct-15
19-Nov-15

-36.00

30-Jan-16

3-Mar-16

59.00
59.00

-53.00
-65.00
328.00

MILAHA LOGISTIC CITY


Transfomer
HV-TRANSFORMER
Description
IFT drawing received from M/s. Ramco
IFC drawing received from M/s. Ramco
KAHRAMAA Approved drawings from CEG
Oil Type Transformers Submittal to M/s CEG
Approved Material Submittal of Transformers by M/s CEG
Approval of Transformer by Kahramaa
Uploading of HV panel HV cable transformers forms on kahramaa website
Missing Scheme Drawings (New Scheme Drawing for Milaha Project from
Kahramaa)

Document Ref.

Q14-20-MEP-RY-0083
RINF-L1265-2015
Q14-20-MEP-RY-0266
Q14-20-MEP-RY-0352

29-Nov-15

Sl. No

Actual
18 th April

Baseline

Delay

Description
RTC-149-RFI-109 dated 18th April 2016 for PA system

Document Ref.

Вам также может понравиться