HV CHRONOLOGY
Sl. No
Actual
19-May-15
23-Jul-15
17-Jun-15
-36.00
7-Jan-16
17-Jun-15
-204.00
4-Oct-15
13-Sep-15
-21.00
16-Nov-15
1-Oct-15
-46.00
Baseline
Delay
Description
IFT drawing received from M/s. Ramco
18-Oct-15
19-Oct-15
1-Oct-15
-18.00
1-Dec-15
3-Nov-15
-28.00
6-Dec-15
19-Oct-15
13-Sep-15
-36.00
11
17-Jan-16
1-Oct-15
-108.00
18-Oct-15
23-Nov-15
1-Oct-15
-53.00
14
22-Dec-15
18-Oct-15
-65.00
19-Nov-15
Q14-20-MEP-RY-0040
RINF-L1240-2015
Q14-20-MEP-RY-0041
RINF-L1027-201
13
15
RINF-L1215-2015
10
12
Q14-20-MEP-RY-0051
Document Ref.
Q14-20-MEP-RY-0083
RINF-L1265-2015
16
20-Jan-16
Q14-20-MEP-RY-0234
17
30-Jan-16
Q14-20-MEP-RY-0266
18
20-Feb-16
Q14-20-MEP-RY-0309
19
21-Feb-16
SAMKO-MLC-RFI-E-039
20
29-Feb-16
SAMKO-MLC-RFI-E-041
21
3-Mar-16
Missing Scheme Drawings (New Scheme Drawing for Milaha Project from
Kahramaa)
Q14-20-MEP-RY-0352
RAMCOQA-TRANSMIT-000628
RINF-L1128-2016
22
3-Mar-16
23
10-Mar-16
24
13-Mar-16
25
23-Feb-16
Q14-20-MEP-RY-0325
26
7-Mar-16
RTC-149-LTR-019-SI
AS/RAM/034/P/5/014/NW
27
17-Mar-16
28
17-Apr-16
SAMKO-MLC-MS-E-010A
Q14-20-MEP-RY-0360
RAMCOQA-TRANSMIT-000649
Q14-20-MEP-RY-0377
QR-10-0133/SO/RTC5/0416/L00149
Sl. No
Actual
Baseline
Delay
1
2
3
19-May-15
23-Jul-15
7-Jan-16
17-Jun-15
17-Jun-15
-36.00
-204.00
19-Oct-15
13-Sep-15
-36.00
17-Jan-16
1-Oct-15
-108.00
12-Oct-16
18-Oct-15
360.00
22-Feb-16
7-Mar-16
17-Mar-16
10
16
17-Apr-16
11
12
13
Description
IFT drawing received from M/s. Ramco
IFC drawing received from M/s. Ramco
KAHRAMAA Approved drawings from CEG
MV, Synchronizing, Capacitor Panels Submittal to M/s
CEG
Approved Material Submittal MV, Synchronizing,
Capacitor Panels by M/s CEG
Approval of MV Panels by Kaharmaa
MV panel document to be stamp & sign by the client &
consultant. Drawings of MV panel were submitted to
M/c CEG
CEG stated that since most of the equipments laods are
under discussion i.e. refrigration load, Fire pump load
that is why they are returning the submittal
IFC & Actual load from all sub-contractors were
provided along with the DB detail. Also it was
highlighted which panels will change due to change.
Partail approavl was asked in this regard.
CEG requested to submit actual loads based on materail
submittal for S/s -01 ( qtelBld) & S/S/-WH-B4. - They
said that S/S/-16 load for sewage treatment is not
finalsied. - MV panels S/S/-3,S/S-4 and S/S-9 loads still
not finlised.
Data relocation instruction ( New IFC) due to which
the MV panels for B2 & B3 have changed and require
Kahramaa approavl
SAMKO sent letter stating the status of all the MV
panels based on the revsied IFC and loads they had
revied and ased the client for their advise regarding the
MV panel
Projacs informed which panel to hold and which panels
to submit for approavl & Kahramaa stamping Hold MV
panels for B2 & B3
SAMKO submitted S/S-3 MV-4, S/S/-5, MV 1 & 2 &
S/S-1 MV-1 for CEG to stamp as per the Projacss letter
QR-10-0133/SO/RTC5/0416/L00165 dated 10th May
2016
Document Ref.
Q14-20-MEP-RY-0041
RINF-L1027-201
Q14-20-MEP-RY-0325
RTC-149-LTR-019-SI dated 7th March 2016
AS/RAM/034/P/5/014/NW dated 5th march
2016 from CEG
Q14-20-MEP-RY-0377
QR-10-0133/SO/RTC5/0416/L00149
MILAHA LOGIST
HV CHRONOLOGY
HV-CABLE
Sl. No
Actual
1
2
3
5
6
7
8
9
19-May-15
23-Jul-15
7-Jan-16
19-Oct-15
1-Dec-15
22-May-16
20-Jan-16
30-Jan-16
20-Feb-16
21-Feb-16
29-Feb-16
10
3-Mar-16
11
3-Mar-16
Baseline
Delay
17-Jun-15
17-Jun-15
1-Oct-15
3-Nov-15
6-Dec-15
-36.00
-204.00
-18.00
-28.00
168.00
46.00
Document Ref.
Q14-20-MEP-RY-0040
RINF-L1240-2015
Q14-20-MEP-RY-0234
Q14-20-MEP-RY-0266
Q14-20-MEP-RY-0309
SAMKO-MLC-RFI-E-039
SAMKO-MLC-RFI-E-041
Q14-20-MEP-RY-0352
RAMCOQA-TRANSMIT-000628
RINF-L1128-2016
MILAHA LOGISTIC
HV PANEL
Sl. No
Actual
Baseline
Delay
1
2
3
4
19-May-15
23-Jul-15
7-Jan-16
4-Oct-15
17-Jun-15
17-Jun-15
13-Sep-15
59.00
-36.00
-204.00
-21.00
16-Nov-15
1-Oct-15
110.00
-46.00
6
7
8
9
10
12-Oct-16
30-Jan-16
20-Feb-16
21-Feb-16
29-Feb-16
18-Oct-15
360.00
11
3-Mar-16
12
10-Mar-16
13
13-Mar-16
Document Ref.
Q14-20-MEP-RY-0051
RINF-L1215-2015
Q14-20-MEP-RY-0266
Q14-20-MEP-RY-0309
SAMKO-MLC-RFI-E-039
SAMKO-MLC-RFI-E-041
Q14-20-MEP-RY-0352
SAMKO-MLC-MS-E-010A
Q14-20-MEP-RY-0360
RAMCOQA-TRANSMIT-000649
MILAHA LOGISTIC
HV-TRANSFORM
Sl. No
Actual
Baseline
Delay
1
2
3
4
5
6
19-May-15
23-Jul-15
7-Jan-16
23-Nov-15
22-Dec-15
12-Oct-16
17-Jun-15
17-Jun-15
1-Oct-15
18-Oct-15
19-Nov-15
-36.00
30-Jan-16
3-Mar-16
59.00
59.00
-53.00
-65.00
328.00
Document Ref.
Q14-20-MEP-RY-0083
RINF-L1265-2015
Q14-20-MEP-RY-0266
Q14-20-MEP-RY-0352
29-Nov-15
Sl. No
Actual
18 th April
Baseline
Delay
Description
RTC-149-RFI-109 dated 18th April 2016 for PA system
Document Ref.