ASSIGNMENT NO.1
Subject: BASIC CIVIL ENGINEEERING
Section: A,D,G,B,E,C,F
Date of Assignment: 07.08.2013
Submission: 14.08.2013

Date of

1) Determine the total carpet area of three storeyed building from the
following data:
Plot Area = 40 m x 30 m
FSI allowed = 0.9
Ratio
of
Carpet
area/
built
up
area
=
0.8
(a,c,h,i,l)
2) If a plot size is 10 m x 20 m and according to bye laws , built up area is
50% of plot area
with FSI= 1.5. Find out the number of storeys that can be built on the plot.
(a,c,h,i,l)
3) A Professor wants to construct a double storied bungalow on a plot of 15
m x 20 m size. Front margin is 4.5 m and rear and side margins are 3m
each. What will be the total built up area ? Also calculate FSI. ( Summer
2013)
(a,c,h,i,l)
4) On a plot of size 25 m x 36 m, the shorter side is facing the main road. If
front margin is 3 m and all other margins being 2 m each, calculate the
possible construction on each of the floors of a G + 2 storeyed building.
Assume equal construction on ground and 1st floor. FSI allowed in the area
is 1.5. ( W 2012)
(a,c,h,i,l)
5) A plot is having dimensions 30 m x 40. A building constructed on it
occupies 400 m2 on ground and 350 m2 on first floor. If permissible FSI is
0.8. how much area can be constructed on second floor?
(a,c,h,i,l)
6) Determine the FSI allowed for G + 1 storeyed building from the following
data:
a) carpet area per floor = 350 m2
b) ratio of carpet area to built up area = 0.82
c) Plot
area
=
900
m2
(a,c,h,i,l)
7) On a plot of size 24 m x 35 m, the shorter side is facing the main road. If
front margin is 3m and all other margins being 2 m each, calculate the
possible construction on each of the floors of a G + 2 storeyed building, if
full ground coverage ( after sparing the margins) is intended. Assume
equal construction on 1st and 2nd floor. FSI allowed in the area is 1.5.
(a,c,h,i,l)
8) A plot owner proposed G + 1 Construction with 225 m 2 on each floor, on a
plot of size 20 m x 25 m. If all margins are 2.5 m and FSI alllowed is 1.0,
calculate additional construction possible on the plot. If maximum possible

construction is to be made on the ground floor ( after sparing the


margins), calculate the possible additional construction on ground floor
and
first
floor,
if
any.
(a,c,h,i,l)