Presupuesto

OBRA:

AMPLIACON Y REMODELACION DE SERVICIOS COMPLEMENTARIOS - TOPICO Y GUARDERIA

UBICACIN:

ISTP. REPUBLICA FEDERAL DE ALEMANIA - CHICLAYO

FECHA:

SETIEMBRE 2016

Item

Descripcin

Unidad

Metrado

Precio

Parcial

1.00 TRABAJOS PRELIMINARES


1.01 TRAZO, NIVEL Y REPLANTEO

M2

690.30

S/. 0.59

S/. 407.28

1.02 DEMOLICION Y APERTURA DE VANOS

GLB

1.00

S/. 1,500.00

S/. 1,500.00

2.01 CORTE DE TERRENO A MANO H(Prom)=0.15 M (M)

M2

45.00

S/. 3.88

S/. 174.60

2.02 EXCAVACION DE ZANJAS

M3

16.64

S/. 37.53

S/. 624.57

2.03 NIVELACION Y APISONADO MANUAL DE TERRENO

M2

45.00

S/. 2.22

S/. 99.90

2.04 RELLENO CON MATERIAL PROPIO (inc. Compactador)

M3

9.00

S/. 47.80

S/. 430.20

2.05 ACARREO DE MATERIAL DE DESMONTE (M)

M3

32.05

S/. 14.07

S/. 450.98

2.06 ELIMINACION DE MATERIAL DE DESMONTE (REAL)

M3

32.05

S/. 18.42

S/. 590.41

2.07 RELLENO CON ARENILLA e=4" (M)

M2

4.50

S/. 7.45

S/. 33.53

2.08 RELLENO CON AFIRMADO e=4" (M)

M2

4.50

S/. 8.67

S/. 39.02

3.01 FALSO PISO DE E=0.085m;F'c=140Kg/cm2 (1:2:4) (M)

M2

45.00

S/. 29.87

S/. 1,344.15

3.02 CONCRETO F'C=100 KG/CM2 + 25% P.M. PARA CIMIENTOS

M3

5.55

S/. 230.78

S/. 1,280.83

3.03 CONCRETO F'C=100 KG/CM2 + 25% P.M. PARA SOBRECIMIENTOS

M3

0.30

S/. 230.78

S/. 69.23

3.04 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS(M)

M2

4.00

S/. 48.36

S/. 193.44

S/. 1,327.17

2.00 MOVIMIENTO DE TIERRAS

3.00 OBRAS DE CONCRETO SIMPLE

4.00 OBRAS DE CONCRETO ARMADO


4.01 CONCRETO EN ZAPATAS F'C=210 KG/CM2

M3

3.24

S/. 409.62

4.02 ACERO ESTRUCTURAL

KG

86.40

S/. 4.40

S/. 380.16

4.03 CONCRETO EN COLUMNAS F'C=210 KG/CM2

M3

3.74

S/. 409.62

S/. 1,533.62

4.04 ENCOFRADO Y DESENCOFRADO DE COLUMNAS(M)

M2

49.92

S/. 48.36

S/. 2,414.13

4.05 ACERO ESTRUCTURAL

KG

294.72

S/. 4.40

S/. 1,296.77

4.06 CONCRETO EN VIGAS CIMENTACION F'C=210 KG/CM2 (M)

M3

0.76

S/. 379.38

S/. 286.81

4.07 ACERO ESTRUCTURAL

KG

68.08

S/. 4.40

S/. 299.55

4.08 CONCRETO EN SOBRECIMIENTO F'C=210 KG/CM2

M3

3.05

S/. 409.62

S/. 1,247.29

4.09 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO(M)

M2

20.30

S/. 48.36

S/. 981.71

4.10 ACERO ESTRUCTURAL

KG

294.72

S/. 4.40

S/. 1,296.77

4.11 CONCRETO EN ALERO F'C=210 KG/CM2

M3

0.75

S/. 409.62

S/. 307.22

4.12 ENCOFRADO Y DESENCOFRADO DE ALERO(M)

M2

4.50

S/. 48.36

S/. 217.62

4.13 ACERO ESTRUCTURAL

KG

24.19

S/. 4.40

S/. 106.44

4.14 CONCRETO EN TECHO F'C=210 KG/CM2

M3

3.60

S/. 409.62

S/. 1,474.63

4.15 ENCOFRADO Y DESENCOFRADO DE TECHO(M)

M2

45.00

S/. 48.36

S/. 2,176.20

4.16 ACERO ESTRUCTURAL

KG

202.50

S/. 4.40

S/. 891.00

4.17 LADRILLO TECHO 30X30XH= 15CM.

UND

405.00

S/. 1.35

S/. 546.75

4.18 CONCRETO EN VIGAS PERALTADAS F'C=210 KG/CM2

M3

2.16

S/. 409.62

S/. 884.78

4.19 ENCOFRADO Y DESENCOFRADO DE VIGAS PERALTADAS(M)

M2

12.60

S/. 48.36

S/. 609.34

4.20 ACERO ESTRUCTURAL

KG

174.56

S/. 4.40

S/. 768.06

5.01 MURO DE SOGA LADRILLO CORRIENTE 6X12X24 cm.

M2

78.70

S/. 48.99

S/. 3,855.51

5.02 MURO DE DRYWALL

M2

5.87

S/. 78.99

S/. 463.28

6.01 TARRAJEO MUROS

M2

419.60

S/. 29.28

S/. 12,285.89

6.02 TARRAJEO CIELO RASO

M2

111.03

S/. 35.28

S/. 3,917.14

7.01 PISO PORCELANATO (Atencion espera, topico, psicologia, dental)

M2

58.83

S/. 82.95

S/. 4,879.95

7.02 PISO CERAMICO (Baos)

M2

8.97

S/. 72.95

S/. 654.14

7.03 PISO LAMINADO (Guarderia)

M2

40.43

S/. 79.85

S/. 3,227.94

7.04 PISO CEMENTO PULIDO (Patio)

M2

10.00

S/. 45.11

S/. 451.10

M2

46.46

S/. 72.95

S/. 3,389.26

9.01 SALIDA DE DESAGE (PTO)

PTO

16.00

S/. 56.66

S/. 906.56

9.02 SALIDA DE AGUA FRIA (PTO)

PTO

15.00

S/. 66.66

S/. 999.90

9.03 CAJA DE DESAGE

UND

1.00

S/. 125.47

S/. 125.47

9.04 EQUIPOS SANITARIO - INODORO

UND

3.00

S/. 275.63

S/. 826.89

5.00 TABIQUERIA

6.00 REVOQUES Y ENLUCIDOS

7.00 PISOS

8.00 ENCHAPES
8.01 ENCHAPE CERAMICO (Baos)
9.00 INSTALACIONES SANITARIAS

9.05 EQUIPOS SANITARIO - LAVATORIO

UND

3.00

S/. 195.64

S/. 586.92

9.06 EQUIPOS SANITARIO - REGADERA DE DUCHA

UND

1.00

S/. 105.40

S/. 105.40

10.00 INSTALACIONES ELECTRICAS


10.01 PUNTOS ELECTRICOS

PTO

48.00

S/. 65.01

S/. 3,120.48

10.02 EQUIPO ELECTRICO - LUMINARIA

PTO

14.00

S/. 65.01

S/. 910.14

10.03 TABLERO DE DISTRIBUCION

UND

1.00

S/. 245.85

S/. 245.85

530.63

S/. 10.30

S/. 5,465.49

UND

6.00

S/. 485.25

S/. 2,911.50

M2

4.80

S/. 245.35

S/. 1,177.68

14.01 VENTANAS VIDRIO CRUDO INCOLORO

M2

24.15

S/. 95.30

S/. 2,301.50

14.02 MAMPARAS VIDRIO CRUDO INCOLORO

M2

11.73

S/. 145.28

S/. 1,704.13

11.00 PINTURA
11.01 PNTURA A DOS MANOS

M2

12.00 CARPINTERIA DE MADERA


12.01 PUERTAS INTERIORES CONTRAPLACADAS
13.00 CARPINTERIA METALICA
13.01 REJAS
14.00 VIDRIO

S/. 80,796.26

COSTO DIRECTO
GASTOS GENERALES

8%

UTILIDAD

7%

S/. 6,463.70
S/. 5,655.74
S/. 92,915.70

SUB TOTAL
I.G.V.
TOTAL PRESUPUESTO
SON :

CIENTO NUEVE MIL SEISCIENTOS CUARENTA Y 52/100 NUEVOS SOLES

18%

S/. 16,724.83
S/. 109,640.52