1. QA/QC Meeting.
2. Electrical Package at PB1 Housekeeping.
8 hrs
8 hrs
8 hrs
1. QA/QC Meeting.
2. Penetrant Testing at B6-L2L4 and
B6-L3L4 Splice Beam at Power Block 1 Bypass Stack (Power Station).
8 hrs
8 hrs
1. QA/QC Meeting.
2. Request Materials needed for Penetrant
Testing.
3. Follow-up Signatures for Penetrant
Testing Documents.
8 hrs
Rest Day
0 hrs