1. Toolbox Meeting All Departments.


2. Monitor Block 1 Bypass Stack possible
Penetrant Testing Activities.
3. LNG Tank 2 Blinding, Follow-up
Sampler for 900 PSI Concrete Pouring.
4. Inventory of Scrap Rebars: 12m 36mm at
26 pcs, and 3.9m 36mm at 98 pcs. Mat'ls
needed for Bypass Stack Foundation.

Pagbilao 650-MW Power Station Project

1. QA/QC Meeting.
2. Electrical Package at PB1 Housekeeping.

8 hrs

8 hrs

1. Meeting with Environmentalists.


2. Follow-up Power Station Electrical
Maintenance.

8 hrs

1. QA/QC Meeting.
2. Penetrant Testing at B6-L2L4 and
B6-L3L4 Splice Beam at Power Block 1 Bypass Stack (Power Station).

8 hrs

1. Penetrant Testing at Power Station:


B1-L3L4 A/B, B3-L1L2, B3-L1L3,
B4-L1L2, B4-L1L3, B5-L2L4, B5-L1L2,
and B5-L3L4.

8 hrs

1. QA/QC Meeting.
2. Request Materials needed for Penetrant
Testing.
3. Follow-up Signatures for Penetrant
Testing Documents.

8 hrs

Rest Day

0 hrs

Employee Signature:

Date:

Manager Approved:

Date:

* Please fax the Weekly Time Sheet to HK Office the week after (Monday).

8-Oct-16

Total

Вам также может понравиться