Академический Документы
Профессиональный Документы
Культура Документы
OracleApps88@yahoo.com
In the Above window inventory parameters are defined. For Process Manufacturing process
manufacturing check box is very important, this check box should be checked only in this way a
process manufacturing enabled Inventory organization is defined. All Other information will be
the same as of other discrete organization. All other relevant information is captured as shown
in the below Screen shots
Costing Information
Lot Information
OracleApps88@yahoo.com
Item Sourcing
Inter-Org Information
OracleApps88@yahoo.com
After Defining all the parameters of Process Manufacturing Organization we will be able to
work in any form in Process Manufacturing Modules just by assigning this org to a specific
Application.
OracleApps88@yahoo.com
OPM Financials
OPM financial >setup > cost types
OracleApps88@yahoo.com
Cost Method
It represents a code that identifies this costing method. For example, enter STND for standard
costing. Required
Cost Type
Indicate the cost method type you are defining:
Standard Cost
Actual Cost
Lot Actual Cost
Click the Lot Actual Cost to indicate that the lot actual cost method is used for lot cost
calculation purposes. If Lot Actual Cost is selected then the Raw Material Calculation type and
Product Calculation type fields are not applicable and they are disabled.
Usage
It indicates if the cost method is for general or Lab use. The general usage method is set by
default. If you set the stage to general use, the cost rollup considers only the production and
costing recipes. If you set the usage to lab use, the lab recipes are used over the production or
OracleApps88@yahoo.com
costing recipes. The usage field is valid only for the standard cost type. If you are using the
actual cost type, then this field is disabled.
Lot Actual Cost Type
Start Date
This is only available for Lot Cost Methods. Enter a start date. The start date is used to collect all
transactions that happened after the specified date for lot cost calculation purposes.
If this field is left blank, then the Lot Actual Cost process uses all transactions in the system for
the OPM Company for which the Lot Actual Cost process is run. The process then selects a
large number of transactions and could result in performance problem as large number of
records are being inserted into the lot cost tables. It is recommended that you set this field
depending on how long lots are typically held for consumption in inventory. It could be a few
inventory periods from the current period. For example, if the current period is January 2004,
then you can specify September 1st, 2003, to ensure all transactions from the prior three
inventory periods are considered. If some of the lot costed items have lots dating further back,
then specify appropriate value.
Alternate Cost Method
If the cost method is an Actual Cost method, then the check box is enabled.
If the lot cost checkbox is enabled, then the Raw Material Calculation Type and Product
Calculation Type are disabled and the Start Date and Alternate Cost Method fields are enabled.
Both Standard and Actual cost methods are allowed but not Lot Actual Cost methods.
When you select the standard cost calculation, you define the cost of ingredients in each
inventory organization during a specific period of time. The cost information remains static
during each defined time period. OPM Costing calculates the standard costs of items using the
Standard Cost Rollup, based on recipes, formulas, and routings defined in the OPM Product
Development application
OracleApps88@yahoo.com
Standard cost lets you define the costs for items, formulas, formula ingredients, recipes, and
resources used during the production process.
For standard costs:
Establish the formulas, routings, and recipes
Run the Cost Rollup process
The cost of a product is based on:
Formulas, recipes, and routings
Resource costs
Overheads
This is a more dynamic method of calculating Item costs based on actual inventory and resource
transaction data. The following are the business transactions that are used to calculate the actual
costs:
Purchasing receipts including Freight and Special Charges estimated on the PO, returns, and
corrections of receipts
OracleApps88@yahoo.com
Paid Invoices
Batch ingredient consumption and resource usage
Opening inventory balances
Cost overheads
Cost adjustments
General Ledger Expense allocations for indirect overheads
All material transactions including internal order receipts
OPM also captures freight and special charges on a purchase order.
Allocating General Ledger expense is a method by which you can distribute the indirect
expenses of manufacturing (such as administrative and general expenses) to item costs.
The balances in the expense accounts are distributed to item(s) based on either fixed
percentages or dynamically derived using other General Ledger account balances, for example,
statistical balances that track the item quantities or resource usages.
For Actual Cost Methods, you can establish a variety of actual cost calculations based on the
raw material calculation type you associate with the cost method and the production calculation
type. There are 15 different possible combinations in OPM (note the discussion for the Raw
Material Calculation Type field). With the lot cost support an Actual Cost method can be
defined as a Lot Cost method.
Updates to the general ledger are made using the cost method defined on the Fiscal Policy
window regardless of the cost type. The description for the cost type you specified displays
automatically.
Raw Material Calculation Type
You can only access this field if you are defining the Actual Costing method in the Cost Type
field. Indicate the type of raw material cost calculations that will occur for this actual costing
method. The valid options are listed as follows:
Period moving average cost (PMAC)
Period weighted average cost (PWAC)
Perpetual weighted average (PPAC)
Last transaction (LSTT)
Last invoice (LSTI)
The type descriptions (shown in parentheses) are abbreviations for these calculation types. The
lookup displays both the calculation type and the abbreviation. Required.
Product Calculation Type
You can only access this field if you are defining the Actual Costing method in the Cost Type
field. If you want OPM to derive actual costs for product components, indicate the type of
calculations it should perform. The valid options are listed.
Period moving average cost (PMAC)
Period weighted average cost (PWAC)
Perpetual weighted average (PPAC)
The type descriptions (shown in parentheses) are industry standard abbreviations for these
calculation types; the lookup displays both the calculation type and the abbreviation.
Defining Cost Calendars
You maintain costs by defining the costing calendars. A cost calendar can be shared across
multiple cost types and legal entities. A cost calendar can span multiple years.
OracleApps88@yahoo.com
For each costing calendar, you can define an unlimited number of costing periods. Each period
is assigned a period status to indicate costing activity that is permitted.
Never Opened - the period was never opened, you cannot establish costs or run any cost
processes in a never opened period.
Open - all activity is allowed.
Frozen - no updates can be made for existing items (however, new item costs can be entered
or calculated and their costs updated).
Closed - no activity is performed in a closed period. Periods cannot be reopened for costing
activity once they are closed.
The costing calendar is completely separate from the fiscal calendar and the periods therein.
Cost Calendars support multiple legal entities and cost type. You cannot assign two calendars
to the same legal entity and cost type combination for the same time period. For example, if you
define a cost calendar called FY06 - monthly calendar for the year 2006 and assign to a Legal
Entity and cost type, you cannot assign another cost calendar, Q06 - quarterly calendar for year
2006, to the same Legal Entity and cost type combination.
If you are using the Period Moving Average Cost, then use the same start and end dates for the
period as the fiscal financial calendar defined for your Legal Entity's Primary Ledger in GL.
The Cost Calendars window supports multiple languages (MLS enabled). When you call this
window, the Globe icon is enabled. If you have multiple languages installed, then use the
option to add the calendar description in any of the installed languages.
OracleApps88@yahoo.com
OracleApps88@yahoo.com
1.
2.
Enter the code to identify the Component Class. For example, enter DRYMAT for raw
materials, or SOLMAT for solutions. Required
3.
Enter a Description for the component class. For example, enter Raw Materials or
Solutions. Required
4.
You have the option of building component class association hierarchies for reference
and reporting purposes. The Primary Component Class indicates the primary cost
component class with which the component class you are defining now is associated.
The default is the class code you specified in the Component Class. You can change the
entry.
5.
Component Group is an optional entry that lets you further group the component
classes for analysis and reporting purposes.
6.
Usage indicates if this cost component classification is being entered for use as a
material, overhead, resource, or expense detail from routings. Select one of the following
values (Required):
a. Material
b. Resource
c. Overhead
d. Expense Allocations
e. Std Cost Adjustment
Once you set the usage indicator for a component class, it cannot be changed after costs
have been defined using this component class.
Once costs have been created or calculated using a component class, the usage cannot be
changed.
OracleApps88@yahoo.com
7.
Enter the Sort Sequence for the component class. It indicates the order in which
component classes displays on forms and reports. 1 is the first or top line and 2 indicate
the second line, and so on. A zero (0) lets the application to determine the sort order.
Required.
8.
Product Cost Calculation indicator lets you flag those component costs to be excluded
from the Cost Rollup process. Certain identifiable costs (for example, transfer costs) are
for specific ingredient items, and are not required to be rolled up into the products. The
valid values are:
a. Include in Product Cost Calculation
b. Exclude From Product Cost Calculation
Select Exclude From Product Cost Calculation if this is a non-product cost component class. The
default, Include in Product Cost Calculation, applies if the component class must be included.
This flag is not applicable for Lot Cost.
9.
Valuation Option indicator lets you identify whether the component class must be used
for valuing inventory or not. The valid values are:
a. Will be used for inventory valuation
b. Will not be used for inventory valuation
10.
OracleApps88@yahoo.com
Resources
1.
2.
3.
After completing the Cost Component Classes window, open the Item Costs window by
selecting Item Costs from the Inquiries menu.
4.
Complete the Item Costs window. Enter the unit cost reflecting the revision or
adjustment indicated on the Cost Component Classes window. See: Item Costs.
OracleApps88@yahoo.com
When you add a new cost, it is recommended that you perform a cost rollup and cost
update to calculate the revised unit cost and process the GL financial cost, respectively.
See: Cost Rollup and Cost Update.
Indirect Component Processing for Standard Costing
5.
When standard costs are used, you can update adjustments or indirect components of standard
product costs separately without defining formula routings and/or overhead details. You can
identify the standard indirect cost component, update non-direct materials and resources within
production batches, and reconcile "batch close" variance at the close of a production batch.
OracleApps88@yahoo.com
1.
2.
Enter the Code to identify the cost analysis type. For example, DIR for Direct Costs, or
IND for Indirect Costs. Required
3.
Enter a Description for the analysis code. For example, enter Value Added or Non-value
Added. Required
OracleApps88@yahoo.com
1.
2.
3.
4.
5.
Enter the cost type to use for inventory valuation in Valuation Method.
6.
Indicate if the fiscal policy is based on costs from the previous cost period or the current
period in Cost Basis.
Enter the default material component that identifies the cost component to be applied to
the fiscal policy in Component Class. Required
8.
Enter the code that identifies the cost Analysis Code to be applied to the fiscal policy
Enter the default overhead component that identifies the cost component to be applied
to the fiscal policy in Component Class. Required
2.
Enter the default overhead Analysis Code that identifies the cost analysis code to be
applied to the fiscal policy
OracleApps88@yahoo.com
NOTE:
Till up to now we have made OPM org and defined the related and necessary setup in OPM
Financials. Now we shall proceed to product development Where we will be able to
incorporate formulas, routings and recipes.
Setting up Parameters
Set up Oracle Process Manufacturing (OPM) Product Development parameters in the Product
Development Security Manager responsibility. You can set up parameters for new
organizations, or query and modify parameters for existing organizations.
Parameter values can vary by organization. These parameters control various functions in the
Product Development application. For example, if version control for formulas is enabled for
organization PR1, then at the point of saving a formula, the application checks the formula
organization to determine whether or not to apply version control rules. Organization PR2 can
have a different setting for formula version control.
OracleApps88@yahoo.com
OracleApps88@yahoo.com
NOTE: First of all these parameters are set for all the organizations then these are defined for
individual OPM orgs. As shown in the below screen shots
Formula
1. Enter Allow Zero Ingredient Quantity as:
a. No to specify you cannot enter ingredients with zero quantity. An error displays
when a zero ingredient quantity is entered. Default
b. Yes to specify possible entry of a zero ingredient quantity.
c. Allow with warning to specify entry of a zero ingredient quantity with a
warning message displayed. If you accept the warning, then you can proceed.
2. Enter Byproduct Active as:
a. Yes to specify you can access the By-Products window. Default.
b. No to specify you cannot access the By-Products window
3. Enter Default Consumption/Yield Type as:
a. Automatic By Step for automatic consumption of ingredients and automatic
yield of products and byproducts as each step is completed. Default
b. Manual for ingredients to default to manual consumption and inserted products
and byproducts to default to manual yield.
c. Incremental for inserted items to default to incremental consumption or
incremental yield.
OracleApps88@yahoo.com
OracleApps88@yahoo.com
b. VOL to specify use of the volume unit of measure type when item quantities are
converted to a common unit of measure for scaling, theoretical yield, and total
output quantity.
c. Another valid unit of measure type for conversion purposes. Set up this unit of
measure type.
NOTE: Same will be incorporated for OPM orgs separately as shown in the following Screen
Shot, however here the check boxes of plant and Laboratory should be checked
Operation
OracleApps88@yahoo.com
1.
OracleApps88@yahoo.com
Routing
OracleApps88@yahoo.com
Recipe
OracleApps88@yahoo.com
1. Enter Default Recipe Status and Default Validity Rule Status as follows:
a. New to make changes at any time, assuming you have security access. Default.
b. Approved for Laboratory Use for use in laboratory batches and cost rollups for
the laboratory.
c. Approved for General Use for use in production batches.
d. On Hold to specify the object cannot be used until the status is changed.
e. Frozen to prevent any further changes to the object and any dependent data.
f. Obsolete/Archived to specify the object can no longer be used unless the status is
changed.
2. Enter Process Instruction Paragraph as:
a. NULL if the process instruction paragraph is not used. Default.
b. A user-defined paragraph code to define process instruction entry using the
standard Text Editor functionality. Process instructions entered in the Recipe
Designer are stored against this paragraph code.
3. Enter Recipe Type as:
a. Master to indicate that the default recipe type is process cell specific. Master
recipes define exactly how a product is made in a specific process manufacturing
cell.
b. Site to indicate that the default recipe type is at the site level. There is one site
recipe for each site that makes the product, or some portion of the product. A
site recipe has the same structure as a general recipe, but may be modified for
the local language and unit of measure. It may also be modified to take into
account local material availability, or it may only define a part of the general
recipe that is actually performed on the site.
c. General to indicate that the default recipe type is one general recipe for each
specific product variation made by a company. It defines, in equipment
independent manner, the material and process dependencies required to make a
product. The general recipe is usually created during or after the pilot plant scale
up of a research and development recipe.
OracleApps88@yahoo.com
Substitution
OracleApps88@yahoo.com
OracleApps88@yahoo.com
Laboratory
Enter Costing Source Organization as the default organization for least-cost formulation. All
process-enabled inventory organizations are available.
Above check will protect the data table visibility at back end. Formula data is visible only in
TOAD when this box is check.
OPM- PRODUCT DEVELOPMENT
ATTENTION:
After Deploying all above necessary setup we will be able to incorporate the Formula,
Operations, Routing and Recipe. Screen shots of the user related application is as follows.
OracleApps88@yahoo.com
These are self explanatory so there is no need to explain all these. However these are fully
explained in the Product development User guides
Formulator > Setup > Formula Class
Formula Classes group formulas with similar characteristics and requirements for reporting
purposes. For example, use a formula class to classify all formulas for ACRYLIC paints, or to
classify all formulas for ORGANIC paints. Food seasoning formulas could be grouped under a
SEASONINGS class. You specify the formula class on the Formula Details window.
OracleApps88@yahoo.com
Enter a new Status Code number. The number you enter is sorted into ascending order with the
other status codes when you save and reopen the Status Codes window.
Codes entered between any two predefined codes, such as 101 to 199, or 201 to 299 are included
in the workflow associated with the predefined status code with the same first digit. For
example, if you enter the code 110, it becomes part of the workflow associated to Code 100. If
you enter a code number 699, it becomes part of the workflow associated to Code 600.
Predefined status codes are shown in a table at the end of this task.
The Enable Version check box determines whether the status code entered is set up for version
control. Any modification made to an operation, routing, formula, or recipe while it is set to the
status entered in the Meaning field initiates or bypasses activation of a new version depending
on the selection you make here, and the value entered for the appropriate version control
profile option.
o Select the check box if you want the status code to enable version control when a
modification is made to an operation, routing, formula, or recipe. The
appropriate version control profile option must be set to Yes or Optional.
o Clear the check box if you want the status code to bypass version control when a
modification is made to an operation, routing, formula, or recipe.
Status Details
The Status Details window enables you to enter a target status for a new status code. You can
optionally enter rework status, pending status, and assign a workflow indicator.
OracleApps88@yahoo.com
OracleApps88@yahoo.com
Formula Details
OracleApps88@yahoo.com
Ingredients
Ingredients:
OracleApps88@yahoo.com
OracleApps88@yahoo.com
OracleApps88@yahoo.com
OracleApps88@yahoo.com
Operation Details
Operations are a combination of one or more activities performed in a production batch and the
resources used to perform those activities. The Operation Details Activities window links
operations to activities. Use the Activity Factor and activity-resource association to enter an
activity several times within an operation. Activity Factor simplifies data entry of the same
activity several times by defining the specific number of times that an activity is performed
during an operation. Activity factor is taken into consideration for planning and resource
calculation purposes. Display the Operation Activity window to link one or more resources to a
single activity. Go to the Operation Activity Line Edit window to edit individual activity lines.
OracleApps88@yahoo.com
Sequence Dependency is selected when the activity has a sequence dependent setup. It is
cleared when there is no sequence dependency.
Enter the Offset Interval as the time delay from the start of the activity to the point where the
resource is actually required.
Activity-Resource Details
The Operation Activity window assigns resources to each activity, and lets you edit a resource
line once activities are associated with an operation. You access this window when you click
Resources on the Operation Details Activities window.
OracleApps88@yahoo.com
Charge calculates resource usage by capturing the number of passes required to process a step.
This is based on the maximum capacity of the step as derived from specific resources used.
Throughput
Process units of measure and usage units of measure are derived from the plant resource if one
is defined. You can override these values using this window. A process quantity is converted to
an operation process quantity unit of measure if needed.
Process Quantity
This value combined with the Usage quantity defines the usage rate. For example, if a resource
can mix 200 gallons per hour, enter 200 as the Process Quantity, 1 as the Usage, and the unit of
measure for hours.
Scheduling Information
OracleApps88@yahoo.com
Select Auxiliary for resources that work as companions with the primary
resources to perform an activity in the Operation. These resources do not affect
the rate of the Operation. For example, a primary resource in a mixing activity is
a mixer with a throughput rate of 100 gallons per hour. An auxiliary resource is
the worker who operates the mixer. No matter how fast or slow the worker is,
the mixer rate remains at a constant 100 gallons per hour.
o Select Primary to indicate that this is the rate determining resource. It limits or
determines throughput. It is also referred to as the bottleneck or critical resource.
There can only be one Primary per resource.
o Select Secondary to indicate the resource that would replace the primary
resource when it is not available. This resource performs the same task as the
primary resource. It is unconstrained, and it has usage. The Advanced Planning
and Scheduling application does not schedule the secondary resource.
Enter the Count as the number of resources needed for the activity entered. For example, it two
blenders are used for mixing, enter a 2 in the count.
Enter the Offset Interval as the time delay from the start of the activity to the point where the
resource is actually required.
o
Scale Type
o
o
o
OracleApps88@yahoo.com
executing a task. They can be generic or specific. Each industry and company uses different
machines and instruments, and there are different requirements for recording process
parameters.
A process parameter details information such as temperature, pressure, or time that is pertinent
to the product, but does not fall into the classification of input or output. You can use process
parameters as set points, comparison values, or in conditional logic.
Parameter Values
The following fields default from the process parameter set up in the planning
application:
o Seq is the sequence of the resource process parameter.
o Parameter is the process parameter name. For example, Bath Temperature.
o Minimum is the lowest acceptable value for a numeric range type of process
parameter.
o Maximum is the highest acceptable value for a numeric range type of process
parameter.
o Units is the unit of measure for the process parameter.
To reset values based on the hierarchy:
You can override certain process parameters at the operation and recipe levels. Click Reset
Values to remove overrides set up for a process parameter. The following illustrates how the
process parameter is reset.
The hierarchy is:
Recipe
Operation
Default value from the planning application
For example, if the default for a process parameter from the planning application is set to 10,
you can override it at the operation level and at the recipe level. The following values are used
for illustration:
Recipe = 20
Operation = 15
Default value from the planning application = 10
OracleApps88@yahoo.com
The Routing Details window enables you to enter the details for a specific routing.
Understanding the Enforce Step Dependency Indicator
When Enforce Step Dependency is selected, several business rules are applied:
The Release Type field is set to Manual to indicate that the step must be released and
completed manually.
You cannot change the step dependency and step release type at the step level.
All steps must be completed before you can complete a batch using this routing.
All steps must be closed before you can close a batch using this routing.
Business rules validate step start and completion dates and times for appropriate batch
step rescheduling.
Routing details:
1. Navigate to the Routing Details window.
2. Enter the code for the Routing. Required.
3. Enter a Routing Version of the Routing. Required.
OracleApps88@yahoo.com
4. After entering all relevant information and saving the Routing with the default Status of
New, return to this window if you need to change Routing Status by selecting Change
Status from the Actions menu. Depending on whether Workflow is enabled, a different
set of statuses is available.
Select a Status for the Routing you are entering from one of the following:
o Approved for Laboratory Use to indicate that the Routing is approved for
laboratory use.
o Approved for General Use to indicate that the Routing is approved for use in
production.
o Obsolete/Archived to indicate that the Routing is no longer approved for use
and is obsolete, archived, or both.
If Workflow is enabled, when you select:
o Approved for Laboratory Use, Status changes to Request Approval for
Laboratory Use until all approvers have accepted the Routing, at which time its
Status changes to Approved for Laboratory Use.
o Approval for General Use, Status changes to Request Approval for General Use
until all approvers have accepted the Routing, at which time its Status changes to
Approved for General Use.
Refer to the Understanding the "Status Approval Workflow" topic for additional
information.
5. Enter a Routing Description that briefly describes the Routing. Required.
6. Enter a Class for the Routing to identify how it is categorized. The Class Description
assigned to the Class displays.
7. Enter the Valid From date for this Routing. The default date is the current system date.
Required.
8. Enter a To date for the expiration of this Routing. If there is no expiration date for this
Routing, leave the field blank.
9. Enter the process Quantity for this Routing. This is the total quantity of material for the
Routing, and is used to scale individual step requirements. Required.
10. Enter the process Quantity UOM associated with this Routing. The process Quantity
UOM must interconvert with the UOM defined for Theoretical Process Loss based on
the primary product UOM conversion in the Routing. Required.
11. Enter the Planned Loss for this Routing. This value is expressed as a percent. For
example, a loss of 1.304% would be entered as 1.304.
12. The Theoretical Process Loss for this Routing displays. This value is entered on the
Theoretical Process Loss window, and is based on the value assigned to the Class
associated with this Routing.
13. Enter the Owner to indicate the individual who is responsible for initiating this Routing.
Required.
14. Enter the Owner Organization to indicate the plant, laboratory, or other facility that is
responsible for initiating this Routing. Required.
15. Enforce Step Dependency is:
o Selected when the routing enforces step dependency.
o Cleared when the routing does not enforce step dependency.
Routing Steps
16. Enter the Step number to associate with an Operation in this Routing. It is
recommended that the first number in this sequence be 10, the second 20, and so forth.
This enables you to add intermediate steps between 10 and 20 at a later time. Required.
17. Enter the code for the Operation performed in this Routing. Required.
18. Enter a Version number for the Routing. Required.
OracleApps88@yahoo.com
OracleApps88@yahoo.com
1.
2.
3.
4.
5.
OracleApps88@yahoo.com
OracleApps88@yahoo.com
Prerequisites
Optionally, enter and save operations.
OracleApps88@yahoo.com
OracleApps88@yahoo.com
6. Enter the main Product for the Formula associated with this Recipe. If you enter a new
Recipe, enter the Formula to fill this field automatically.
7. The Output Quantity displays the sum of all materials. UOM indicates the unit of
measure for the Formula associated with this Recipe.
8. Enter the Formula number for the Recipe. Required. Once a recipe is saved, this field
cannot be edited. You cannot use an inactive Formula in a recipe. The formula Version
displays. Required.
9. Creation Organization displays the organization code for the initial Owner. This field is
not updateable for an existing Recipe. Required.
10. Enter a Routing number for the Recipe. A routing can be added to an existing Recipe.
The Version for the Routing entered displays.
11. Theoretical Process Loss displays the hypothetical loss of process material associated to
a routing as a percentage. If no routing is associated to a recipe, or if no routing class is
associated to a given routing, and no Process Loss is defined for that routing, this field is
blank.
12. Enter the Planned Process Loss as the loss of process material observed during
production of a batch using the recipe. If no value is entered in this field, it defaults to
the Theoretical Process Loss. You can change this value on a New or existing recipe.
13. Total Output Qty displays with its UOM.
14. Enter the Laboratory that has current ownership of the recipe. This is a Folder field.
15. Enter the Owner Organization. This field is the default organization for the Owner of
the Recipe. In order for you to enter or edit information for the Recipe, you must have an
association with this organization and permission to access and change this field.
Required.
16. Enter the Owner of the Recipe. The Owner name must be a valid User name. This field
defaults to the current User. Required.
Note: You must enter all information on this window before you select the Calculate
Step Qty check box.
17. The Calculate Step Qty check box indicates whether you want to enter step quantities
manually or have the application calculate them for you.
o Select the Calculate Step Qty check box to enable the application to calculate
step quantities automatically. Quantities are based on the amount of materials
that go into and out of each supported step. Step Quantity fields cannot be
entered after you select the check box. You must associate all items marked as
contributing to step quantity to specific Steps on the Recipe Step/Material
Association window.
o Clear the Calculate Step Qty indicator to enter step quantities manually. Step
quantities are calculated using routing step quantity, total output quantity of
formula, and routing header quantity.
Plant/Laboratory
18. The following fields are display only:
o Organization displays the Organization code that the Process Loss is being
defined for. This must be a plant or a laboratory. Required.
o Organization Name displays a description of the plant or laboratory.
o Type indicates whether this is a plant or a laboratory.
o Process Loss displays the material that is lost through the process. This field is
blank if you did not enter a Routing. This field allows you to override the default
Process Loss.
Customer
OracleApps88@yahoo.com
OracleApps88@yahoo.com
date, or blank, then the application assigns the value of the routing end date to the validity rule
end date.
To duplicate a recipe:
1. Query the Recipe Details record to duplicate.
2. Choose New from the File menu.
3. Choose Duplicate Record Above from the Edit menu.
4. Enter a new Recipe name and Version number.
5. Save the window.
To display the Formula Details window:
1. Choose Formula from the Actions menu. The Formula Details window displays.
2. Close the window.
To display the Routing Details window:
1. Choose Routing from the Actions menu. The Routing Details window displays.
2. Close the window.
To display the E-Record Details window:
1. Choose E-Record Details from the Actions menu. The E-Record Generic Query
displays if this option is implemented in your application.
2. Refer to "Appendix D Oracle E-Records Events in Product Development" for
information on e-records.
3. Close the window.
To display the Specifications window:
1. Choose Specifications from the Actions menu. The Specifications window displays.
2. Evaluate specifications.
3. Close the window.
To display the Samples window:
1. Choose Samples from the Actions menu. The Samples window displays.
2. Evaluate the samples.
3. Close the window.
OracleApps88@yahoo.com
Minimum Transfer Quantity (MTQ) has a restriction on the gap between the time that the
MTQ is yielded for the item, and the start of the next routing that involves that item. The gap is
defined with a minimum and maximum value based in the TIME unit of measure for hour.
When calculating the gap, the minimum value creates the gap, and the maximum value limits
the duration of the gap between the routing and the MTQ yield point. This MTQ calculation can
be added for all products of a recipe.
Minimum and maximum values are optional, and blank values represent an infinite gap
between the manufacturing processes:
If you enter the minimum value only, then a specific gap must exist between the MTQ
time point and the next routing for the item. However, the end of the gap is infinite.
If you enter both minimum and maximum values, then the gap is fixed and requires the
next routing to start in the defined period after the MTQ time point.
Minimum delay and maximum delay represent this gap. The values for these can never be
negative, and the minimum must always be less than or equal to the maximum value. The entry
of an MTQ for any of the products is not required. Blank value for MTQ implies the full
quantity must be yielded before the next routing can start.
Prerequisites
Enter and save recipes.
If the Automatic Step Quantity Calculation is used:
A routing must be associated with the recipe.
Each item marked as contributing to step quantity must be associated
with a step, and have a conversion specified between the standard mass
unit of measure and standard volume unit of measure.
All operations must use a mass or volume unit of measure.
To display recipe step/material associations:
1. Navigate to the Recipe Step/Material Association window.
2. The following fields are display only:
o Formula displays the formula used in a recipe with the Version and Formula
Description.
OracleApps88@yahoo.com
Routing displays the routing used in a recipe with the Version and Routing
Description.
Associations
Step displays the step number associated with the listed Operation in the
displayed Routing. You cannot add a Step to a routing on this window. You
must do this on the Routing Details window. Required.
o Maximum Delay displays the delay offset in hours. This is a restriction on the
gap between the point in time that the minimum transfer quantity is yielded for
the item and the start of the next routing involving the item. If the maximum
delay is set, then the material must be used before this delay. For future use by
the Oracle Advanced Supply Chain Planning application.
o Minimum Delay displays the Minimum Delay offset in hours. This must be less
than or equal to the Maximum Delay. For future use by APS.
o Item Description displays the descriptions each product, byproduct, or
ingredient listed.
o Line Unit of Measure displays the unit of measure for each product, byproduct,
or ingredient listed.
o Minimum Transfer Quantity displays the minimum quantity of product needed
to yield a partial quantity before the next routing can start. For future use by
APS.
o Operation displays the operation associated with the Step. The operation
Version displays.
o Step Qty displays the default quantity of material associated with the Step. The
UOM for the Step Quantity displays.
o Line displays the line number for each product, byproduct, or ingredient listed.
Required.
o Item displays the code associated with each product, byproduct, or ingredient
listed.
o Type displays the type of Line associated in the Step as a product, byproduct, or
ingredient.
o Item Qty displays the Quantity of product, byproduct, or ingredient yielded by
the listed Formula.
o Line UOM displays the unit of measure for the Item Quantity.
3. Close the window.
Editing the association of materials and steps:
1. Enter the Step from the LOV. Required.
2. The following fields are display only:
o Operation displays the operation associated with the Step. The operation
Version is displayed.
o Step Qty displays the default quantity of material associated with the Step. The
UOM for the Step Quantity displays.
3. Enter the Line from the LOV. Required.
4. The following fields are display only:
o Item displays the code associated with each product, byproduct, or ingredient
listed.
o Type displays the type of Line associated in the Step as a product, byproduct, or
ingredient.
o Item Qty displays the Quantity of product, byproduct, or ingredient yielded by
the listed Formula.
o Line UOM displays the unit of measure for the Item Quantity.
o
OracleApps88@yahoo.com
OracleApps88@yahoo.com
Formula displays the formula used in the recipe with its Version and
Description.
o Routing displays the routing used in the recipe with the routing Version and
Description.
o Status displays the Status of the Validity Rule. This field cannot be higher than
its associated recipe. For example, a Validity Rule cannot be Approved for
General Use until the recipe associated to it is Approved for General Use.
You can change the status of recipes or validity rules to On-hold or Obsolete
even if they are used in batches as long all these batches are closed or cancelled.
3. Organization displays the organization that owns this Validity Rule, and the
Organization Description. This must be your Plant or Laboratory. You can enter and
save a new Organization.
Validity Rule
4. Select Recipe Use as:
o Production for use in production of products.
o Planning for use in planning material consumption.
o Costing for use in establishing costs.
o Technical for use in establishing technical classes and subclasses.
Required.
5. Enter a Product in the Formula for the Validity Rule. The product Description field
displays. Required.
6. Enter the Preference number for the Validity Rule. When more than one formula can be
used to produce the same product, the Preference field is used to show the Validity Rule
that must be used first, second, third, and so forth. Preference defaults to 1. Required.
For example, one formula can be used to produce between 10 and 150 gallons of a
product. Another formula can be used to produce between 100 and 1000 gallons of the
same product. Since either formula can be used to produce 100 to 150 gallons of
material, the Preference field shows the suggested order of use. Lower numbers indicate
a higher Preference. The number 1 indicates the highest Preference.
7. Enter the Standard Quantity of product made with this Formula. This quantity is only
used for product costing. It does not restrict quantities that can be produced with the
Formula. Standard defaults to the quantity provided in the Formula displayed.
Required.
8. UOM is the unit of measure for the standard quantity. You can enter and save a
different unit of measure. Required.
9. Enter the Minimum quantity of product that can be made using the Formula. Minimum
defaults to 1. Required.
10. Enter the Maximum quantity of product that can be made using the Formula. Required.
11. Theoretical displays the theoretical process loss based on the Validity Rule Standard
Quantity.
12. Enter the Planned process loss. This overrides planned process loss entered at the
routing level.
13. Enter the From date as the date the Validity Rule becomes effective. The date must be
within the effective date for any routing associated to the recipe. Required.
14. Enter To date as the date to stop using the Validity Rule. This is an optional field and
must be left blank if no expiration date is defined for the Validity Rule.
Step Quantity
15. The following fields are display only:
o Step displays the step number associated with the operation displayed.
o
OracleApps88@yahoo.com
Operation indicates the operation associated to the step. The operation Version
displays.
o Description indicates a description of the operation.
o Step Quantity and its UOM indicates the quantity processed by the routing step
and the unit of measure of the step quantity.
o Charges indicates the total calculated charges for the step.
16. Save the window.
o
OracleApps88@yahoo.com