Академический Документы
Профессиональный Документы
Культура Документы
In the middle of 1998, Mr. Malik, the financial manager of SADE, a Bahraini civil
engineering company, was reviewing the contract it had just been awarded by the
municipality of Dhahran in Saudi Arabia for the construction of a new road network linking
the airport complex and the city. The life of the contract would be the remaining 6 months of
1998 and four full years over the period 1999 to 2003. The details of the five year contract
awarded to SADE are described in Figure 1. Equipment would need to be purchased more or
less immediately but the main costs and revenues would occur in the period 1999 to 2003.
Given the initial advance, cash inflows and outflows in 1998 would be timed so that the
maximum cash deficit of the contract at any time would be 11m SR. The construction work
would continue until the end of 2002. The invoices (or billings) shown in Figure 1 could be
treated as sales.
First of all, Mr. Malik planned to review his evaluation of the profitability of the contract and
to check that it yielded more than the 15% return requested by SADE on projects in Saudi
Arabia. (15% percent was also equal to the cost of financing for SADE for construction
projects in Saudi Arabia).
Mr. Malik recognized that favourable results on a contract such as this depended on
everything proceeding smoothly. Unfortunately, it seemed to him that it would be pure luck if
the necessary combination of events were all to occur in his favour. Even though it was
unpleasant, his thoughts began to turn to those aspects of the project that could go wrong.
He first wondered which of the various assumptions in his contract evaluation were
particularly critical. He decided to make changes to one assumption at a time so that he could
see which one had the largest impact on the value of the Dhahran Roads contract.
He felt more or less certain that the key factors that could jeopardize profitability would be
cost overruns (such as higher equipment costs or increased annual costs), incomplete or
delayed payments by the customer, and the resultant effect on the timing of inflows and
outflows of cash.
ASSIGNMENT on DHAHRAN (A):
1. Assist Mr. Malik in building a spreadsheet model to evaluate the profitability of the
Dhahran Roads contract, using the data in Figure 1. Check that the contract yields more
than 15%. Calculate the NPV of the contract at the end of December 1998 i.e. do not
discount the estimated cashflow for the six months of 1998, but do so for each subsequent
years cashflow.
2. Carry out sensitivity analysis on your model. In particular, what is the effects on NPV of
the following changes in assumptions:
a.
b.
c.
d.
Which risks have most impact on profitability? What do these results tell us about the risk of
the Dhahran Roads project?
[Hint: Use the scenario manage to model the above four contingencies.]
Costs incurred
7
28
31
25
17
Billings
11
43
48
39
27
c) Use Monte Carlo simulation to analyse the risk profile of this project, focusing on
the impact of uncertainty on the NPV and the maximum cash deficit.
Suggestion:
- Use the triangular distribution for annual costs and equipment costs
- Use the RiskDiscrete function to model the uncertainties about delayed
payment and the recovery of retention payments. (Look it up in the
@Risk help file for details)
d) Discuss the results of the above analysis and provide recommendations about
whether the project should be taken and about how the above risks could be
managed.