Вы находитесь на странице: 1из 1

APPROVAL BEFORE PLASTERING

Project:

Date:

Contractor:

No.:

Building / item(s)
According to Drawing No.

Date:

RHV Inspection Report


Description

Accept

Time:
No

N.A

Remark

Inspection work
Purity (do not stick dust, moss, oil)
Even (do not have raveling, asperity )
Wetness (watering up the wall before plastering)
Roughness (in compliance with each type of
structure)
Plaster coat (slump)
Thickness of plastering
Solid of wall
Your submission for approval is subject to following conditions:


Approved

Approved on condition as noted

 Amend and resubmit

Not approved as noted

Note:
Witnessed by Owner

Name:
Position:
Date:

Date: Jan. 2008


Rev.: 01

Approved by Consultant
Royal HaskoningDHV

Name:
Position:
Date:

Requested by Contractor

Name:
Position:
Date:

Code: TEC-00-16-A2