THAI ASIAN POWER SOLUTION CO.,LTD.

228/12-14 M.5 Srinakarin Road T.Bangmuang


A.Muang Samutprakarn 10270
Issued date : 9/10/2014
Project Name : CPVC RESIN PLANT PROJECT
Client : ASIAN CHEMICAL & ENGINEERING CO.,LTD. CONTROL PANEL PROGRESS REPORT Period from : 6/10/2014 - 9/10/2014
Fabrication By : THAI ASIAN POWER SOLUTION CO.,LTD.

Description

This week

Start Finish

Plan(%) Act.(%) Acc.(%) Date

Date

Approve Drawing

100

100

100

15-Sep 24-Sep

Making Panel

100

10

10

25-Oct 15-Oct

Order Equipment and Delivery

100

100

10

16-Sep 20-Oct

Assembly and Wiring Equipment 100

Sep-14

Oct-14

Nov-14

w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4

13-Oct 2-Nov

Testing

100

3-Nov 6-Nov

Factory Acceptance Test

100

7-Nov 7-Nov

Delivery to Asian Chemical

100

8-Nov

Prepared By :

Plan
Progress

THAI ASIAN POWER SOLUTION CO.,LTD.

Equipment Received

Plan order & Material on process


control panel