Академический Документы
Профессиональный Документы
Культура Документы
Category Amber
Caesar Apparels Limited
Mahanagar Packaging Ltd. and Quality Fashion Ltd
BSCIC Industrial Estate, Block-A, Baizid Bostami Road, Chittagong
(22.386503N, 91.806692E)
8th June 2014
Category RED if
Key actions on
page 4 to 10
are not
immediately
carried out.
Executive Summary
On Sunday 8th June 2014 Mr Sebastian Kaminski and Mr Erick Karla of Arup carried out a visual
structural survey of the Caesar Apparels Ltd. factory at the coordinates given on the cover page
of this report. We inspected all parts of the building.
We met with Abdur Rahim (General Manager), Abu Jahed Monju (Manager HR, Admin &
Compliance) and Shafiqul Islam (Building Owner). The General Manager has been at this factory
for one year. The factory consists of one six storey production building. The site was reported by
the Manager to have no flooding history. The company rents 2 floors (1st and 3rd) of the building.
The ground and the 2nd floor of the building is occupied by Chittagong Mahanagar Packaging Ltd.
and Quality Fashion Ltd. respectively.
The fourth and fifth floors are currently under construction. A large reinforced concrete water
tank is also to be constructed on the East side of the building roof. The company has occupied
their floors since 2013.
We were presented with copies of Permit drawings for the building. The drawings dated
November 2006 were signed by the local authority in March 2007 and indicated a six storey
building. No as-built drawings were provided.
We were also presented with compressive strength testing of concrete cylinders made from
ready-mix concrete in January 2014. These were not considered relevant to this assessment.
All live loads in Northern first floor storage area to be reduced to 1.5kPa, and in area indicated
in following sheets live load to be limited on all floors to 1.5kPa, construction work to stop and
Gazi tanks to be emptied of water on all floors. Tanks to be relocated over internal columns
following detailed calculation and justification. This is pending verification of column capacities
by the Building Engineer.
A Detailed Engineering Assessment should be carried out and this needs to be addressed
immediately.
A
B
C
D
E
F
Actions on 5th
1 2
A
B
C
D
E
F
Actions on 4th
1 2
A
B
C
D
E
F
Loads on 3rd
1 2
A
B
Reduce Live Load to 1.5kPa
C
D
E
F
Actions on 2nd
1 2
A
Reduce Live Load to 1.5kPa
C
D
E
F
Loads on 1st
1 2
A
B
Reduce Live Load to 1kPa
C
D
E
F
10
High column stresses, no loading plan and high uncontrolled live loads
Cracks at head of masonry walls
Cracks to external column
Inconsistencies Between Drawings and As Built Construction
We see no reason to suspend operations in the facility due to these concerns (subject to the
required actions noted at the end of this report).
Further actions with associated priorities and timeframes are given at the end of this report.
Please note that these actions should be completed as soon as practically possible and certainly
within the timeframe noted.
We have reviewed the property from an outline seismic perspective and would consider that the
building along with many others in the Chittagong region to have a significant risk of collapse in a
major Seismic event.
11
Building Extents
12
Building Extents
13
North/Front Elevation
14
Building Extents
West Elevation
South elevation
15
Building Extents
East elevation
Roof
5th Floor
4th Floor
3rd Floor
2nd Floor
1st Floor
Ground Floor
Building: Current Use of Factory Floors
Roof: Plastic water tank and construction work on going.
16
Building Extents
Number of Stories:
Six storey building (GF+5)
Year of construction:
Started construction work in 2006.
Completed 1st,2nd and 3rd floor between 2006 and
2008.
Started construction of 4th and 5th floor in 2014
and is still on-going.
Drawing permission:
Permission for six storey building from BSCIC
authority.
Status of permit:
Permitted up to six stories and construction ongoing as per permission.
Column layout and number of columns doesnt
match with permitted drawing.
Building Extents
17
Measured Grid
1 2
A
B
C
D
E
F
300 x 450
300 x 375
Building
Extents
18
Structural System
19
Structural System:
RC beam and slab construction. Lateral stability is provided
by moment/sway frame action. Additional stability provided
by brick infill walls.
Column sizes (excluding finishes):
Typical internal column: 450X300mm, render 10-20mm
Edge column 1: 375X300mm, render 10-40mm
Edge column 2: 300X250mm, render 10-40mm
Span size:
6.45X4.8m (maximum)
Slab thickness :
1st to 3rd floor: 140mm (average), + 20-30mm finishes
4th to 6th floor: 140mm (average), no finishes present
Beam size (excluding finishes):
Long direction: 250x600 mm deep, render 10-20mm
Short direction: 250x450 mm deep, render 10-20mm
Structural drawing
Floor-to-ceiling height:
Ground floor: 3.2m
Typical floor: 3.0m (average)
Aggregates:
Ground to 3rd floor brick chips all elements.
4th above stone chips in beam and slab, brick in columns.
Structural System
20
Structural System
Structural System
Observations
23
24
Loads on 1st
1 2
A
B
C
D
E
F
25
Heavy loaded
storage area
Brick aggregate in
columns
Heavy storage loads on
1st floor
26
27
Crack along head of faade masonry wall on cantilever leaves wall unrestrained at
head to wind loads out-of-plane
28
29
30
31
12
B
C
7 8
D
E
F
Undocumented Cantilevers
Undocumented Edge Columns
32
Problems Observed
ITEM 1:
ITEM 2:
ITEM 3:
ITEM 4:
33
Priority 1
(Immediate - Now)
Priority 2
(within 6-weeks)
Priority 3
(within 6-months)
34
Reduce all live loads in Northern first floor storage area to 1.5kpa.
In area indicated: empty water out of all Gazi tanks, limit live load on all
floors to 1.5kpa, stop construction work on upper floors provide
temporary restraints to any walls in the temporary condition.
Building Engineer to review design, loads and columns stresses in all
columns.
Verify insitu concrete stresses either by 100mm diameter cores or
existing cylinder strength data for cores from 4 columns.
A Detail Engineering Assessment of Factory to be commenced, see
attached Scope.
Produce and actively manage a loading plan for all floor plates
within the factory giving consideration to floor capacity and
column capacity.
Detail Engineering Assessment to be completed
35
Priority 1
None required
(Immediate - Now)
Priority 2
(within 6-weeks)
Priority 3
(within 6-months)
36
Priority 1
(Immediate - Now)
Priority 2
Repair as necessary
(within 6-weeks)
Priority 3
(within 6-months)
37
Priority 1
None Required
Building Engineer to update the drawings to reflect the asbuilt structure and loading levels at all floor levels,
including as built floor finishes thickness.
None Required.
(Immediate - Now)
Priority 2
(within 6-weeks)
Priority 3
(within 6-months)
38
Except as otherwise noted, drains and other services were not viewed or tested during our inspection and are therefore similarly excluded from this
Report. We have not inspected any parts of the structure which are covered, unexposed or inaccessible and we are therefore unable to report that any
such part of the property is free from defect.
External inspection of the faade walls has generally been carried out from ground level only by visual sighting. No opening up works were carried out
(except as noted) and we rely on the Architects and Engineers drawings provided to us for our views on concealed parts of the structure and in particular
foundations. Strengths of materials and components are untested and we recommend that the factory owners Building Engineer carries out insitu testing
over and above those suggested to satisfy themselves with the material strengths and component details.
Recommendations, where given, are for the purpose of providing indicative advice only, are not exhaustive, relate solely to identifying key and obvious
structural defects as identified in this presentation, and do not take the form of or constitute a specification for works. We take no responsibility for the
works as constructed. This report does not interfere with the factory owners Building Engineers responsibility for the structural performance of this
building, The Building Engineer remains fully responsible for the structural adequacy of the building.
This report does not comment in detail on the future seismic performance of the building and only highlights the fact that the building may experience
significant damage or collapse in a seismic event along with many others in the Dhaka region.
The observations in this report are based on the Engineering Judgement of the lead surveyor/engineer at the time of the survey. We assume in making
these observations that no covering up of faults defects, filling or plastering over cracking or significant repair work has been carried out by the building
owner. Any future alteration or additional work by the building owner will void this report.
39