Вы находитесь на странице: 1из 3

DOCUMENT No.

(Project/ Doc)

CALCULATIONS

QT00159 / A2 / C01

PROJECT TITLE

OFFICE

C628 - DOHA NORTH SEWERAGE, TREATMENT &


ASSOCIATED WORKS

DOHA
SUBJECT

SHEET No.

TSE Pump Station Pipe Diameter Selection


ISSUE

TOTAL
SHEET

AUTHOR

DATE

T WOAKES

28/02/2006

T WOAKES

5/03/2006

N ROBINSON

12/06/2006

M DEANE

14/07/2006

CHECKED BY

DATE

APPROVED
BY

DATE

M CRISP

13/06/2006

D MACRAE

14/06/2006

SUPERSEDES DOC. No.

OF

COMMENTS

DATE

DESIGN BASIS STATEMENT (Inc. sources of info/data, assumptions made, standards, etc.)
OVERVIEW
The following calculations have been prepared to determine the required diameter of the pipework
(a) from the TSE balancing tanks to the common suction manifold,
(b) the suction pipework,
(c) the discharge pipework,
(d) and the common discharge manifold
(a) The worst case scenario for the balance tank outlets is for two adjacent tanks passing flow
into the same end of suction manifold, with the maximum 2030 flow. This will produce the
maximum flow through the twin pipes leading to the suction manifold, and will produce the
maximum flow through the suction manifold itself. It is assumed that this is a "Special
Circumstance" (see ref. 1).
(b)(c) The maximum flow into and out of each pump based on the design flow of 1,172 l/s.
(d) Under normal operation, the discharge manifold will have a maximum flow equal to the
maximum 2030 demand divided by two.
Ref. 1

Flow rates are based on the following (using 1,172 l/s per pump)
3,516 l/s
7,032 l/s
6 pumps running
3 pumps running
4,688 l/s
8,204 l/s
7 pumps running
4 pumps running
The following pipe diameters have been calculated based on a allowable velocities :

Ref. 2

Normal circumstances : 0.5m/s (min) to 2.0m/s (max) under hourly peak conditions
Special circumstances : up to 2.5 m/s
Suction velocity
: 1.8 m/s (max)
Discharge velocity
: 2.5 m/s (max)
CONCLUSIONS
Pipe
Balance Tank outlets
Inlet manifold
Suction pipework
Delivery pipework
Discharge Manifold

Dia (mm) Peak Velocity


*
1400
2.66
2000
2.61
1000
1.49
900
1.84
1600
2.04

* 7 pumps running

Maximum head loss at peak flow


under worst case scenario's between
TSE tanks and pump inlets =
2.216 m

REFERENCES
1. Flow calculations "QT00159 / A1 / C04 - TSE 3 Pumping Capacity"
2. Qatar Sewerage and Drainage Design Manual Project DFC 1050/D9, Volume 4;
Section 2.4, Page 13, (General TSE Mains) - "In normal circumstances ...a range from 0.5m/s to 2.0m/s under hourly
peak conditions may be considered appropriate". "However in special circumstances, velocities up to 2.5 m/s may be
acceptable in the main trunk and distribution pipelines"
Section 2.8.7, Page 38, (Pump Suction & Delivery) - "Suction velocities should not normally exceed 1.8m/s."
"Di h
l iti
h ld t
ll
d25 / "

K:\QT00159 - Doha North STW\D-Calcs\Part A2 - TSE Pump Station\C01(4) -Pipe Velocities.xls

Sheet no

DOCUMENT No. (Project/ Doc)

OF

QT00159 / A2 / C01
SUBJECT

TSE Pump Station Pipe Diameter Selection


CALCULATIONS

SUBJECT

Pipe Diameter >>


Pipe Area >>
Phase
Future
(7pumps)
Max 2030
(6pumps)

Outlet from Balance


Tanks
1200
1400
1600
1.131
1.539
2.011
Pipe Velocities

Flow (l/s) Tanks in Use


8,204
7,032

Max 2010

4,625

Min 2030

701

Min 2010

289

OUTPUT

4
2
4
2
4
2

1.81
3.63
1.55
3.11
1.02
2.04

1.33
2.66
1.14
2.28
0.75
1.50

1.02
2.04
0.87
1.75
0.58
1.15

4
2
4
2

0.15
0.31
0.06
0.13

0.11
0.23
0.05
0.09

0.09
0.17
0.04
0.07

(marginally higher than 2.5 - OK)


(< 2.5 - OK)

Inlet Manifold Upstream of Pumps


1

Pipe Diameter >>


Pipe Area >>
Phase

Flow (l/s)

Future
(7pumps)

8,204

Max 2030
(6pumps)

7,032

Max 2010

4,625

Min 2030

701

Min 2010

289

1800
2.545

2000
3.142

No. of Mains
in Use

2200
3.801

2400
4.524

Delivery Manifold
Downstream of Pumps 2
1400
1.539

1500
1.767

1600
2.011

Pipe Velocities

2
1
2
1
2
1

1.61
3.22
1.38
2.76
0.91
1.82

1.31
2.61
1.12
2.24
0.74
1.47

1.08
2.16
0.92
1.85
0.61
1.22

0.91
1.81
0.78
1.55
0.51
1.02

2.66
2.32
2.04
Not used with 7 pumps
2.28
1.99
1.75
Not used with 6 pumps
1.50
1.31
1.15

2
1
2
1

0.14
0.28
0.06
0.11

0.11
0.22
0.05
0.09

0.09
0.18
0.04
0.08

0.08
0.15
0.03
0.06

0.23

0.20

0.17

0.09

0.08

0.07

Length of main upstream of first pump offtake

Downstream of last pump convergence, assuming both delivery mains in use and all pumps available

(less than 2.5 or


marginally higher

than 2.5 - OK)

Pump Discharge / Suction Pipework


Pipe Diameter >>
Pipe Area >>
Phase

Flow (l/s)

Future
(7pumps)

8,204

Max 2030
(6pumps)

7,032

Min 2030

701

Max 2010

4,625

Min 2010

289

400
0.126

600
0.283

No of Pumps
in Use
7
6
1
4
1

800
0.503

900
0.636

1000
0.785

1200
1.131

Pipe Velocities
9.33

4.15

2.33

1.84

1.49

1.04

9.33

4.15

2.33

1.84

1.49

1.04

5.58

2.48

1.39

1.10

0.89

0.62

9.20

4.09

2.30

1.82

1.47

1.02

2.30

1.02

0.57

0.45

0.37

0.26

< 2.5

< 1.8

K:\QT00159 - Doha North STW\D-Calcs\Part A2 - TSE Pump Station\C01(4) -Pipe Velocities.xls

OK

Sheet no

DOCUMENT No. (Project/ Doc)

OF

QT00159 / A2 / C01
SUBJECT

TSE Pump Station Pipe Diameter Selection


CALCULATIONS

SUBJECT

OUTPUT

Worst case flow - 7 Pump Operation


Losses in Suction Pipework
Only 2 TSE tanks in use
Pump No

- (8 & 9 not operating)

1600mm dia TSE

1600mm dia TSE

M i

TSE Balancing Tank


(Out of Service)

M i

TSE Balancing Tank


(Out of Service)

Pipe / Fitting

Dia
mm

Vel
m/s

Outlet from TSE Balancing Ta


Pipe from TSE Balancing Tan
Valve
Divergence
Branch to bus main
Pipe
Tee
Bus main
Bus Main (past tee)
Bus main
Bus Main (past tee)
Bus main
Bus Main (past tee)
Bus main
Bus Main (past tee)
Bus main
Bus Main (past tee)
Bus main
Bus main
Bus Main (past tee)
Bus main
Bus Main (past tee)
Bus main
Bus Main (past tee)
Bus main
Bus Main to suction pipe
Convergence
Suction pipe
Suction pipe
Suction pipe
Suction pipe
Suction pipe
Suction pipe
Suction pipe

1400
1400
1400
1400
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
900
900
900
900
900
900
900
900

2.66
2.66
2.66
2.66
2.61
1.31
2.61
2.61
2.61
2.61
2.61
2.61
2.61
2.24
2.24
1.87
1.87
1.52
1.52
1.52
1.14
1.14
0.76
0.76
0.38
0.38
1.84
1.84
1.84
1.84
1.84
1.84
1.84
1.84

Losses >

TSE Balancing Tank


(Phase 1)

length
m

ks
loss

28.0

0.092

TSE Balancing Tank


(Phase 1)

kf
value

kf
loss

Description

0.10

0.036

0.12
1.00
1.20

0.043
0.362
0.417

0.35

0.122

0.35

0.122

0.35

0.122

0.35

0.122

0.35

0.089

0.35

0.062

0.12
0.35

0.014
0.041

0.35

0.023

0.35

0.010

1.20
0.80
0.12

0.009
0.138
0.021

0.75

0.130

0.75

0.130

Bellmouth
Pipe
Valve
1400 -2000
2000-2000 Tee
Pipe
Past Tank Tee
Pipe
Past Pump 9 Tee
Pipe
Past Pump 8 Tee
Pipe
Past Pump 7 Tee
Pipe
Past Pump 6 Tee
Pipe
Past Pump 5 Tee
Pipe
In line Valve
Past Pump 4 Tee
Pipe
Past Pump 3 Tee
Pipe
Past Pump 2 Tee
Pipe
Pump 1 Tee
2000-900 Convergence
Valve
Pipe
1 x 90 Bend
Pipe
1 x 90 Bend
Pipe
900/500 Taper

4.7
19.0

0.039

6.1

0.013

6.1

0.013

6.1

0.009

6.1

0.006

6.1

0.004

6.1

0.002

6.1

0.001

6.1

0.000

3.2

0.009

3.2

0.009

2.0

0.005

Pipe Friction
0.202

Maximum head loss at peak flow under worst case scenario


2.216 m
between TSE tanks and pump inlets =

K:\QT00159 - Doha North STW\D-Calcs\Part A2 - TSE Pump Station\C01(4) -Pipe Velocities.xls

Fitting Losses
2.013

Total
2.216

0.1
0.2
0.2

0.3
0.3
0.5
1.0
0.2025