Академический Документы
Профессиональный Документы
Культура Документы
When
signalized intersections.
21/1/2015
GUIDELINES
21/1/2015
DISADVANTAGES
Increase total intersection delay
especially during off peak
periods.
Probable increase in certain
types of accidents (rear end
collisions)
Can interrupt the progressive
flow of traffic on a route
causing increased delay and
stopping.
21/1/2015
DISADVANTAGES
21/1/2015
RED
RED
YELLOW
GREEN
21/1/2015
21/1/2015
21/1/2015
21/1/2015
21/1/2015
PHASE DESIGN
To
11
21/1/2015
2 PHASE CYCLE
N
S
12
S
21/1/2015
3 PHASE CYCLE
N
N
E
W
S
13
N
E
21/1/2015
4 PHASE CYCLE
P/S : There are at least three possible phasing options for 4 phase cycle.
14
21/1/2015
DESIGN PRINCIPLE
Factors in design:
i.
Traffic Capacity
ii.
Saturated Flow, S
iii.
iv.
v.
21/1/2015
TRAFFIC CAPACITY
Capacity
units (p.c.u).
Type of Vehicle
16
Motorcycle
0.33
Passenger car
1.00
Light Vans
2.00
Medium Lorries
1.75
Heavy Lorries
2.25
Buses
2.25
21/1/2015
vehicle volume per hour to passenger car unit per hour, pcu/hr.
ANSWER
Type Of
Vehicle
Total Vehicle /
hour
Equivalent
Factor
PCU/Hr
150
0.33
49.50
BAS
50
2.25
112.50
VAN KECIL
60
1.75
105.00
LORI SEDANG
40
2.00
80.00
300
1.00
300.00
MOTOSIKAL
KERETA &
TEKSI
JUMLAH
17
647.00
21/1/2015
SATURATED FLOW, S
Saturation
following scenario:
Assume that an intersections approach signal were to
stay green for an entire hour, and the traffic was as
dense as could reasonably be expected. The number of
21/1/2015
SATURATED FLOW, S
W (m)
3.0
S
1845
(pcu/hr)
19
3.25
3.5
3.75
4.0
4.25
4.5
4.75
5.0
5.25
1860
1885
1915
1965
2075
2210
2375
2560
2760
21/1/2015
+
=1
=1
where;
I = the inter-green time between the phases, usually 5 sec
a = amber time, usually 3 sec
21/1/2015
=1
where;
yi = highest y value from the approach within that phase i.
(where y =
Q=
S = Saturated flow
Y should not be higher than 0.85. If the value found is higher than 0.85, it is
recommended that the geometrics of the intersection be upgraded to
increase the capacity.
21
21/1/2015
22
21/1/2015
= 0
where;
23
21/1/2015
24
21/1/2015
EXAMPLE 1
A 2 phase traffic light system will be installed on the following
intersection. Both flow volume, Q and Saturated Flow, S are shown in
the figure.
N
Given:
Q = 416 pcu/hr
S = 1970 pcu/hr
= 3 sec
Loss time
= 2 sec
E
W
Q = 1450 pcu/hr
S = 3160 pcu/hr
Q = 780 pcu/hr
S = 3160 pcu/hr
S
25
Q = 350 pcu/hr
S = 1970 pcu/hr
21/1/2015
EXAMPLE 1
Based on the data, determine;
a)
b)
c)
d)
Sketch the light timing diagrams for this 2 phase traffic light.
26
21/1/2015
ANSWER 1
Phase 1
Approach
Q (pcu/hr)
416
350
780
1450
S (pcu/hr)
1970
1970
3160
3160
yi = Q/S
0.21
0.18
0.25
0.46
0.21
0.46
=
=1
Phase 2
=1
= 0.21 + 0.46
= 0.67 0.85 (ok)
27
21/1/2015
ANSWER 1
a)
Given:
=1
=1
+
=1
Loss time, li
= 2 sec
=1
= 6 sec
28
21/1/2015
ANSWER 1
b)
1.5 + 5
=
1
1.5(6)+5
=
10.67
29
21/1/2015
ANSWER 1
c)
determine beforehand.
= 0
PHASE 1 (N-S)
PHASE 2 (E-W)
0.21
1 = 42 6
0.67
0.46
= 42 6
0.67
= 11 sec
= 25 sec
30
21/1/2015
ANSWER 1
c)
Loss time, li
= +
= 2 sec
PHASE 1 (N-S)
PHASE 2 (E-W)
1 = 11 + 2 3
2 = 25 + 2 3
= 10 sec
= 24 sec
31
21/1/2015
ANSWER 1
d)
= 2 sec
9 10
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60
PHASE 1
PHASE 2
32
21/1/2015
9 10
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60
PHASE 1
PHASE 2
33
21/1/2015
REFERENCES
Jabatan Kerja Raya (1987). A Guide To The Design Of Traffic Signal. Arahan Teknik (Jalan)
13/87. Jabatan Kerja Raya, Kuala Lumpur.
Meor Othman Hamzah, et.al.(2001) Rekabentuk Jalanraya Untuk Jurutera. Dewan Bahasa dan
Pustaka, Kuala Lumpur.
34
21/1/2015 12:45 PM
35
21/1/2015 12:45 PM