Вы находитесь на странице: 1из 22

School of Engineering

DESIGN PROJECT 4170- 2016


CHAPTER 8 - PART A
SAFETY ASSESSMENT
Reference : CHE 4170 2016 Unit Guide

Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

Weightings for report excluding the 4 interviews


Week

Activity

Report (report mark is 80% of total mark)


Data gathering task (presentation on Moodle)
Task A
Task A
Task A
Task C
Task B
Task B
Task B
Task C
Task C
Task C
Task C
Task C
Task C

Ch1 Problem Definition


Ch2 Process Technology Evaluation & Selection
Ch3 Process Synthesis & Flowsheet Development
Ch4 Mass and Energy Balances
Ch5 Specification of equipment items
Ch6 Detailed Process and Mechanical Design
Ch7 Piping and Instrumentation Diagram
Ch8 Safety and Environmental Assessment
Ch9 Group HAZOP
Ch10 Plant Layout
Ch11 Economic Evaluation
Ch12 Project Viability
Report presentation mark

Value %

Page Limit

3%

3 slides +
References

4%
6%
14%
10%
5%
15%
7%
7%
4%
4%
10%
5%
6%
Total 100%

8
20
30
20
1p/spec
10p/section
2p/section
5p/section

10
8
12
6
300 (max)

23 Sept 2013
Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

CH8: SAFETY EVALUATION


Details of task:

Part A Safety (Individual)


NOTE : No textbook writing , diagrams, materials available within the general HSE fraternity
is allowed. Non- compliance will be subjected to penalty.

This chapter focuses on the detailed design of one section of plant per team member, which is related
to the team members P&ID, (except for the two team members writing Part B).

Each team member (except for the writers of Part B) should identify specific hazards associated with
this section of plant and explain how these hazards are mitigated.

This should include a discussion on inherent safety ie designing out the hazard where possible, safe
operating procedures for this section and include normal operation, start-up, shutdown and operation
during cleaning.

Emergency Response should also be discussed as a form of mitigation.

An bow tree analysis should be conducted, for at least one hazardous scenario identified for the P&ID.

Requirements for specific procedures should be addressed, but detailed procedures are not required.

3
Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

CH8: SAFETY EVALUATION


Details of task:
Part A Safety (Individual)

Identify the nominated section for each member.

Briefly highlight the various process hazards associated with the plant and make references to key
equipment/sections within your work package which are most susceptible to a hazardous event i.e. fire,
explosion, toxic emissions, thermal. Tabulate under Hazards Identified, Causes, Potential Outcomes
and Mitigation Measures

List down the Standard Operating procedures (SOPS) , i.e Start Up, Normal Operation, Shut Down
procedures for the DD item within your work package. Shut down procedures must cover the need to
drain and decontaminate the plant to facilitate maintenance access. Write a brief process narrative for
the section with step wise procedures (systematic and sequential) in bullet point format. Identify
precautions to be taken for the relevant steps. Tabulate.

Prepare a bow tie diagram for a Hazardous scenario, identified for a major operating unit or system
in your section of the plant. (DD item). This could be Major Fire, Significant Leakage, Catastrophic
Failure or a combination of all. You need to be specific about the design and engineering features
associated with that equipment and NOT generic., i.e references to equipment, item tag nos. etc.

4
Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

SAFETY ASSESSMENT AND RISK MANAGEMENT

You need to construct a bow tie for at least


one hazardous scenario on your P&ID
Hint- Look for scenarios with controls or alarms etc.

Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

HAZARDS
What are the hazards in your plant section ?

Chemical properties and conditions

Explosion/Implosion

Release of toxic chemicals

Runaway reactions.

But also think about.

Cold/hot temperature exposure


Mechanical failure
Corrosion
Mixing of incompatibles
Incorrect material selection
Wrong sequence of activities etc

Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

INHERENT VERSUS ENGINEERED SAFETY


Inherent Safety
Avoids the need for hazardous materials
Uses less hazardous materials or lower inventories
Uses them at lower temperatures or pressures
Dilutes them with inert materials
( Eliminate, Minimise, Substitute, Moderate, Simplify )

Engineered Safety
Uses systems (below) to mitigate the risk associated with the
handling of hazardous materials.
Shutdown systems, pressure relief systems, and fire fighting
systems

Absorption, Dispersion, Containment systems


Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

CONTROL MEASURES

Hierarchy of controls
Examples of controls include:
Procedures
Control systems and alarms
Emergency response
Training
Maintenance
Testing
Sarah Sinclair 2014
Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

BOW-TIE DIAGRAM

Pick one major incident for YOUR P&ID


Bow-Ties
How can it happen? Generate a list of hazards
that could lead to your major incident.
What stops the hazard from causing the major
incident ? These are the preventative control
measures.
What outcomes could there be?
What stops or reduces the outcome? These
are mitigative control measures.
Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

CONTROL MEASURES

Bow-Tie
What does the
bow-tie tell you?
Discussion
Does it make sense?
What could be improved/examined in
more detail later? (Hint: are there paths
that
dont
have
enough
control
measures?)

Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

BOW-TIE DIAGRAM

FAULT TREE
Incidents

Causes

(with control
measures)

Proactive or
Preventative
Controls
Sarah Sinclair 2014

Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

EVENT
Outcomes
TREE (with
control
measures)

Reactive or
mitigative
Controls

School of Engineering

EXAMPLE BOW-TIE DIAGRAM


Hazards
Corrosion

Consequences
Inspection and
Maintenance

External
Fire

Drains
System

Foam
system

Overpressure

Process
Control
System

Pressure
Relief
System

Vehicle
Impact

Vehicle
Controls

Impact
Barriers

Dropped
Object

Crane
operating
procedures

Ignition
Suppression

Vessel
design
standards

Large Scale
Release from
Pressure
Vessel

Gas
detection

Incident

Preventative Controls

Evacuation

Mitigating Controls

Sarah Sinclair 2014


Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

Remote
isolation
valve

Unignited
near miss

Process
area fire

Site
explosion
and fire

BOW TIE GRAPHIC FOR AMMONIA RELEASE

Source : Safe Work Australia : Guide For Major Hazard Facilities: Safety Case: Demonstrating The Adequacy
Of Safety Management And Control Measures

School of Engineering

MITIGATION
Inherent
Procedures
Control Systems and Alarms
Emergency Response
Training
Maintenance

Testing
Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

OPERATING PROCEDURES - START UP


How will your section of the plant be started ?

What are the pre start- up checks to be carried out , i.e proof test of
alarms
Which equipment and systems are turned on first ?
What order of sequence do valves and controls get opened or action
initiated ?

Will alarms need to be on defeat or kept on overide


What other systems have to be checked and performance verified
before plant can be energised ?
What level of maintenance intervention is required for start up ?
Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

OPERATING PROCEDURES-NORMAL OPERATION


How will your section of the plant be normally operated
What are the key parameters to be monitored ; i.e temperatures,
pressures, flowrates, concentrations, amperages, voltages
What critical process control actions have to be monitored ?
What order of sequence do valves and controls get opened or
action initiated ?
What procedures are in place for process deviations
need to be on defeat or over-ridden ?

Will alarms

What maintenance planning systems (MPS) are in place to ensure


operational integrity of the plant ?
Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

OPERATING PROCEDURES - SHUTDOWN


How will your section of the plant be safely shutdown ?
What critical equipment and systems have to be turned off in
sequence ?
What order of sequence do valves and controls get opened/shut or
action initiated/ deactivated ?

What would be the status of alarms ?


What are the venting, purging and absorption requirements ?

What is the status of all utilities ?


What other systems have to be on continued monitoring, i.e inventory,
stock tank levels, container filling, despatches etc. ?
Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

EMERGENCY RESPONSE
A form of mitigation; minimise the consequences. How will your
section of the plant be safely shutdown ?
Emergency Response may include :

Deluge, Absorption, Containment.


Isolation
Evacuation Alarms, muster points, etc
Emergency Responders
to fight fire and attend to
leakages and emissions and rescue victims.
Support from elsewhere, i.e external bodies, local
authorities
Training.
Relationship to environment and the external community.
Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

CHAPTER 8 A - MARKING SCHEME

SECTION

MARKS

Safety Considerations Inherent safety in design and


engineering

10 %

Process hazards, i.e. identification, cause, outcome and control


measures

25 %

Start Up, Normal Operation, Shut Down Procedures.


Readiness for maintenance inspection following shutdown

25 %

Bow Tie Analysis:


Preventive Controls
Mitigative Controls

20%
10 %

Report Clarity

10 %

Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

NOTE TO REPORT CLARITY

A 1.5 spacing, with a font size 12. The minimum margin on the binding
(inside edge) is 3cm.

Reference: Harvard Author (Date) system and list in alphabetical order. Pay
particular attendance to web references and include the date sighted.
Print: Double-sided
Appendices: including any failure scenario and probability tables. It is
suggested that you number the appendices to match each chapter, i.e.
Appendix A8 contains the appendices for Chapter 8

Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

MARKING RUBRICS

1. High Distinction (HD): Demonstrate excellent level of professionalism in


explaining all the salient contents so that readers understand how the process
safety issues,

occupational health and

safety considerations

and risk

management impacts have been addressed.


2. Distinction (D): Demonstrate good level of professionalism in explaining all the

salient contents so that readers have a sound appreciation of the impacts of


safety, occupational health and risk management issues of plant operations
3. Credit (C):Generally described but needs further needs minor improvement to

meet the professional standard


4. Pass (P): Fairly written but lacks the professionalism
5. Fail (F): Not followed the above criteria

Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

School of Engineering

THANK YOU

Monash University Malaysia is jointly owned by Monash University and the Jeffrey Cheah Foundation

Вам также может понравиться