Академический Документы
Профессиональный Документы
Культура Документы
Case Study
On
Structural Steel Beam Failure
EPCMD-2-QM00-CAS-GE-004
01
17.12.2010
00
16.10.2001
Rev
Date
Revised to EPCM
standard
Issued for
information
Revision
DD/DSK
SNS/TSR
AJV
DSK
AJV/APC
SCG
Prepared By
Checked By
Approved
By
Reliance
Contents
1. Purpose 3
2. Scope..3
3. Case Study and Analysis 3
4. Lessons Learned 5
5. Recommendations 6
6. Attachments (Only With The Hard Copy) .6
6.1
6.2
6.3
6.4
6.5
6.6
Page 2 of 7
Reliance
1.
Purpose
The purpose of this case study is to document
2.
Scope
The scope of this case study is limited to the study details adopted at
Jamnagar Refinery; analysis and conclusion arrived for dealing with such
issues. This study is for internal use of Reliance only for facilitating the
decision-making process.
3.
3.1
It was expansion Bay of the main pipe rack. The joining connection
plate between beam and insert plate had slotted holes to provide
expansions. Instead these got anchored because the connection
plate was tack welded with beam and the bolts were missing.
3.1.2
3.1.3 The case under study is combination of both RCC and Structural Steel.
Structural steel is connected to RCC through insert plates or with the help of
anchor fasteners mechanical / chemical. In this case structural steel
EPCMD 2 QM00 CAS GE 004_00.doc
Confidential Reliance. All rights reserved
Page 3 of 7
Reliance
connection plate was supposed to be welded to insert plate embedded in RCC
column and bolted to the beam. This being a expansion joint, slotted holes
were provided in the beam. After approximately one year of commissioning of
plant one beam of section UC254 X 73, collapsed at Crude Unit 311 between
column A-23 and A-24 (Ref. Dwg. No.C63-RD311-501 Rev. 02). There were
several brainstorming sessions among the team members of construction,
FDC, and CES departments for analyzing cause and implementing corrective
measures. This case study gives the details of analysis and conclusion arrived
for dealing with such cases to avoid similar failures in other areas.
Out of four hold fastener bars welded to insert plate on RCC side
found sheared at weld joint, three were rusted and one was fresh,
indicating that separation occurred some time back. (Ref. Dwg. No.
C73-RD300-001 Rev. 0).
10
As per drawing
Comparison matrix
Sl.
No.
1
Requirement
Observation
5mm to 6mm.
Page 4 of 7
Reliance
001 Rev. 0.
3
with no gap.
clearly.
form No FM-CIV-0030.
Engineer.
3.2
Analysis
3.2.1 Being expansion joint one side of the beam was supposed to be
with sliding connection.. Bolts should have been at the center of
the slotted with nuts just snug-fitted to provide provision for
expansion. Instead connection plates were tack welded to beam
and thus making sliding joint as fixed one which caused additional
stresses in the whole assembly.
3.2.2 By this stressing, the weakest link i.e. holds fasteners and insert
plate gave away, leading to collapse of the beam.
3.3
Conclusion
Page 5 of 7
Reliance
3.3.1 Sliding joint required in the expansion bay as per drawing was not
existing and this has exerted extra force on the connection and was
the cause of failure.
3.3.2 Rusted fracture of three hold fasteners of insert plate indicates that
failure started from this weakest link. Because hold fasteners were
just stud welded to insert plate.
3.3.3 Later on because of falling of the beam, connection plate connected
to insert plate through extended additional plate by welding also
failed and subsequently tack welds between connection plate with
beam section also gave away.
4.
Lessons Learnt
4.1
4.2
Bolts in the slotted holes should be at the center of the slot at the
time of construction and have free movement in the direction of
expansion. As recommended by Designer expansion bay connection
shall have nuts snug-fitted and bolt threads peened to prevent
back-off of nut.
4.3
4.4
4.5
4.6
5.
Recommendation
5.1
Expansion joint shall be Hold Point for all concerned e.i. for
Execution
as
well
as
Quality
Control.
This
point
shall
be
Page 6 of 7
Reliance
6. Attachment (only with the hard copy)
6.1
6.2
6.3
6.4
6.5
6.6
Page 7 of 7