Академический Документы
Профессиональный Документы
Культура Документы
(under Republic Act No. 9184 and its Revised Implementing Rules and Regulation)
Decision of Bids and
Awards Committee
(BAC)
Motion for
Reconsideration
BAC
GRANTED
DENIED
Questioned
action/decision
is reversed or
modified.
BAC
Decision/
Resolution
inform bidder of
the decision
inform bidder
of the decision
END
Protest
BAC Secretariat
The Bidder shall file the protest (i.e. the verified position
paper addressed to the appropriate official concerned with
non-refundable protest fee) with the BAC Secretariat of the
appropriate procuring unit concerned [Head Office PrO
BAC Sec.; SPC SPC BAC Sec.; Regions - BAC Sec. of
the concerned region]
Cash Department
(CD)
DG of Sector/Sector-InCharge; or Head of
SPC/Officer-In-Charge of
SPC; or Governor/Officer-InCharge; or Monetary Board
A
1
In case a failed bidder signifies his intention to file a request for reconsideration, the BAC shall keep the bid envelopes of the
said failed bidder unopened and/or duly sealed until such time that the request for reconsideration has been resolved (Sec.
55.1)
In no case shall any protest taken from any decision treated in this Rule shall stay or delay the bidding process. Provided,
however, that the protests must first be resolved before any award is made (Sec. 57).
The non-refundable protest fee shall be in an amount equivalent to no less than one percent (1%) of the Approved Budget for
the Contract (ABC) (Sec. 55.3).
The Head of the Procuring Entity refers to the governing board or its duly authorized official, for the GOCCs, GFIs, and SUCs
(Sec. 5[t]).
Decision/ Resolution
of the Deputy
Governor/Sector-inCharge; or Head of
SPC/OIC of SPC; or
Governor/OIC; or
Monetary Board
DENY PROTEST
GRANT PROTEST
Questioned
action/decision
that is subject of
protest is
reversed/modified
inform bidder of
the decision
END
inform bidder
of the decision
BAC SEC.
COURT ACTION
END