Comments on Schedule

Construction of Grey Structure


(Core &
TIH-The Indus Hospital Phase-1 Ext
Project

Revision
No.
A

Date
Aug, 2016

Page
1

Dear Mr. Ali,


With reference to your Schedule submitted for Construction
of Grey Structure (Core & Shell) please note the comments
as mentioned below for your onward action:
1. Includes activities as mentioned below:
a. Batching Plant set up activity has not been indicated in the schedule.
b. Dewatering Works activity has not been mentioned in the Schedule.
c. Termite proofing activity has not been mentioned in the Schedule.
d. Sub Base soil preparation activity has not
been
mentioned
in
the
Schedule.
e. Backfilling activity has not been mentioned in the Schedule.
f. Tower Crane Installation activity has not been mentioned in the Schedule.
2.

Itemization of Combined Basement Head into

items

as

mentioned

below:

Construction of Grey Structure (Core & Shell) Works:


a. Preliminary & Mobilization Works:
b. Structure Works:
i. Substructure Works:
ii. Super Structure Works:
iii. Finishing Works
iv. Head House,
UGWT, External
Works etc.
i. Substructure Works:
Combined Basement (Hospital & ECOL Building):
1. Basement Hospital Building:
a. 60% of Basement Area (Hospital Building)
(Exclusive of
Blood Centre & Laundry Area)
i. Indicate the Grid highlighting
the
60%
footprint
of
Basement
Area
(Hospital
Building).

Comment
[AS1]:
Milestone
specified in the LOA to
incorporated in the Schedule.

as
be

Comments on Schedule
Construction of Grey Structure
(Core &
TIH-The Indus Hospital Phase-1 Ext
Project

Revision
No.
A

Date
Aug, 2016

Page
2

ii. Further breakdown the 60% of Basement Area


(Hospital Building) into zones for ease of
detailed tracking such as mentioned below
followed by Grid highlighting
the each Zone for each
activity:
1. Excavation Works
a. Zone-1
b. Zone-2
c.
2. Pile Head Breaking
a. Zone-1
b. Zone-2
c.
3. PCC for Pile Caps
a. Zone-1
b. Zone-2
4. Water Proofing Works
a. Zone-1
i. Grid No---------to-----------ii. Grid No---------to----------b. Zone-2
i. Grid No---------to-----------ii. Grid No---------to----------iii. Breakdown of Pours indicating the No. of Pours
in
each
zone
and
highlighting their respective
Grids.
5. Pile Caps R.C.C Works
a. Zone-1
i. Pour 1
i. Shuttering Works
ii. Rebar Fixing
iii. Concrete Pouring
iv. Curing
ii. Pour 2
iii.

Comments on Schedule
Construction of Grey Structure
(Core &
TIH-The Indus Hospital Phase-1 Ext
Project

Revision
No.
A

Date
Aug, 2016

Page
3

b. Zone-2
i. Pour 1
ii. Pour 2
iii. .
6. PCC for SOG
7. Water Proofing Works
a. Zone-1
i. Grid No---------to-----------ii. Grid No---------to----------b. Zone-2
4. SOG R.C.C Works
a. Zone-1
i. Pour 1
i. Shuttering Works
ii. Rebar Fixing
iii. Concrete Pouring
iv. Curing
ii.
Pour 2
iii.
b. Zone-2
i. Pour 1
ii. Pour 2
iii. .
5. RCC Columns
(Shuttering Works, Rebar
Fixing, Concrete
Pouring &Curing)
Zone-1
Columns Grid
No---------to-----------Columns Grid
No---------to----------Zone-2
Columns

Grid

No---------to------------

Columns

Grid

No---------to------------

Comments on Schedule
Construction of Grey Structure
(Core &

Revision
No.

TIH-The Indus Hospital Phase-1 Ext


Project

Date
Aug, 2016

Page
4

The same above to


be adopted for other
items
Shear
/Lift Wall, Stair Case,
Ramps, Water Proofing
Works
for
Retaining
Walls,
Masonry
Works,
Retaining Walls etc.
6. Beams/Slab
a. Zone-1 (Grid Ref :)
i. Pour 1 (Grid Ref :)
i. Shuttering Works
ii. Rebar Fixing
iii. Concrete Pouring
iv. Curing
ii. Pour 2 (Grid Ref :)
iii.
b. Handing Over of 60% Basement Area (Hospital
Building) to second contractor for start of Hospital
Building.
c. 25% of Basement Area (Hospital
Building) (Exclusive of
Blood Centre & Laundry Area)
The same above Work
Breakdown Structure to
be adopted.
d. 15% of Basement Area (Hospital
Building) (Inclusive of
Blood Centre & Laundry Area)
The same above Work
Breakdown Structure to
be adopted.
i. Leftover Piling Works (No. of
Piles to be
mentioned)
1. Survey & Layout

2. Boring Works
3. Steel Cage
Fixing
4. Concreting
Works
5.
Strength
Gaining/Concrete
Maturity
Period of Pile
ii.
Pile Testing
Works

Comment [AS2]: Milestone as specified in the LOA to be incorporated in the Schedule.


Comment [AS3]: Milestone as specified in the LOA to be incorporated in the Schedule.

Comment [AS5]: Milestone as


specified in the LOA to be
incorporated in the Schedule.
Comment [AS4]: Milestone as specified in the LOA to be incorporated in the Schedule.

Comments on Schedule
Construction of Grey Structure
(Core &
TIH-The Indus Hospital Phase-1 Ext
Project

Revision
No.
A

Page

Date
Aug, 2016

1. Static Load Test


a. Test Arrangement &
b. Report Preparation
2. Dynamic Load Test
a. Test Arrangement &
b. Report Preparation
3. Integrity Test
a. Test Arrangement &
b. Report Preparation
4. Sonic Coring Test
a. Test Arrangement &
b. Report Preparation

Testing

Testing

Testing

Testing

The same above


Work
Breakdown
Structure to be
adopted.
Zone-2
2. Basement ECOL Building:
The same above Work Breakdown
Structure to be adopted.
ii. Super Structure Works:
ECOL Building
ECOL Building (Ground Floor for Blood
Centre)
RCC
(Shuttering
Rebar
Concrete
&Curing)

Columns
Works,
Fixing,
Pouring

Zone-1
Ground Floor
Columns Grid
No--------to------------Ground Floor
Columns Grid
No--------to-----------

Ground Floor Colum


No--------to-------------

Comment [AS6]: Milestone as specified in the LOA to be incorporated in the Schedule.


Comment [AS7]: Milestone as
specified in the LOA to be
incorporated in the Schedule.

Comments on Schedule
Construction of Grey Structure
(Core &

Revision
No.

TIH-The Indus Hospital Phase-1 Ext


Project

Date

Aug, 2016

Page
6

Ground Floor Columns Grid No--------to------------The same above to


be adopted for other
items Shear /Lift Wall,
Stair Case, Ramps.
Beams/Slab
b. Zone-1 (Grid Ref :)
iv. Pour 1 (Grid Ref :)
i. Shuttering Works
ii. Rebar Fixing
iii. Concrete Pouring
iv. Curing
v. Pour 2 (Grid Ref :)
vi.
ECOL

Th

Building

(remaining

sa

floors)

me

ECOL

ab

Building

ov

(First Floor)

The

same

Breakdown

above
Structure

Work
to

be

adopted.

same

Breakdown

rk
Bre

ECOL Building (Second Floor)


The

Wo

above
Structure

Work
to

adopted.
ECOL Building (Third Floor)

be

ak
do
wn
Str
uct

ure

to

be

adopted.

Comment [AS8]: Milestone as


specified in the LOA to be
incorporated in the Schedule.

ECOL Building (Fourth Floor)


The

same

Breakdown

above
Structure

Work
to

be

adopted.
ECOL Building (Fifth Floor)
The

same

Breakdown

above
Structure

Work
to

be

adopted.
ECOL Building (Sixth Floor)
The

same

Breakdown

above
Structure

Work
to

be

adopted.
ECOL Building (Seventh Floor)

Comments on Schedule
Construction of Grey Structure
(Core &

Revision
No.

TIH-The Indus Hospital Phase-1 Ext


Project

Date
Aug, 2016

The same above Work Breakdown


Structure to be adopted.
ECOL Building (Eight Floor)
The same above Work Breakdown
Structure to be adopted.
ECOL Building (Ninth Floor)
The same above Work Breakdown
Structure to be adopted.
ECOL Building (Tenth Floor)
The same above Work Breakdown
Structure to be adopted.
ECOL Building (Eleventh Floor)
The same above Work Breakdown
Structure to be adopted.
ECOL Building (Twelfth Floor)
The same above Work Breakdown
Structure to be adopted.
ECOL Building (Roof Floor)
The

same

above

Work

Breakdown

Structure to be adopted. iii. Finishing Works


Masonry Works
Zone-1
Masonry
Works
No---------to-----------Masonry
Works
No---------to----------Zone-2
Masonry

Works

Grid
Grid

Grid

Page
7

No---------to-----------Masonry
Works
No---------to-----------

Grid

Plaster Works
Zone-1
Plaster
Works
Grid
No---------to-----------Plaster
Works
Grid
No---------to-----------

Comments on Schedule
Construction of Grey Structure
(Core &
TIH-The Indus Hospital Phase-1 Ext
Project

Revision
No.
A

Date
Aug, 2016

Page
8

Zone-2
Plaster Works Grid No---------to-----------Plaster Works Grid No---------to----------iv.

our 2
3. .

Head House, UGWT, External


Works etc.
1. Head House
a. Excavation Works
b.
Foundation
(Shuttering,
Steel
Concrete
Pouring, Curing)
c.

Works
Fixing,

2. Underground Water Tank


a. Batching Plant relocation for
Excavation Works
b. Excavation Works
c. PCC for Raft Foundation
d. Water Proofing Works
e. Raft Works Under Ground Water
i. Zone-1
1. Pour 1
i.
Shuttering Works
ii.
Rebar Fixing
iii.
Concrete Pouring
iv. Curing
2. Pour 2
i
.

ii.
Zone2
1. Pour 1
2
.
P

Comment [AS9]: Milestone as


specified in the LOA to be
incorporated in the Schedule.

Comments on Schedule
Construction of Grey Structure
(Core &
TIH-The Indus Hospital Phase-1 Ext
Project
f.

Revision
No.
A

Date
Aug, 2016

Page
9

RCC Columns & Wall Works UGWT (Shuttering Works,


Rebar Fixing, Concrete Pouring &Curing)
Zone-1
Colu
mns
Grid
No-------to---------Colu
mns
Grid
No-------to---------Zone-2
Colu
mns
Grid
No-------to---------Colu
mns
Grid
No-------to----------

g. Water Proofing Works


h. RCC Works Top Slab Underground Water Tank
iii. Zone-1
1. Pour 1
v.
Shuttering Works

vi. Rebar Fixing


vii. Concrete Pouring
viii. Curing
2. Pour 2
i.
iv. Zone-2
1. Pour 1
2. Pour 2
3. .
3. External Works
v.

Overall Completion of the entire


Works
Comment [AS10]: Milestone as specified in the

LOA
to be
incor
porat
ed in
the
Sche
dule.