Project (MSP)
The following tables describe the data exchange mapping between the Project
Management module and Microsoft Project. Although the data mapping between both
products is as close as possible for the purpose of import/export, the Project
Management module was not designed to be another Microsoft Project. Therefore,
some information may be lost when importing and exporting.
DATA MAPPINGS DURING PROJECT MANAGEMENT MODULE EXPORT
Options (from MSP Tools menu)
Project
Project
Management
Management
Module Field
Module Table
Field
View tab
Currency Symbol
curr_symbol
Positive Currency
pos_curr_fmt_type
Format
Number of Decimal
decimal_digit_cnt
Places
Schedule tab
Durations Format
user_data
Unit of Time
Default Duration
Type
def_duration_type
PM Field
Fixed Duration and Units/Time
Fixed Duration and Units
Fixed Units/Time
Fixed Units
Units Format Unit
of Time
Units per Time
format
Calendar tab
Work Hours Per
Day
Work Hours Per
Week
Fiscal Year Begins
Calculation tab
Critical Activities
Project
Management
Module Table
MSP Field
CURRTYPE
CURRTYPE
Symbol
Placement
CURRTYPE
Decimal digits
USERDATA
PROJECT
Duration is entered
in
Default task type
MSP Field
Fixed Duration
Fixed Duration
Fixed Units
Fixed Work
user_data
USERDATA
Work is entered in
user_data
USERDATA
Show Assignment
Units as a
day_hr_cnt
PREFER
week_hr_cnt
PREFER
fy_start_month_num
PROJECT
critical_drtn_hr_cnt
PROJECT
The currency settings exported are based on the currency selected in the User
Preferences, Currency tab in the Project Management module.
Project
Project
Management
Module Field
Project
Management
Module Table
Field
Project Properties
Project Name/WBS
wbs_name
Name
Notebook
wbs_memo
Description
User Defined Field
User Defined
Title
User Defined Field
User Defined
Title
User Defined Field
User Defined
Title
User Defined Field
User Defined
Title
Project Information
Default Project
clndr_id
Calendar
Data Date
data_date
Project Leveling
Priority
n/a
n/a
Resource
Project
Management
Module Field
n/a
Resource Name
Resource ID
Max Units/Time
Price/Unit
Price/Unit*Overtime
Factor
Resource Name (of
parent)
E-Mail Address
Resource Type (labor,
equipment, material)
Project
Management
Module Table
MSP Field
PROJWBS
Title
WBSMEMO
Comments
Field*
UDFVALUE
Manager
Field*
UDFVALUE
Subject
Field*
UDFVALUE
Category
Field*
UDFVALUE
Keywords
PROJECT
Calendar
PROJECT
priority_num
PROJECT
defaults to Project
Start Date
calculated by MSP
n/a
Schedule from
n/a
Current Date**
Project Management
Module Table Field
auto-generated by MSP
rsrc_name
rsrc_short_name
max_qty_per_hr
cost_per_qty
cost_per_qty*ot_factor
Project
Management
Module
Table
n/a
RSRC
RSRC
RSRC
RSRC
RSRC
ID
Name
Initials
Max Units
Standard Rate
Overtime Rate
RSRC
Group
email_addr
rsrc_type
RSRC
RSRC
Email Address
Type (work=
labor or
MSP Field
Unit of Measure
Units & Prices
unit_abbrev
start_date
cost_per_qty
cost_per_qty2
cost_per_qty3
cost_per_qty4
cost_per_qty5
PM Field
Effective date
Price/Unit 1-5
UMEASURE
RSRCRATE
equipment,
material =
material)
Material Labor
Cost Rate
Tables
MSP Field
Effective Date
Standard Rate (A-E)
Resource Notes
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
rsrc_notes
User defined field*
RSRC
UDFVALUE
Notes
Text1 Text30
UDFVALUE
Cost1 Cost10
UDFVALUE
Date1 Date10
UDFVALUE
UDFVALUE
UDFVALUE
UDFVALUE
UDFVALUE
Duration1
Duration10
Number1
Number20
Start1
Start10
Finish1
Finish10
Flag1 Flag20
UDFVALUE
UDFVALUE
Task
Project
Management
Module Field
Project Management
Module Table Field
n/a
Activity Name
auto-generated by MSP
task_name
Project
Management
Module
Table
n/a
TASK
Baseline Cost1
Baseline
Cost10 (MSP
2002 and later)
Baseline Work1
Baseline
Work10 (MSP
2002 and later)
MSP Field
ID
Name
WBS Code***
n/a
Primary Constraint
wbs_short_name
calculated on export
cstr_type
PM Field
Start on
Start on or before
Start on or after
Mandatory Start
Finish on
Finish on or after
Finish on or before
Mandatory Finish
As late as possible
Activities without constraints
Primary Constraint
Date
Activity Leveling
Priority
PM Field
Task Dependent
Resource Dependent
Start Milestone
Finish Milestone
Level of Effort
WBS
Outline Level
Constraint Type
MSP Field
Must start on
Start no later than
Start no earlier than
Must start on
Must finish on
Finish no earlier than
Finish no later than
Must finish on
As late as possible
As soon as possible
cstr_date
TASK
Constraint Date
priority_type
TASK
Priority
PM Field
Top
High
Medium
Low
Lowest
Activity Type
PROJWBS
n/a
TASK
MSP Field
Highest
Higher
Medium
Lower
Lowest
task_type
TASK
Task or
Milestone
MSP Field
Task - Scheduling Ignores Resource Calendars
is checked (MSP 2000 and later)
Task - Scheduling Ignores Resource Calendars
is not checked (MSP 2000 and later)
Milestone - Mark Task as Milestone is checked
Milestone - Mark Task as Milestone is checked
Task - Scheduling Ignores Resource Calendars
is not checked (MSP 2000 and later)
At Completion
Duration
Original Duration
total_drtn_hr_cnt
TASK
Duration
target_drtn_hr_cnt
TASK
Actual Duration
Remaining Duration
act_drtn_hr_cnt
remain_drtn_hr_cnt
TASK
TASK
Baseline
Duration
Actual Duration
Remaining
Duration
Duration Type
duration_type
PM Field
Fixed Duration and Units/Time
Fixed Units/Time
Fixed Units
Fixed Duration and Units
Fixed Units/Time
Predecessors
Start
Finish
Early Start
Early Finish
Late Start
Late Finish
Planned Start
Planned Finish
Actual Start
Actual Finish
At Completion Labor
Units
Budgeted Labor Units
Actual Labor Units
Estimate At
Completion Cost
(actual cost +
estimate to complete
cost)
At Completion
Expense Cost
Budget At
Completion
(budgeted labor,
nonlabor, and
expense cost)
Actual Cost (actual
labor, nonlabor, and
expense cost)
Accrual Type
PM Field
Start of Activity
Uniform over Activity
Finish of Activity
Activity Calendars
Expected Finish (MSP
2000 and later)
TASK
Task Type
MSP Field
Fixed Duration (Effort Driven No)
Fixed Units (Effort Driven Yes)
Fixed Work (Effort Driven No)
Fixed Duration (Effort Driven Yes)
Fixed Units (Effort Driven No)
n/a
start_date
end_date
early_start_date
early_end_date
late_start_date
late_end_date
target_start_date
target_end_date
act_start_date
act_end_date
total_work_qty
TASKPRED
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
Predecessors
Start
Finish
Early Start
Early Finish
Late Start
Late Finish
Baseline Start
Baseline Finish
Actual Start
Actual Finish
Work
target_work_qty
act_work_qty
EAC
TASK
TASK
TASK
Baseline Work
Actual Work
Cost
total_expense_cost
TASK
Fixed Cost
BAC
TASK
Baseline Cost
ACWP
TASK
Actual Cost
cost_load_type
PROJCOST
Fixed Cost
Accrual
MSP Field
Start
Prorated
End
clndr_id (foreign key)
expect_end_date
TASK
TASK
Task Calendar
Deadline
Physical % Complete
(MSP 2002 and later)
phys_complete_pct
TASK
Estimate To
Complete (Remaining
labor, nonlabor, and
expense cost)
Notebook Description
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
ETC
TASK
Physical %
Complete (MSP
2002 and later)
Remaining Cost
task_memo
User defined field*
TASKMEMO
UDFVALUE
Notes
Text1-Text30
UDFVALUE
Cost1Cost10
UDFVALUE
UDFVALUE
Duration1Duration10
Start1-Start10
UDFVALUE
Finish1-Finish10
UDFVALUE
Flag1-Flag20
UDFVALUE
UDFVALUE
Number1Number20
Date1 Date10
UDFVALUE
UDFVALUE
UDFVALUE
Baseline Cost1
Baseline Cost10
(MSP 2002 and
later)
Baseline
Duration1
Baseline
Duration10
(MSP 2002 and
later)
Baseline Work1
Baseline
Work10 (MSP
2002 and later)
Resource Assignments
Project
Project
Management
Management
Module Field
Module Table
Field
Budgeted
target_qty_per_hr
Units/Time
At Completion Units total_qty
Budgeted Units
target_qty
Actual Regular
act_reg_qty
Units
Actual Overtime
act_ot_qty
Units
At Completion Cost
total_cost
Budgeted Cost
target_cost
Actual Cost
act_cost
Lag
lag_drtn_hr_cnt
Resource Curve
curv_id (foreign
key)
PM Field
Linear
Triangular Increase
Triangular Decrease
Double Peak
Early Peak
Offset Triangular
Bell Shaped
Trapezoidal
All other curve types
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
Project
Management
Module Table
MSP Field
TASKRSRC
Units
TASKRSRC
TASKRSRC
TASKRSRC
Work
Planned Work
Actual Work
TASKRSRC
Actual Overtime
Work
Cost
Planned Cost
Actual Cost
Delay
Work Contour
TASKRSRC
TASKRSRC
TASKRSRC
TASKRSRC
TASKRSRC
MSP Field
Flat
Back Loaded
Front Loaded
Double Peak
Early Peak
Late Peak
Bell
Turtle
Contoured
Defined Field
UDFVALUE
Notes
Defined Field
UDFVALUE
Cost1 Cost10
Defined Field
UDFVALUE
Date1 Date10
Defined Field
UDFVALUE
Defined Field
UDFVALUE
Duration1
Duration10
Start1 Start10
Defined Field
UDFVALUE
Finish1 Finish10
Defined Field
UDFVALUE
Text1 Text30
Defined Field
UDFVALUE
Flag1 Flag20
Defined Field
UDFVALUE
Baseline Cost1
Baseline Cost10
(MSP 2002 and
later)
UDFVALUE
UDFVALUE
Baseline Work1
Baseline Work10
(MSP 2002 and
later)
Number1
Number20
*
The User Defined Field is exchanged if a mapping is defined for the field.
**
These fields are calculated by Microsoft Project.
***
When WBS records are exported, the following occurs:
WBS Code
wbs_short_name
PROJWBS
WBS
WBS Name
wbs_name
PROJWBS
Task Name
Notes:
All project-level calendars and any global calendars assigned to activities are
exported to Microsoft Project as Working Time Calendars.
Calendars assigned to resources are exported to Microsoft Project as Resource
Working Time Calendars.
Project
Management
Module Table
Project
Management
Module Field
CURRTYPE
CURRTYPE
Currency Symbol
Positive Currency
Format
Number of Decimal
Places
Decimal digits
decimal_digit_cnt
CURRTYPE
Schedule tab
Default task type
def_duration_type
PROJECT
PM Field
Fixed Duration and Units/Time
Fixed Units/Time
Fixed Units
MSP Field
Fixed Duration
Fixed Units
Fixed Work
Calendar tab
Fiscal year starts in
Calculation tab
Tasks are critical if
slack is less than or
equal to __ days
Default Duration
Type
fy_start_month_num
PROJECT
critical_drtn_hr_cnt
PROJECT
Critical Activities
Project
Management
Module Table
Field
Project
Management
Module Table
Project
Management
Module Field
Project Properties
Title
wbs_name
PROJWBS
Comments
wbs_memo
WBSMEMO
Manager
UDFVALUE
Subject
UDFVALUE
Category
UDFVALUE
Keywords
UDFVALUE
Project Name/WBS
Name
Notebook
Description
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
Project
MSP Field
Project Information
Calendar
clndr_id
PROJECT
PROJECT
data_date
Default Project
Calendar
Data Date
Status date
Priority
priority_num
PROJECT
Finish Date**
plan_end_date
PROJECT
Resource
MSP Field
Name
Resource Initials or
Resource Name
Max Units
Standard Rate
Overtime Rate
rsrc_name
rsrc_short_name
Project
Management
Module
Table
RSRC
RSRC
max_qty_per_hr
cost_per_qty
cost_per_qty*ot_factor
RSRC
RSRC
RSRC
Group
RSRC
Email Address
Type (work= labor,
material = material)
email_addr
rsrc_type
RSRC
RSRC
Material Labor
Cost Rate Tables
unit_abbrev
start_date
cost_per_qty
cost_per_qty2
cost_per_qty3
cost_per_qty4
cost_per_qty5
UMEASURE
RSRCRATE
MSP Field
Effective date
Standard Rate (A-E)
Project Management
Module Table Field
Project Leveling
Priority
Must Finish By
Project
Management
Module Field
Max Units/Time
Price/Unit
Price/Unit*Overtime
Factor
Resource Name (of
parent)
E-Mail Address
Resource Type
(labor, equipment,
material)
Unit of Measure
Units & Prices
Resource Name
Resource ID
PM Field
Effective Date
Price/Unit 1-5
Notes
Text1 Text30
rsrc_notes
User defined field*
RSRC
UDFVALUE
Cost1 Cost10
UDFVALUE
Date1 Date10
UDFVALUE
Duration1
Duration10
Number1
Number20
Start1 Start10
UDFVALUE
UDFVALUE
UDFVALUE
Finish1 Finish10
UDFVALUE
Resource Notes
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
Flag1 Flag20
UDFVALUE
Baseline Cost1
Baseline Cost10 (MSP
2002 and later)
Baseline Work1
Baseline Work10
(MSP 2002 and later)
UDFVALUE
UDFVALUE
Task
MSP Field
ID
Name
WBS
Outline Level
Constraint Type
Project Management
Module Table Field
auto-increment or MSP ID
task_name
wbs_short_name
builds the WBS structure
cstr_type
MSP Field
Must start on
Start no later than
Start no earlier than
Must finish on
Finish no earlier than
Finish no later than
As late as possible
As soon as possible
Project
Management
Module
Table
TASK
TASK
PROJWBS
n/a
TASK
User Defined
Field Title
Project
Management
Module Field
Activity ID
Activity Name
WBS Code
n/a
Primary
Constraint
PM Field
Mandatory Start
Start on or before
Start on or after
Mandatory Finish
Finish on or after
Finish on or before
As late as possible
Activities without constraints
Constraint Date
cstr_date
TASK
Priority
priority_type
TASK
MSP Field
Highest
Higher
Medium
Lower
Lowest
User Defined
Field Title
User Defined
Field Title
PM Field
Top
High
Medium
Low
Lowest
Primary
Constraint Date
Activity Leveling
Priority
Task or Milestone
task_type
TASK
MSP Field
Task - Scheduling Ignores Resource
Calendars is checked (MSP 2000 and
later)
Task - Scheduling Ignores Resource
Calendars is not checked (MSP 2000
and later)
Milestone - Mark Task as Milestone is
checked
Activity Type
PM Field
Task Dependent
Resource Dependent
Start Milestone
total_drtn_hr_cnt
TASK
Baseline Duration
target_drtn_hr_cnt
TASK
Actual Duration
Remaining Duration
act_drtn_hr_cnt
remain_drtn_hr_cnt
TASK
TASK
Task Type
duration_type
TASK
MSP Field
Fixed Duration (Effort Driven No)
Fixed Units (Effort Driven Yes)
Fixed Work (Effort Driven No)
Fixed Duration (Effort Driven Yes)
Fixed Units (Effort Driven No)
At Completion
Duration
Original
Duration
Actual Duration
Remaining
Duration
Duration Type
PM Field
Fixed Duration and Units/Time
Fixed Units/Time
Fixed Units
Fixed Duration and Units
Fixed Units/Time
Predecessors
Start
Finish
Early Start
Early Finish
Late Start
Late Finish
Baseline Start
Baseline Finish
Actual Start
Actual Finish
Work
n/a
start_date
end_date
early_start_date
early_end_date
late_start_date
late_end_date
target_start_date
target_end_date
act_start_date
act_end_date
total_work_qty
TASKPRED
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
Baseline Work
target_work_qty
TASK
Actual Work
act_work_qty
TASK
Predecessors
Start
Finish
Early Start
Early Finish
Late Start
Late Finish
Planned Start
Planned Finish
Actual Start
Actual Finish
At Completion
Labor Units
Budgeted Labor
Units
Actual Labor
Units
Cost
EAC
TASK
Fixed Cost
total_expense_cost
TASK
Baseline Cost
BAC
TASK
Actual Cost
ACWP
TASK
cost_load_type
PROJCOST
MSP Field
Start
Prorated
End
Estimate At
Completion Cost
(actual cost +
estimate to
complete cost)
At Completion
Expense Cost
Budget At
Completion
(budgeted labor,
nonlabor, and
expense cost)
Actual Cost
(actual labor,
nonlabor, and
expense cost)
Accrual Type
PM Field
Start of Activity
Uniform over Activity
Finish of Activity
Task Calendar
TASK
Deadline
expect_end_date
TASK
Physical % Complete
(MSP 2002 and later)
phys_complete_pct
TASK
Remaining Cost
ETC
TASK
Notes
task_memo
TASKMEMO
Text1-Text30
UDFVALUE
Cost1Cost10
UDFVALUE
Duration1Duration10
Start1-Start10
UDFVALUE
UDFVALUE
Finish1-Finish10
UDFVALUE
Activity
Calendars
Expected Finish
(MSP 2000 and
later)
Physical %
Complete (MSP
2002 and later)
Estimate To
Complete
(Remaining
labor, nonlabor,
and expense
cost)
Notebook
Description
User Defined
Field Title
User Defined
Field Title
User Defined
Field Title
User Defined
Field Title
User Defined
Field Title
Flag1-Flag20
UDFVALUE
Number1-Number20
UDFVALUE
Date1 Date10
UDFVALUE
Baseline Cost1
Baseline Cost10 (MSP
2002 and later)
Baseline Duration1
Baseline Duration10
(MSP 2002 and later)
Baseline Work1
Baseline Work10
(MSP 2002 and later)
UDFVALUE
UDFVALUE
User Defined
Field Title
UDFVALUE
User Defined
Field Title
Resource Assignments
MSP Field
Project
Management
Module Table
Field
Units
target_qty_per_hr
Work
Planned Work
Actual Work
Actual Overtime
Work
Cost
Planned Cost
Actual Cost
Delay
Work Contour
MSP Field
Flat
Back Loaded
Front Loaded
Double Peak
Early Peak
Late Peak
Bell
Turtle
Contoured
User Defined
Field Title
User Defined
Field Title
User Defined
Field Title
User Defined
Field Title
Project
Management
Module Table
Project
Management
Module Field
TASKRSRC
Budgeted
Units/Time
At Completion Units
Budgeted Units
Actual Regular Units
Actual Overtime
Units
At Completion Cost
Budgeted Cost
Actual Cost
Lag
Resource Curve
total_qty
target_qty
act_reg_qty
act_ot_qty
TASKRSRC
TASKRSRC
TASKRSRC
TASKRSRC
total_cost
target_cost
act_cost
lag_drtn_hr_cnt
curv_id (foreign
key)
TASKRSRC
TASKRSRC
TASKRSRC
TASKRSRC
TASKRSRC
PM Field
Linear
Triangular Increase
Triangular Decrease
Double Peak
Early Peak
Offset Triangular
Bell Shaped
Trapezoidal
Not imported
Notes
UDFVALUE
Cost1 Cost10
UDFVALUE
Date1 Date10
UDFVALUE
Duration1
Duration10
Start1 Start10
UDFVALUE
UDFVALUE
Finish1 Finish10
UDFVALUE
Text1 Text30
UDFVALUE
Flag1 Flag20
UDFVALUE
Baseline Cost1
Baseline Cost10
(MSP 2002 and
later)
Baseline Work1
Baseline Work10
(MSP 2002 and
later)
Number1
Number20
UDFVALUE
UDFVALUE
UDFVALUE
*
**
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
Defined Field
Defined Field
Defined Field
Defined Field
Defined Field
Defined Field
Defined Field
Defined Field
Defined Field
The User Defined Field is exchanged if a mapping is defined for the field.
These fields are calculated by Microsoft Project.
Notes:
Working Time Calendars in Microsoft Project are imported into the Project
Management module as project-level calendars.
Resource Working Time Calendars in Microsoft Project are imported into the
Project Management module as resource-level calendars.