Data mappings for the Project Management module and Microsoft

Project (MSP)
The following tables describe the data exchange mapping between the Project
Management module and Microsoft Project. Although the data mapping between both
products is as close as possible for the purpose of import/export, the Project
Management module was not designed to be another Microsoft Project. Therefore,
some information may be lost when importing and exporting.
DATA MAPPINGS DURING PROJECT MANAGEMENT MODULE EXPORT
Options (from MSP Tools menu)
Project
Project
Management
Management
Module Field
Module Table
Field
View tab
Currency Symbol
curr_symbol
Positive Currency
pos_curr_fmt_type
Format
Number of Decimal
decimal_digit_cnt
Places
Schedule tab
Durations Format
user_data
Unit of Time
Default Duration
Type

def_duration_type

PM Field
Fixed Duration and Units/Time
Fixed Duration and Units
Fixed Units/Time
Fixed Units
Units Format Unit
of Time
Units per Time
format
Calendar tab
Work Hours Per
Day
Work Hours Per
Week
Fiscal Year Begins
Calculation tab
Critical Activities

Project
Management
Module Table

MSP Field

CURRTYPE
CURRTYPE

Symbol
Placement

CURRTYPE

Decimal digits

USERDATA
PROJECT

Duration is entered
in
Default task type

MSP Field
Fixed Duration
Fixed Duration
Fixed Units
Fixed Work

user_data

USERDATA

Work is entered in

user_data

USERDATA

Show Assignment
Units as a

day_hr_cnt

PREFER

Hours per day

week_hr_cnt

PREFER

Hours per week

fy_start_month_num

PROJECT

Fiscal year starts in

critical_drtn_hr_cnt

PROJECT

Tasks are critical if


slack is less than or
equal to __ days

The currency settings exported are based on the currency selected in the User
Preferences, Currency tab in the Project Management module.

Project
Project
Management
Module Field

Project
Management
Module Table
Field

Project Properties
Project Name/WBS
wbs_name
Name
Notebook
wbs_memo
Description
User Defined Field
User Defined
Title
User Defined Field
User Defined
Title
User Defined Field
User Defined
Title
User Defined Field
User Defined
Title
Project Information
Default Project
clndr_id
Calendar
Data Date
data_date
Project Leveling
Priority
n/a
n/a

Resource
Project
Management
Module Field
n/a
Resource Name
Resource ID
Max Units/Time
Price/Unit
Price/Unit*Overtime
Factor
Resource Name (of
parent)
E-Mail Address
Resource Type (labor,
equipment, material)

Project
Management
Module Table

MSP Field

PROJWBS

Title

WBSMEMO

Comments

Field*

UDFVALUE

Manager

Field*

UDFVALUE

Subject

Field*

UDFVALUE

Category

Field*

UDFVALUE

Keywords

PROJECT

Calendar

PROJECT

priority_num

PROJECT

Start date and


Status date
Priority

defaults to Project
Start Date
calculated by MSP

n/a

Schedule from

n/a

Current Date**

Project Management
Module Table Field
auto-generated by MSP
rsrc_name
rsrc_short_name
max_qty_per_hr
cost_per_qty
cost_per_qty*ot_factor

Project
Management
Module
Table
n/a
RSRC
RSRC
RSRC
RSRC
RSRC

ID
Name
Initials
Max Units
Standard Rate
Overtime Rate

rsrc_name (of parent)

RSRC

Group

email_addr
rsrc_type

RSRC
RSRC

Email Address
Type (work=
labor or

MSP Field

Unit of Measure
Units & Prices

unit_abbrev
start_date
cost_per_qty
cost_per_qty2
cost_per_qty3
cost_per_qty4
cost_per_qty5

PM Field
Effective date
Price/Unit 1-5

UMEASURE
RSRCRATE

equipment,
material =
material)
Material Labor
Cost Rate
Tables

MSP Field
Effective Date
Standard Rate (A-E)

Resource Notes
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title

rsrc_notes
User defined field*

RSRC
UDFVALUE

Notes
Text1 Text30

User defined field*

UDFVALUE

Cost1 Cost10

User defined field*

UDFVALUE

Date1 Date10

User defined field*

UDFVALUE

User defined field*

UDFVALUE

User defined field*

UDFVALUE

User defined field*

UDFVALUE

User defined field*

UDFVALUE

Duration1
Duration10
Number1
Number20
Start1
Start10
Finish1
Finish10
Flag1 Flag20

User defined field*

UDFVALUE

User Defined Field


Title

User defined field*

UDFVALUE

Task
Project
Management
Module Field

Project Management
Module Table Field

n/a
Activity Name

auto-generated by MSP
task_name

Project
Management
Module
Table
n/a
TASK

Baseline Cost1
Baseline
Cost10 (MSP
2002 and later)
Baseline Work1
Baseline
Work10 (MSP
2002 and later)

MSP Field

ID
Name

WBS Code***
n/a
Primary Constraint

wbs_short_name
calculated on export
cstr_type

PM Field
Start on
Start on or before
Start on or after
Mandatory Start
Finish on
Finish on or after
Finish on or before
Mandatory Finish
As late as possible
Activities without constraints
Primary Constraint
Date
Activity Leveling
Priority

PM Field
Task Dependent
Resource Dependent
Start Milestone
Finish Milestone
Level of Effort

WBS
Outline Level
Constraint Type

MSP Field
Must start on
Start no later than
Start no earlier than
Must start on
Must finish on
Finish no earlier than
Finish no later than
Must finish on
As late as possible
As soon as possible

cstr_date

TASK

Constraint Date

priority_type

TASK

Priority

PM Field
Top
High
Medium
Low
Lowest
Activity Type

PROJWBS
n/a
TASK

MSP Field
Highest
Higher
Medium
Lower
Lowest
task_type

TASK

Task or
Milestone

MSP Field
Task - Scheduling Ignores Resource Calendars
is checked (MSP 2000 and later)
Task - Scheduling Ignores Resource Calendars
is not checked (MSP 2000 and later)
Milestone - Mark Task as Milestone is checked
Milestone - Mark Task as Milestone is checked
Task - Scheduling Ignores Resource Calendars
is not checked (MSP 2000 and later)

At Completion
Duration
Original Duration

total_drtn_hr_cnt

TASK

Duration

target_drtn_hr_cnt

TASK

Actual Duration
Remaining Duration

act_drtn_hr_cnt
remain_drtn_hr_cnt

TASK
TASK

Baseline
Duration
Actual Duration
Remaining
Duration

Duration Type

duration_type

PM Field
Fixed Duration and Units/Time
Fixed Units/Time
Fixed Units
Fixed Duration and Units
Fixed Units/Time
Predecessors
Start
Finish
Early Start
Early Finish
Late Start
Late Finish
Planned Start
Planned Finish
Actual Start
Actual Finish
At Completion Labor
Units
Budgeted Labor Units
Actual Labor Units
Estimate At
Completion Cost
(actual cost +
estimate to complete
cost)
At Completion
Expense Cost
Budget At
Completion
(budgeted labor,
nonlabor, and
expense cost)
Actual Cost (actual
labor, nonlabor, and
expense cost)
Accrual Type
PM Field
Start of Activity
Uniform over Activity
Finish of Activity
Activity Calendars
Expected Finish (MSP
2000 and later)

TASK

Task Type

MSP Field
Fixed Duration (Effort Driven No)
Fixed Units (Effort Driven Yes)
Fixed Work (Effort Driven No)
Fixed Duration (Effort Driven Yes)
Fixed Units (Effort Driven No)

n/a
start_date
end_date
early_start_date
early_end_date
late_start_date
late_end_date
target_start_date
target_end_date
act_start_date
act_end_date
total_work_qty

TASKPRED
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK

Predecessors
Start
Finish
Early Start
Early Finish
Late Start
Late Finish
Baseline Start
Baseline Finish
Actual Start
Actual Finish
Work

target_work_qty
act_work_qty
EAC

TASK
TASK
TASK

Baseline Work
Actual Work
Cost

total_expense_cost

TASK

Fixed Cost

BAC

TASK

Baseline Cost

ACWP

TASK

Actual Cost

cost_load_type

PROJCOST

Fixed Cost
Accrual

MSP Field
Start
Prorated
End
clndr_id (foreign key)
expect_end_date

TASK
TASK

Task Calendar
Deadline

Physical % Complete
(MSP 2002 and later)

phys_complete_pct

TASK

Estimate To
Complete (Remaining
labor, nonlabor, and
expense cost)
Notebook Description
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title

ETC

TASK

Physical %
Complete (MSP
2002 and later)
Remaining Cost

task_memo
User defined field*

TASKMEMO
UDFVALUE

Notes
Text1-Text30

User defined field*

UDFVALUE

Cost1Cost10

User defined field*

UDFVALUE

User defined field*

UDFVALUE

Duration1Duration10
Start1-Start10

User defined field*

UDFVALUE

Finish1-Finish10

User defined field*

UDFVALUE

Flag1-Flag20

User defined field*

UDFVALUE

User defined field*

UDFVALUE

Number1Number20
Date1 Date10

User defined field*

UDFVALUE

User Defined Field


Title

User defined field*

UDFVALUE

User Defined Field


Title

User defined field*

UDFVALUE

Baseline Cost1
Baseline Cost10
(MSP 2002 and
later)
Baseline
Duration1
Baseline
Duration10
(MSP 2002 and
later)
Baseline Work1
Baseline
Work10 (MSP
2002 and later)

Resource Assignments
Project
Project
Management
Management
Module Field
Module Table
Field
Budgeted
target_qty_per_hr
Units/Time
At Completion Units total_qty
Budgeted Units
target_qty
Actual Regular
act_reg_qty
Units
Actual Overtime
act_ot_qty
Units
At Completion Cost
total_cost
Budgeted Cost
target_cost
Actual Cost
act_cost
Lag
lag_drtn_hr_cnt
Resource Curve
curv_id (foreign
key)
PM Field
Linear
Triangular Increase
Triangular Decrease
Double Peak
Early Peak
Offset Triangular
Bell Shaped
Trapezoidal
All other curve types
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title

Project
Management
Module Table

MSP Field

TASKRSRC

Units

TASKRSRC
TASKRSRC
TASKRSRC

Work
Planned Work
Actual Work

TASKRSRC

Actual Overtime
Work
Cost
Planned Cost
Actual Cost
Delay
Work Contour

TASKRSRC
TASKRSRC
TASKRSRC
TASKRSRC
TASKRSRC
MSP Field
Flat
Back Loaded
Front Loaded
Double Peak
Early Peak
Late Peak
Bell
Turtle
Contoured

Defined Field

User defined field*

UDFVALUE

Notes

Defined Field

User defined field*

UDFVALUE

Cost1 Cost10

Defined Field

User defined field*

UDFVALUE

Date1 Date10

Defined Field

User defined field*

UDFVALUE

Defined Field

User defined field*

UDFVALUE

Duration1
Duration10
Start1 Start10

Defined Field

User defined field*

UDFVALUE

Finish1 Finish10

Defined Field

User defined field*

UDFVALUE

Text1 Text30

Defined Field

User defined field*

UDFVALUE

Flag1 Flag20

Defined Field

User defined field*

UDFVALUE

Baseline Cost1
Baseline Cost10
(MSP 2002 and
later)

User Defined Field


Title

User defined field*

UDFVALUE

User Defined Field


Title

User defined field*

UDFVALUE

Baseline Work1
Baseline Work10
(MSP 2002 and
later)
Number1
Number20

*
The User Defined Field is exchanged if a mapping is defined for the field.
**
These fields are calculated by Microsoft Project.
***
When WBS records are exported, the following occurs:
WBS Code
wbs_short_name
PROJWBS
WBS
WBS Name
wbs_name
PROJWBS
Task Name
Notes:
All project-level calendars and any global calendars assigned to activities are
exported to Microsoft Project as Working Time Calendars.
Calendars assigned to resources are exported to Microsoft Project as Resource
Working Time Calendars.

DATA MAPPINGS DURING PROJECT MANAGEMENT MODULE IMPORT


Options (from MSP Tools menu)
MSP Field
Project
Management
Module Table
Field
View tab
Symbol
curr_symbol
Placement
pos_curr_fmt_type

Project
Management
Module Table

Project
Management
Module Field

CURRTYPE
CURRTYPE

Currency Symbol
Positive Currency
Format
Number of Decimal
Places

Decimal digits

decimal_digit_cnt

CURRTYPE

Schedule tab
Default task type

def_duration_type

PROJECT

PM Field
Fixed Duration and Units/Time
Fixed Units/Time
Fixed Units

MSP Field
Fixed Duration
Fixed Units
Fixed Work
Calendar tab
Fiscal year starts in
Calculation tab
Tasks are critical if
slack is less than or
equal to __ days

Default Duration
Type

fy_start_month_num

PROJECT

Fiscal Year Begins

critical_drtn_hr_cnt

PROJECT

Critical Activities

Project
Management
Module Table
Field

Project
Management
Module Table

Project
Management
Module Field

Project Properties
Title

wbs_name

PROJWBS

Comments

wbs_memo

WBSMEMO

Manager

User Defined Field*

UDFVALUE

Subject

User Defined Field*

UDFVALUE

Category

User Defined Field*

UDFVALUE

Keywords

User Defined Field*

UDFVALUE

Project Name/WBS
Name
Notebook
Description
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title

Project
MSP Field

Project Information
Calendar
clndr_id

PROJECT

Start date and

PROJECT

data_date

Default Project
Calendar
Data Date

Status date
Priority

priority_num

PROJECT

Finish Date**

plan_end_date

PROJECT

Resource
MSP Field

Name
Resource Initials or
Resource Name
Max Units
Standard Rate
Overtime Rate

rsrc_name
rsrc_short_name

Project
Management
Module
Table
RSRC
RSRC

max_qty_per_hr
cost_per_qty
cost_per_qty*ot_factor

RSRC
RSRC
RSRC

Group

rsrc_name (of parent)

RSRC

Email Address
Type (work= labor,
material = material)

email_addr
rsrc_type

RSRC
RSRC

Material Labor
Cost Rate Tables

unit_abbrev
start_date
cost_per_qty
cost_per_qty2
cost_per_qty3
cost_per_qty4
cost_per_qty5

UMEASURE
RSRCRATE

MSP Field
Effective date
Standard Rate (A-E)

Project Management
Module Table Field

Project Leveling
Priority
Must Finish By

Project
Management
Module Field

Max Units/Time
Price/Unit
Price/Unit*Overtime
Factor
Resource Name (of
parent)
E-Mail Address
Resource Type
(labor, equipment,
material)
Unit of Measure
Units & Prices

Resource Name
Resource ID

PM Field
Effective Date
Price/Unit 1-5

Notes
Text1 Text30

rsrc_notes
User defined field*

RSRC
UDFVALUE

Cost1 Cost10

User defined field*

UDFVALUE

Date1 Date10

User defined field*

UDFVALUE

Duration1
Duration10
Number1
Number20
Start1 Start10

User defined field*

UDFVALUE

User defined field*

UDFVALUE

User defined field*

UDFVALUE

Finish1 Finish10

User defined field*

UDFVALUE

Resource Notes
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title
User Defined Field
Title

Flag1 Flag20

User defined field*

UDFVALUE

Baseline Cost1
Baseline Cost10 (MSP
2002 and later)
Baseline Work1
Baseline Work10
(MSP 2002 and later)

User defined field*

UDFVALUE

User defined field*

UDFVALUE

Task
MSP Field

ID
Name
WBS
Outline Level
Constraint Type

Project Management
Module Table Field
auto-increment or MSP ID
task_name
wbs_short_name
builds the WBS structure
cstr_type

MSP Field
Must start on
Start no later than
Start no earlier than
Must finish on
Finish no earlier than
Finish no later than
As late as possible
As soon as possible

Project
Management
Module
Table
TASK
TASK
PROJWBS
n/a
TASK

User Defined
Field Title

Project
Management
Module Field
Activity ID
Activity Name
WBS Code
n/a
Primary
Constraint

PM Field
Mandatory Start
Start on or before
Start on or after
Mandatory Finish
Finish on or after
Finish on or before
As late as possible
Activities without constraints

Constraint Date

cstr_date

TASK

Priority

priority_type

TASK

MSP Field
Highest
Higher
Medium
Lower
Lowest

User Defined
Field Title
User Defined
Field Title

PM Field
Top
High
Medium
Low
Lowest

Primary
Constraint Date
Activity Leveling
Priority

Task or Milestone

task_type

TASK

MSP Field
Task - Scheduling Ignores Resource
Calendars is checked (MSP 2000 and
later)
Task - Scheduling Ignores Resource
Calendars is not checked (MSP 2000
and later)
Milestone - Mark Task as Milestone is
checked

Activity Type

PM Field
Task Dependent
Resource Dependent
Start Milestone

NOTE: If Mark Task as Milestone is


checked, it will take precedence over
tasks that have durations and ignore the
calendar option setting.
Duration

total_drtn_hr_cnt

TASK

Baseline Duration

target_drtn_hr_cnt

TASK

Actual Duration
Remaining Duration

act_drtn_hr_cnt
remain_drtn_hr_cnt

TASK
TASK

Task Type

duration_type

TASK

MSP Field
Fixed Duration (Effort Driven No)
Fixed Units (Effort Driven Yes)
Fixed Work (Effort Driven No)
Fixed Duration (Effort Driven Yes)
Fixed Units (Effort Driven No)

At Completion
Duration
Original
Duration
Actual Duration
Remaining
Duration
Duration Type

PM Field
Fixed Duration and Units/Time
Fixed Units/Time
Fixed Units
Fixed Duration and Units
Fixed Units/Time

Predecessors
Start
Finish
Early Start
Early Finish
Late Start
Late Finish
Baseline Start
Baseline Finish
Actual Start
Actual Finish
Work

n/a
start_date
end_date
early_start_date
early_end_date
late_start_date
late_end_date
target_start_date
target_end_date
act_start_date
act_end_date
total_work_qty

TASKPRED
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK
TASK

Baseline Work

target_work_qty

TASK

Actual Work

act_work_qty

TASK

Predecessors
Start
Finish
Early Start
Early Finish
Late Start
Late Finish
Planned Start
Planned Finish
Actual Start
Actual Finish
At Completion
Labor Units
Budgeted Labor
Units
Actual Labor
Units

Cost

EAC

TASK

Fixed Cost

total_expense_cost

TASK

Baseline Cost

BAC

TASK

Actual Cost

ACWP

TASK

Fixed Cost Accrual

cost_load_type

PROJCOST

MSP Field
Start
Prorated
End

Estimate At
Completion Cost
(actual cost +
estimate to
complete cost)
At Completion
Expense Cost
Budget At
Completion
(budgeted labor,
nonlabor, and
expense cost)
Actual Cost
(actual labor,
nonlabor, and
expense cost)
Accrual Type

PM Field
Start of Activity
Uniform over Activity
Finish of Activity

Task Calendar

clndr_id (foreign key)

TASK

Deadline

expect_end_date

TASK

Physical % Complete
(MSP 2002 and later)

phys_complete_pct

TASK

Remaining Cost

ETC

TASK

Notes

task_memo

TASKMEMO

Text1-Text30

User defined field*

UDFVALUE

Cost1Cost10

User defined field*

UDFVALUE

Duration1Duration10
Start1-Start10

User defined field*

UDFVALUE

User defined field*

UDFVALUE

Finish1-Finish10

User defined field*

UDFVALUE

Activity
Calendars
Expected Finish
(MSP 2000 and
later)
Physical %
Complete (MSP
2002 and later)
Estimate To
Complete
(Remaining
labor, nonlabor,
and expense
cost)
Notebook
Description
User Defined
Field Title
User Defined
Field Title
User Defined
Field Title
User Defined
Field Title
User Defined
Field Title

Flag1-Flag20

User defined field*

UDFVALUE

Number1-Number20

User defined field*

UDFVALUE

Date1 Date10

User defined field*

UDFVALUE

Baseline Cost1
Baseline Cost10 (MSP
2002 and later)
Baseline Duration1
Baseline Duration10
(MSP 2002 and later)
Baseline Work1
Baseline Work10
(MSP 2002 and later)

User defined field*

UDFVALUE

User defined field*

UDFVALUE

User Defined
Field Title

User defined field*

UDFVALUE

User Defined
Field Title

Resource Assignments
MSP Field
Project
Management
Module Table
Field
Units
target_qty_per_hr
Work
Planned Work
Actual Work
Actual Overtime
Work
Cost
Planned Cost
Actual Cost
Delay
Work Contour
MSP Field
Flat
Back Loaded
Front Loaded
Double Peak
Early Peak
Late Peak
Bell
Turtle
Contoured

User Defined
Field Title
User Defined
Field Title
User Defined
Field Title
User Defined
Field Title

Project
Management
Module Table

Project
Management
Module Field

TASKRSRC

Budgeted
Units/Time
At Completion Units
Budgeted Units
Actual Regular Units
Actual Overtime
Units
At Completion Cost
Budgeted Cost
Actual Cost
Lag
Resource Curve

total_qty
target_qty
act_reg_qty
act_ot_qty

TASKRSRC
TASKRSRC
TASKRSRC
TASKRSRC

total_cost
target_cost
act_cost
lag_drtn_hr_cnt
curv_id (foreign
key)

TASKRSRC
TASKRSRC
TASKRSRC
TASKRSRC
TASKRSRC
PM Field
Linear
Triangular Increase
Triangular Decrease
Double Peak
Early Peak
Offset Triangular
Bell Shaped
Trapezoidal
Not imported

Notes

User defined field*

UDFVALUE

Cost1 Cost10

User defined field*

UDFVALUE

Date1 Date10

User defined field*

UDFVALUE

Duration1
Duration10
Start1 Start10

User defined field*

UDFVALUE

User defined field*

UDFVALUE

Finish1 Finish10

User defined field*

UDFVALUE

Text1 Text30

User defined field*

UDFVALUE

Flag1 Flag20

User defined field*

UDFVALUE

Baseline Cost1
Baseline Cost10
(MSP 2002 and
later)
Baseline Work1
Baseline Work10
(MSP 2002 and
later)
Number1
Number20

User defined field*

UDFVALUE

User defined field*

UDFVALUE

User Defined Field


Title

User defined field*

UDFVALUE

User Defined Field


Title

*
**

User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title
User
Title

Defined Field
Defined Field
Defined Field
Defined Field
Defined Field
Defined Field
Defined Field
Defined Field
Defined Field

The User Defined Field is exchanged if a mapping is defined for the field.
These fields are calculated by Microsoft Project.

Notes:
Working Time Calendars in Microsoft Project are imported into the Project
Management module as project-level calendars.
Resource Working Time Calendars in Microsoft Project are imported into the
Project Management module as resource-level calendars.