Вы находитесь на странице: 1из 24

SUMMARY OF PROVISIONAL CONTRACT PRICE

- Civil Work JOB NO.


: SS2410
JOB NAME : Ma'aden Aluminum Cast House
AREA DIVISION : Civil Work
BIDDER NAME :
ITEM
A.

AMOUNT

DIRECT COST
1

DIRECT MATERIAL

3,017,035.38

DIRECT LABOR

6,692,871.95

CONSTRUCTION EQUIPMENT

1,778,082.46

TOOLS & CONSUMABLES

B.

C.

DESCRIPTION

Currency expressed by USD

INCLUDED

SUB-TOTAL

11,487,989.80

INDIRECT COST

1,855,000.00

INDIRECT LABOR

INCLUDED

TEMPORARY FACILITIES

INCLUDED

GENERAL FIELD EXPENSES

INCLUDED

INSURANCE

HSE

INCLUDED

OVERHEAD & PROFIT

INCLUDED

TAX & DUTIES (V.A.T. EXCLUDED)

INCLUDED

CAR policy by main contractor

SUB-TOTAL

1,855,000.00

CAMP ( ACCOMMODATION,
TRANSPORT & CATERING)

2,337,631.25

SUB-TOTAL

2,337,631.25

GRAND-TOTAL ( A + B + C )

15,680,621.05

T PRICE
APPENDIX-A

Date: 04-06-2011
Currency expressed by USD
REMARKS

COST ESTIMATION SHEET FOR CIVIL WORK


JOB NO.
: SS-2410
JOB NAME : Ma'aden Aluminum Cast House Project
ISSUE / REV :
AREA DIVISION :
Civil Work
SYSTEM
No.

UNIT

QTY'S (SUB)

DESCRIPTION & Spec.

LARGE MIDDLE SMALL

MATERIAL

UNIT PRICE (Currency :


LABOR

Excavation,Normal Soil,Back Hoe

m3

69,171.00

0.74

1A

Extra over rate for excavation in hard rock

m3

2.46

Back-filling and Compaction,Machine,T=15cm


Dry Density=95%, BS1377

m3

29,814.00

1.24

Back-filling and Compaction,Machine,T=30cm


Short Spec.
Imported Soil
Dry Density=95%, BS1377

m3

25,656.00

Disposal,Machine,0-10km ( Distance )

m3

26,206.00

Sand filling and Compaction,Machine,T=15cm (Compacted )

m3

946.00

7.84

0.96

2.17

0.93

0.14

: Elec. Cable beding


6

Crushed Stone Back-filling and Compaction,Machine,T=15cm


(Compacted )

m3

10,087.00

20.67

1.29

Dewatering
Short Spec.
for Pit[16x5.5x15m]/ 4x8 set*month
[VDC PIT]

LOT

6,767.04

6,767.04

Page 3 of 24

SYSTEM
No.

LARGE MIDDLE SMALL

UNIT

QTY'S (SUB)

DESCRIPTION & Spec.

MATERIAL

UNIT PRICE (Currency :


LABOR

Earth Retaining Wall


Short Spec.
[VDC PIT] Sheet piling or Secant piling with Strut, Pit
Size=16m(L)x5.5m(B)x15m(D), L=20m(15.0m,exposed+5.0m,embeded)

m2

42.29

84.59

Proofing,Epoxy Waterproofing
Short Spec.
[VDC PIT] VDC caster pits Epoxy coating, Wise Chem E-212-F paint
system to inner face of VDC caster pits

m2

1,980.00

58.91

6.55

10

Proofing,Bitumen,2 coat
Short Spec.
[VDC PIT] self adhesive membrane bitustick XL, 1.6mm thick below base
slab of the VDC casting Machine

m2

1,768.00

10.47

2.62

11

Pre-Augering
Short Spec.
[VDC PIT] D2000mm, auger, Length=25m, include D2000mm steel pipe
& equipment Mobilization

Nos

33,448.21

5,574.70

11

Add for mobilisation & Demobilisation for (Sheet piling & pre augering )

item

11

Wise Chem E-212-F paint system to inner faces of VDC caster pits

m2

60.27

6.70

12

Anchor Bolt Installation,M24


Short Spec.
[VDC PIT] M56, L=1620mm, PROJ.=400mm
HD bolts-nominal M56 Grade 8.8x 1620mm lg. c/w bolt tubes, anchor
plates, nuts & washers

Nos

36.00

20.67

20.67

13

Re-bar,Deformed Bar Normal Bending,SD30A,D10


Short Spec.
EN10080, fyk=500MPa

ton

61.00

Page 4 of 24

13,393.10

supply by
SECL

474.84

SYSTEM
No.

LARGE MIDDLE SMALL

UNIT

QTY'S (SUB)

DESCRIPTION & Spec.

MATERIAL

UNIT PRICE (Currency :


LABOR

14

Re-bar,Deformed Bar Normal Bending,SD30A,D13


Short Spec.
EN10080, fyk=500MPa

ton

606.00

supply by
SECL

465.85

15

Re-bar,Deformed Bar Normal Bending,SD30A,D16


Short Spec.
EN10080, fyk=500MPa, Epoxy Coating

ton

135.00

supply by
SECL

494.06

16

Re-bar,Deformed Bar Normal Bending,SD30A,D16


Short Spec.
EN10080, fyk=500MPa

ton

1,398.00

supply by
SECL

465.38

17

Re-bar,Deformed Bar Normal Bending,SD30A,D19


Short Spec.
EN10080, fyk=500MPa, Epoxy Coating

ton

135.00

supply by
SECL

494.06

18

Re-bar,Deformed Bar Normal Bending,SD30A,D19


Short Spec.
EN10080, fyk=500MPa

ton

1,212.00

supply by
SECL

465.38

19

Re-bar,Deformed Bar Normal Bending,SD30A,D22


Short Spec.
EN10080, fyk=500MPa, Epoxy Coating

ton

135.00

supply by
SECL

494.06

20

Re-bar,Deformed Bar Normal Bending,SD30A,D22


Short Spec.
EN10080, fyk=500MPa

ton

1,398.00

supply by
SECL

465.38

21

Re-bar,Deformed Bar Normal Bending,SD30A,D25


Short Spec.
EN10080, fyk=500MPa

ton

1,060.00

supply by
SECL

467.56

22

Re-bar,Deformed Bar Normal Bending,SD30A,D29


Short Spec.
EN10080, fyk=500MPa

ton

198.00

supply by
SECL

467.56

23

Re-bar,Deformed Bar Normal Bending,SD30A,D25


Short Spec.
EN10080, fyk=500MPa

ton

68.00

supply by
SECL

467.56

24

Forming Work,Ply Wood,3 Times

m2

75,142.00

Page 5 of 24

17.79

17.79

SYSTEM
No.

LARGE MIDDLE SMALL

UNIT

QTY'S (SUB)

DESCRIPTION & Spec.

MATERIAL

25

Forming Work,Ply Wood,6 Times

m2

740.00

26

Concrete Pouring,Remicon, D=25mm,C-20,Slump 8cm


Short Spec.
fck=20 MPa at 28 days, Cylinder Strength, EN206-1,Concrete Class XS1

m3

2,580.00

supply by
SECL

28.16

27

Concrete,Remicon, D=25mm,C-30,Slump 8cm


Short Spec.
fck=30 MPa at 28 days, Cylinder Strength, EN206-1,Concrete Class XS1

m3

43,168.00

supply by
SECL

28.46

28

Concrete,Remicon, D=25mm,C-30,Slump 8cm


Short Spec.
NON-Calcareous, fck=30 MPa at 28 days, Cylinder Strength, EN2061,Concrete Class XS1

m3

3,700.00

supply by
SECL

28.46

29

Concrete Pouring,Remicon, D=25mm,C-15,Slump 8cm


Short Spec.
fck=12 MPa at 28 days, Cylinder Strength

m3

4,235.00

supply by
SECL

27.74

30

Pipe Installation,Laying Hume Pipe,Socket Type,DIA 300


Short Spec.
electric UPVC PIPE D150mm

5,676.00

31

Pipe Installation,Laying Hume Pipe,Socket Type,DIA 350


Short Spec.
electric UPVC PIPE D200mm

13,140.00

32

Man Hole,Concrete Manhole


Short Spec. 600MMX600MMX800MM
Cast Iron Cover

Nos

36.00

754.74

188.69

33

Proofing,Epoxy Waterproofing

m2

3,870.00

12.40

3.10

Epoxy paint (Waterproofing), 2coats, light gray colored, thickness of 125


microns per coat

Page 6 of 24

14.93

UNIT PRICE (Currency :


LABOR
18.24

SYSTEM
No.

LARGE MIDDLE SMALL

UNIT

QTY'S (SUB)

DESCRIPTION & Spec.

MATERIAL

UNIT PRICE (Currency :


LABOR

34

Proofing,Bitumen,2 coat
Short Spec.
Asphalt mat or bitumet / Protection coatings to concrete surface

m2

45,128.00

3.62

1.55

35

2cts Surface hardener to ground slab


Short Spec.
2 coat

m2

14.10

3.52

36

Construction Joint
Short Spec.
Longitudinal Joint,400mm and over slab thickness, R16x1000mm Mild
Steel dowels @ 30 cm

728.00

24.14

6.03

37

Construction Joint
Short Spec.
Longitudinal Joint,250mm slab thickness, R12x1000mm Mild Steel
dowels @ 30 cm

6,840.00

17.87

4.75

38

Subbase Course,Crushed Stone


( Lower than 8 cm ),T=30CM

m2

900.00

5.78

0.72

39

PE Film,T=0.2 mm
Short Spec.
Visqueen 1000 gauge dpm

m2

49,208.00

0.93

0.10

40

Expansion Joint 20wide x 20mm deep Grass Rope on 20mm


Compressible Filler
Short Spec.
400mm slab thickness

290.00

33.86

10.11

41

Expansion Joint 20wide x 20mm deep Grass Rope on 20mm


Compressible Filler
Short Spec.
250mm slab thickness

1,428.00

30.54

10.18

42

Expansion Joint 20wide x 20mm deep Grass Rope on 20mm


Compressible Filler
Short Spec.
300mm slab thickness

233.00

31.35

10.45

Page 7 of 24

SYSTEM
No.

LARGE MIDDLE SMALL

UNIT

QTY'S (SUB)

DESCRIPTION & Spec.

MATERIAL

UNIT PRICE (Currency :


LABOR

43

Contraction Joint 10wide x 25mm deep saw cut Filled with Polysulphide
sealant + Softwood crack inducer
Short Spec.
400mm and over slab thickness,including R16x400mm Mild Steel dowels
@ 30 cm

507.00

25.71

6.43

44

Contraction Joint 10wide x 25mm deep saw cut Filled with Polysulphide
sealant + Softwood crack inducer
Short Spec.
250mm slab thickness,including R25x650mm Mild Steel dowels @ 30
cm

3,741.00

25.76

7.27

45

Contraction Joint 10wide x 25mm deep saw cut Filled with Polysulphide
sealant + Softwood crack inducer
Short Spec.
250mm slab thickness,including R16x400mm Mild Steel dowels @ 30
cm

75.00

22.28

6.28

46

Steel Item,Misc.Steel Fabrication,Steel


Short Spec.
H-150x150x7x10 with Hot Dip Galvanized_ASTM A36/A36M

ton

0.17

1,584.70

1,188.53

47

Steel Item,Misc.Steel Fabrication,Steel


Short Spec.
H-200x200x8x12 with Hot Dip Galvanized_ASTM A36/A36M

ton

3.00

1,584.70

1,188.53

48

Steel Item,Misc.Steel Fabrication,Steel


Short Spec.
H-350x350x12x19 with Hot Dip Galvanized_ASTM A36/A36M

ton

26.00

1,584.70

1,188.53

49

Steel Item,Misc.Steel Fabrication,Steel


Short Spec.
H-400x400x11x18 with Hot Dip Galvanized_ASTM A36/A36M

ton

10.00

1,584.70

1,188.53

50

Steel Item,Misc.Steel Fabrication,Steel


Short Spec.
With Hot Dip Galvanized_ASTM A36/A36M, embedded angle L-50X50X5
with anchor bar L=500mm

ton

6.00

1,584.70

1,188.53

Page 8 of 24

SYSTEM
No.

LARGE MIDDLE SMALL

UNIT

QTY'S (SUB)

DESCRIPTION & Spec.

MATERIAL

UNIT PRICE (Currency :


LABOR

51

Steel Item,Ladder,Steel,B 600


Short Spec.
Steel Item, Ladder, Steel, B600 with Hot Dip Galvanized_ASTM
A36/A36M

ton

0.65

5,498.22

4,123.67

52

Steel Item,Insert Plate,Steel


Short Spec.
6t, with Hot Dip Galvanized_ASTM A36/A36M

ton

67.00

1,584.70

1,188.53

53

Steel Item,Insert Plate,Steel


Short Spec.
9t, with Hot Dip Galvanized_ASTM A36/A36M

ton

24.00

1,584.70

1,188.53

54

Steel Item,Insert Plate,Steel


Short Spec.
10t, with Hot Dip Galvanized_ASTM A36/A36M

ton

30.00

1,584.70

1,188.53

55

Steel Item,Insert Plate,Steel


Short Spec.
12t, with Hot Dip Galvanized_ASTM A36/A36M

ton

40.00

1,584.70

1,188.53

56

Steel Item,Insert Plate,Steel


Short Spec.
15t, with Hot Dip Galvanized_ASTM A36/A36M

ton

10.00

1,584.70

1,188.53

57

Steel Item,Insert Plate,Steel


Short Spec.
20t, with Hot Dip Galvanized_ASTM A36/A36M

ton

11.00

1,584.70

1,188.53

58

Steel Item,Insert Plate,Steel


Short Spec.
30t, with Hot Dip Galvanized_ASTM A36/A36M

ton

14.00

1,584.70

1,188.53

59

Steel Item,Insert Plate,Steel


Short Spec.
32t, with Hot Dip Galvanized_ASTM A36/A36M

ton

32.00

1,584.70

1,188.53

60

Steel Item,Insert Plate,Steel


Short Spec.
50t, with Hot Dip Galvanized_ASTM A36/A36M

ton

32.00

1,584.70

1,188.53

Page 9 of 24

SYSTEM
No.
61

UNIT

QTY'S (SUB)

DESCRIPTION & Spec.

LARGE MIDDLE SMALL


Grating,I-50

MATERIAL

UNIT PRICE (Currency :


LABOR

m2

582.00

89.57

67.18

1,000.00

66.14

49.61

Bearing bar H=50mm, THK.=7mm


62

Hand Rail,Steel,H=1.2m
Galvanize steel, Top rail=1/4"STEEL PIPE (42.7X3.25) L=1950mm ,
MID BAR FB-50X6,
TOE PLATE FB-100X6

63

Topographic Surveying
Short Spec.
Drafting will be done using MicroStation and 3D modeling using in
ROADS.

m2

64

Mortar Grouting,Non Shrinkage

m3

Type1, Cube compressive strength 50Mpa at 28 days


65

Pipe Sleeve,Sleeve Pipe


Short Spec.
Winding Pipe 150x600mm (Dia.x Depth), C/S Pipe with Hot Dip
Galvanized

EA

179.00

66

Pipe Sleeve,Sleeve Pipe


Short Spec.
Winding Pipe 175x700mm (Dia.x Depth), C/S Pipe with Hot Dip
Galvanized

EA

357.00

67

Pipe Sleeve,Sleeve Pipe


Short Spec.
Winding Pipe 200x900mm (Dia.x Depth), C/S Pipe with Hot Dip
Galvanized

EA

3,177.00

68

Pipe Sleeve,Sleeve Pipe


Short Spec.
Winding Pipe 200x1100mm (Dia.x Depth), C/S Pipe with Hot Dip
Galvanized

EA

311.00

Page 10 of 24

0.02

1,918.83

338.62

SYSTEM
No.

UNIT

QTY'S (SUB)

DESCRIPTION & Spec.

LARGE MIDDLE SMALL

MATERIAL

UNIT PRICE (Currency :


LABOR

69

Pipe Sleeve,Sleeve Pipe


Short Spec.
Winding Pipe 225x1300mm (Dia.x Depth), C/S Pipe with Hot Dip
Galvanized

EA

641.00

70

Pipe Sleeve,Sleeve Pipe


Short Spec.
Winding Pipe 250x1400mm (Dia.x Depth), C/S Pipe with Hot Dip
Galvanized

EA

324.00

71

Pipe Sleeve,Sleeve Pipe


Short Spec.
Winding Pipe 400x1400mm (Dia.x Depth), C/S Pipe with Hot Dip
Galvanized

EA

416.00

72

Pipe Sleeve,Sleeve Pipe


Short Spec.
Winding Pipe 500x1400mm (Dia.x Depth), C/S Pipe with Hot Dip
Galvanized

EA

48.00

73

Pipe Sleeve,Sleeve Pipe


Short Spec.
Winding Pipe 275x1300mm (Dia.x Depth), C/S Pipe with Hot Dip
Galvanized

EA

1,066.00

74

Water Stop,B=300,PVC
Short Spec.
B=250 mm

1,182.00

8.44

3.62

75

Water Stop,B=300,PVC
Short Spec.
B=450 mm

440.00

10.85

4.65

76

Warning Tape

2,229.00

0.62

0.07

W=100mm

Page 11 of 24

SYSTEM
No.

UNIT

QTY'S (SUB)

DESCRIPTION & Spec.

LARGE MIDDLE SMALL

MATERIAL

UNIT PRICE (Currency :


LABOR

77

Isolation Joint 12mm compressible filler + 12 x 12mm Polysulpfide


sealant
Short Spec.
T=12 mm 250mm Slab thickness

3,366.00

6.16

3.31

78

Isolation Joint 12mm compressible filler + 12 x 12mm Polysulpfide


sealant
Short Spec.
T=12 mm 400mm Slab thickness and Above

295.00

8.02

3.44

79

Isolation Joint 12mm compressible filler + 12 x 12mm Polysulpfide


sealant
Short Spec.
T=12 mm 300mm Slab thickness

111.00

7.09

3.04

80

Laying Brick,One Side


Short Spec.
400x200x100

m2

1,599.00

9.81

12.00

Hardboard 3mm thick. To vertical surface


natural fibreboard.

m2

3,017,035.38

6,692,871.95

GRAND TOTAL

Page 12 of 24

TION SHEET FOR CIVIL WORK

UNIT PRICE (Currency : USD)


EQUIP

TOTAL

TOTAL
COST

MANHOUR
Unit MH Total MH

2.98

3.72

9.84

12.30

2.89

4.13

123,131.82

3.10

6.20

159,067.20

2.62

2.76

72,328.56

3.26

12.06

11,408.76

3.88

25.84

260,648.08

54,136.32

67,670.40

Delivery condition
F.O.B
ON
SITE

BIDDER's
COMMENT

257,316.12
Rate only

Page 13 of 24

DELETED

UNIT PRICE (Currency : USD)


EQUIP
719.00

TOTAL

TOTAL
COST

MANHOUR
Unit MH Total MH

Delivery condition
F.O.B
ON
SITE

BIDDER's
COMMENT

845.88

65.46

129,610.80

13.09

23,143.12

16,724.11

55,747.02

DELETED

53,572.40

66,965.50

DELETED

66.97

DELETED

41.34

1,488.24

527.60

32,183.60

52.76

Page 14 of 24

DELETED

supply
by
SECL

UNIT PRICE (Currency : USD)


EQUIP

TOTAL

TOTAL
COST

51.76

517.61

313,671.66

54.90

548.96

74,109.60

51.71

517.09

722,891.82

54.90

548.96

74,109.60

51.71

517.09

626,713.08

54.90

548.96

74,109.60

51.71

517.09

722,891.82

51.95

519.51

550,680.60

51.95

519.51

102,862.98

51.95

519.51

35,326.68

35.57

2,672,800.94

MANHOUR
Unit MH Total MH

Page 15 of 24

Delivery condition
F.O.B
ON
SITE

BIDDER's
COMMENT

UNIT PRICE (Currency : USD)


EQUIP

TOTAL
COST

TOTAL

MANHOUR
Unit MH Total MH

Delivery condition
F.O.B
ON
SITE

BIDDER's
COMMENT

33.17

24,545.80

9.39

37.54

96,853.20

9.49

37.94

1,637,793.92

9.49

37.94

140,378.00

9.25

36.99

156,652.65

EXCLUDED

EXCLUDED

943.43

33,963.48

15.50

59,985.00

Page 16 of 24

SIZE:
600MMX600MM
X800MM

UNIT PRICE (Currency : USD)


EQUIP

0.72

TOTAL

TOTAL
COST

MANHOUR
Unit MH Total MH

5.17

233,311.76

17.62

30.17

21,963.76

22.62

154,720.80

7.23

6,507.00

1.03

50,684.24

43.97

12,751.30

40.72

58,148.16

41.80

9,739.40

Page 17 of 24

Delivery condition
F.O.B
ON
SITE

BIDDER's
COMMENT

DELETED

UNIT PRICE (Currency : USD)


EQUIP

TOTAL

TOTAL
COST

32.14

16,294.98

33.03

123,565.23

28.56

2,142.00

1,188.53

3,961.75

673.50

1,188.53

3,961.75

11,885.25

1,188.53

3,961.75

103,005.50

1,188.53

3,961.75

39,617.50

1,188.53

3,961.75

23,770.50

MANHOUR
Unit MH Total MH

Page 18 of 24

Delivery condition
F.O.B
ON
SITE

BIDDER's
COMMENT

UNIT PRICE (Currency : USD)


EQUIP

TOTAL

TOTAL
COST

4,123.67

13,745.55

8,934.61

1,188.53

3,961.75

265,437.25

1,188.53

3,961.75

95,082.00

1,188.53

3,961.75

118,852.50

1,188.53

3,961.75

158,470.00

1,188.53

3,961.75

39,617.50

1,188.53

3,961.75

43,579.25

1,188.53

3,961.75

55,464.50

1,188.53

3,961.75

126,776.00

1,188.53

3,961.75

126,776.00

MANHOUR
Unit MH Total MH

Page 19 of 24

Delivery condition
F.O.B
ON
SITE

BIDDER's
COMMENT

UNIT PRICE (Currency : USD)


EQUIP

TOTAL
COST

TOTAL

MANHOUR
Unit MH Total MH

Delivery condition
F.O.B
ON
SITE

BIDDER's
COMMENT

67.18

223.93

130,327.26

49.61

165.36

165,360.00

0.01

0.03

DELETED

2,257.45

DELETED

EXCLUDED

EXCLUDED

EXCLUDED

EXCLUDED

Page 20 of 24

UNIT PRICE (Currency : USD)


EQUIP

TOTAL
COST

TOTAL

MANHOUR
Unit MH Total MH

Delivery condition
F.O.B
ON
SITE

BIDDER's
COMMENT

EXCLUDED

EXCLUDED

EXCLUDED

EXCLUDED

EXCLUDED

12.06

14,254.92

15.50

6,820.00

0.69

1,538.01

Page 21 of 24

UNIT PRICE (Currency : USD)


EQUIP

1,778,082.46

TOTAL

TOTAL
COST

9.47

31,876.02

11.45

3,377.75

10.13

1,124.43

21.81

34,874.19

MANHOUR
Unit MH Total MH

11,487,989.80

Page 22 of 24

Delivery condition
F.O.B
ON
SITE

BIDDER's
COMMENT

DEFINITION OF THE COST COMPONENTS

1. DIRECT COST
1-1. Direct Material
This item represents costs for those materials to be used for the permanent purpose and to be
incorporated into the permanent facilities of the plant which are to be provided by the Bidder
pursuant to the provisions of the Contract.
Costs of transportation, procurement service, customs duties, taxes, and levies for such materials
are included in this price component.
1-2. Direct Labor
This item represents costs for the labor directly engaged in the construction of the permanent
facilities of the Plant.
The direct labor consists of foreman and those workers who worked under the control of a foreman
such as craftsman (carpenter, re-bar worker, welder, electrician, scaffolding worker, etc.,
except equipment operators/drivers to be included in the equipment cost as defined hereinbelow),
helpers and common labors.
The direct labor costs include wages, overtime premiums, insurance, taxes, social burdens, board
and lodging, transportation, recruitment, etc., with an exception of the mob/demob costs etc.,
which are to be included in general field expenses as defined in Para. 2-3 hereinbelow.
1-3. Construction Equipment
Construction equipment means the equipment to handle direct materials.
- Depreciation cost for all construction equipment including all maintenance and service including fuel,
lubricant and grease.
- Rental charges for all construction equipment including all maintenance and services.
1-4. Tools and Consumables (shall be included in Item No.1-3)
This item covers all necessary tools including spare parts, temporary materials such as shoring, etc.,
and construction consumables such as fuel, wooden forms for the forming work, welding rods, acetylene,
oxygen, water, electricity, etc., to be used for and/or in connection with the permanent works.

2. INDIRECT COST
2-1. Indirect Labor and Staffs
This item represents costs of those workers who are not directly engaged in the permanent work,
but engaged in the supporting services to the permanent work.
Namely, indirect labor includes warehouse keepers, machine shop workers, material unloading
workers, etc. Including management and supervisory staffs.
2-2. Temporary Facilities
This item represents provision, installation, maintenance and dismantling costs of temporary facilities
such as offices, warehouses, workshops, camp including furniture, utilities, sewerage, temporary roads,
fencing, etc.

2-3. General Field Expenses


This item is covered lawyer's service fees, contributions, car registration expenses, communication
expenses such as telephone, telex, etc., insurance premiums, visa fees, management visits, and
other costs necessary to execute the works which are not covered in other part of the Contract Price.

2-4. Insurance
Expenses for insurance to be incurred in field such as Worker's Compensation lnsurance, Employee
Liabiity Insurance, Business Mobile Liability Insurance, Construction Equipment Liability Insurance,
all risk marine cargo Insurance for the material supplied by bidder, Oversea traveler accident Insurance, etc

2-5. HSE (Health, Safety, Environment)


Cost necessitated by the Site operation in accordance with safety procedure regulation and instruction
of SECL such as but not limited to;
- Personal safety equipment, helmet, working clothes, belt, shoes, gloves and goggles, etc.
- Fire extinguisher for Site, office and warehouse. Others safety equipments
- Safety net & plank for elevated work area such as beneath of piperack or structure
- Safety training, and Environment
- Scaffolding cost to be included in direct construction cost.

2-6. Overhead and Profit


This item represents the Contractor's overhead and profit expected to be recoverable form the execution
of the Works.
2-7. TAX & DUTIES (V.A.T Excluded)
This item covers all the taxes and duties (except to V.A.T.) to be levied on the Contractor
in connection with the Contractor execution of the Works except for the direct materials.

3. Other Terms and Conditions


If anyother special terms and conditions has to be considered except all of upper said, following local
market trends needed.

Вам также может понравиться