Indented list format

1.0 House Construction


1.1 Site preparation
1.1.1 Layout
1.1.2 Grading
1.1.3 Excavation
1.2 Foundation
1.2.1 Erect forms
1.2.2 Pour concrete
1.2.3 Remove forms
1.3 Framing
1.1.1 Floor joists
1.1.1.1 Install first-floor joists
1.1.1.2 Install second-floor joists
1.1.2 Sub-flooring
1.1.2.1 Install first-floor sub-flooring
1.1.2.2 Install second-floor subflooring
1.1.3 Stud Walls
1.1.3.1 Erect first-floor stud walls
1.1.4 Erect second-floor stud walls Frame Roof

1.2 Utilities
1.2.1

Electrical
1.2.1.1 Rough in
1.2.1.2 Building inspection
1.2.1.3 Finish work
1.2.2 Plumbing
1.2.2.1 Rough in
1.2.2.2 Building inspection
1.2.2.3 Finish work
1.3 Walls
1.3.1 Hang sheetrock
1.3.2 Tape and bed
1.4 Roofing
1.4.1 Install sheathing
1.4.2 Lay shingles
1.5 Finish work
1.5.1 Interior
1.5.1.1 Install cabinets
1.5.1.2 Install appliance
1.5.1.3 Install furnace
1.5.1.4 Lay carpet
1.5.1.5 Paint wall and molding
1.5.1.6 Hang wallpaper
1.5.1.7 Lay tie
Resource

Manpower

Material
Machineries

1. Site Engineer
2. Site ForemenC
3. Concreter

1. Masonry
1. Circular saw
2. Drill

4. Carpenter
5. Plumber

8. Machine operator
9. Fitting installer
10. Painter

3. Timber and woods

*timber framing(post and beam)


3. Reciprocating saw

6. Electrician
7. Main/ pipe layer

2. Concrete

4. Flooring (tie)R
5. aw water

4. Extesion cord
5. Nail guns
6. Table saw compund

miter saw
7. Truck
8. Generator
9. Excavator
10. Concrete mixer

6. Plywood
7. Tape
8. Paint
9. Glue-laminated
10. Steel (foundation)