Академический Документы
Профессиональный Документы
Культура Документы
Definition
commitment means to turn-on a given generation unit
Economics
savings are gained by decommitting some of the generation
units when they are not need to meet the current load demand
the engineering problem is committing enough units to meet
current and future load demands while minimizing starting and
operating costs
Example
consider the cost for operating three generation units
Unit 1:
Unit 2:
Unit 3:
150 P1 600
100 P2 400
50 P3 200
400
0
0
255
233
150
0
50
0
50
Ftotal
0
550
500
295
267
Infeasible
Infeasible
Infeasible
0
3760
5389
0
4911
0
3030
2440
2787
2244
F3
0
50
100
150
150
200
250
300
F2
Min
Gen
0
200
400
600
600
800
1000
1200
F1
Max
Gen
Off
On
Off
On
Off
On
Off
On
P3
Unit 3
Off
Off
On
On
Off
Off
On
On
P2
Unit 2
Off
Off
Off
Off
On
On
On
On
P1
Unit 1
1658
0
586
0
586
5418
5389
5497
5471
5617
Example
notes:
the least expensive way to supply the generation is not with all
three units running or with any combination involving two units
the optimal commitment is to only run unit #1, the most
economic unit
by only running the most economic unit, the load can be supplied
by that unit operating closer to its best efficiency
if another unit is committed, both unit #1 and the other unit will be
loaded further from their best efficiency points, resulting in a
higher net cost
1500 MW
1150 MW Peak Load
1000 MW
500 MW
450 MW Min. Load
3 PM
9 PM
3 AM
Time of day
9 AM
3 PM
Example
Total Loading
use a brute force technique to obtain a shut-down rule for the range of
loads from 1200 to 500 MW in steps of 50 MW
when load is above 1000 MW, run all three units
loading between 600 MW and 1000 MW, run units #1 & #2
loading below 600 MW, only run unit #1
Load Unit 1
Unit 2
1200
1500 MW
1150
1100
1050
200 MW
Unit #3
1000
1000 MW
950
400 MW
Unit #2
900
850
500 MW 600 MW
800
750
Unit #1
700
650
3 PM
9 PM
3 AM
9 AM
3 PM 600
550
Time of day
500
on
on
on
on
on
on
on
on
on
on
on
on
on
on
on
on
on
on
on
on
on
on
on
on
on
on
on
off
off
off
Unit 3
on
on
on
on
off
off
off
off
off
off
off
off
off
off
off
Primary constraints
enough units are committed to supply the load economically
Example
consider a power system consisting of two isolated regions
Eastern region
Units 4 & 5
Eastern
Total
900
800
420
800
420
1200
1040
600
310
4400
3090
1900
160
(in)
(MW)
(MW)
Spinning
Reserve
(MW)
Regional
Generation
(MW)
(MW)
1000
Interchange
Western
Regional
Load (MW)
550 MW
maximum
Unit Output
Units 1, 2 & 3
Unit
Capacity
Western region
Unit
100
1740
380
380
1350
3090
160
290
1310
160
(out)
1190
3090
9
Example
verify the allocation of spinning reserves in the system
western region
generation of largest unit: 900 MW
available spinning reserve
local: 760 MW; tie-line capacity: 390 MW; eastern region: 450 MW
total: 1150 MW - load can be supplied
eastern region
generation of largest unit: 1040 MW
available spinning reserve
local: 450 MW; tie-line capacity: 550 MW; western region: 700 MW
total: 1000 MW - load can not be completely supplied
10
11
Start-up costs
the start-up cost can vary from a maximum
cold-start value to a much smaller warm-start value
12
Cstart-up
cooling
t shut down
= H cold 1 e
F fuel + C fixed
banking
input sufficient energy into
the boiler to just maintain
the operating temperature
banking cost function:
Cbank = H bank F fuel tshut down + C fixed
banking
break-even
point
Cfixed
0
0
7 hr
13
the M load levels and operating limits on the N units are such
that any one unit can supply the load demand and any
combination of units can also supply the loads
Commitment by enumeration
a brute force method
14
Priority-List Methods
consist of a simple shut-down rule
15
if the time is less than the minimum shut-down time for the unit,
keep it committed
the sum of the hourly production costs for the next number of
hours with the next unit to be dropped being committed
and the sum of the restart costs for the next unit based on the
minimum cost of cooling the unit or banking the unit
16
Example
construct a priority list for the units in the first example using
the same cost equations
Unit 1:
Unit 2:
Unit 3:
150 P1 600
100 P2 400
50 P3 200
17
Example
the commitment scheme
Combination
1+2+3
1+2
2
Min MW
300
250
100
Max MW
1200
1000
400
notes
18