Академический Документы
Профессиональный Документы
Культура Документы
Time (weeks)
Predecessor
A
B
C
D
E
F
G
H
I
J
K
L
20
24
12
12
40
60
30
20
12
60
10
8
A,B
B
B,C
E,F
E,F
D,G
H
I,J
I,J
Be very careful when printing a document with this assignment to avoid wasting paper. Be
sure to use Print Preview often to resize your output file before printing. Only print the
minimum to answer the questions.
Copy/paste/edit the response template at the end of this document to create your response!
(I) Sketch an AOA network, (II) using the ASAP scheduling rule, determine how long this project will take, and (III)
determine the critical path. (IV) Create an activity list including ES/EF LS/LF schedules and slacks. (V) Determine
the total project baseline budget at complete (BAC) which includes labor, material and other direct costs. (VI)
Assume budgetary charges are uniformly distributed across any individual activity. Create a weekly budget plan
identifying labor, material and total cost per week utilizing the ASAP scheduling rule. (VII) Construct a total labor
weekly requirements bar chart for the project. (VIII) Construct a cumulative total labor weekly requirements
connected marker chart for the project. (IX) Construct a production department weekly requirements bar chart for
the project. (X) Construct a cumulative production department weekly requirements connected marker chart for the
project. (XI) Given that you only ever have available 5 production staff in any given week, create a new schedule
that better balances the production department load. Rescheduling tasks is your only option to better level the
schedule. Should your revised schedule extend the project by time, no penalty would be incurred. Explain your
leveling adjustment action to reduce the scheduled production staffing in any week to a maximum of 5 production
staff. (XII) Show your revised schedule. (XIII) Describe the impact of your leveling decision to schedule and
budget. The following are the estimated worker-weeks staffing needed for each activity.
Activity
Mgmt*
Fin*
Prod*
Manu
Mktg
Material and
other Direct
Charges
40
20
10
40
12,000
48
24
24
72
240,000
48
12
12
12,000
24
12
24
24
80
40
60
320
80
400,000
120
60
120
120
30,000
120
30
30
45
40
20
40
30
5,000
24
12
24
18
6,000
120
120
60
600
120
120
1,200,000
20
10
15
100
40
40,000
16
16
16
32
32
4,000
Name _____________________________________________
I.
II.
Based on the given duration times, estimate how long this project will take.
III.
IV.
V.
Duration
A
B
C
D
E
F
G
H
I
J
K
L
20
24
12
12
40
60
30
20
12
60
10
8
ES
EF
LS
LF
Determine the total project budget estimate at completion (BAC) which includes labor,
material and other direct costs.
Insert responses to VI, VII, VIII, IX, and X here and the following pages.
VI.
Assume budgetary charges are uniformly distributed across any individual activity.
Create a weekly budget plan identifying labor, material and total cost per week.
VII.
Construct a total labor weekly requirements bar chart for the project. (See the handout
for an example!)
Construct a cumulative total labor weekly requirements connected marker chart for the
project. (See the handout for an example!)
IX
Construct a production department weekly requirements bar chart for the project. (See
the handout for an example!)
X.
Insert responses to XI, XII and XIII here and following pages.
XI.
Given that you only ever have available 5 production staff in any given week, create a
new schedule that better balances the production department load. Explain your leveling
adjustment action to reduce the scheduled production staffing in any week to a maximum
of 5 production staff. Overtime assignments are not available. Leveling is your only
option to address any production staffing issue. It is permissible to extend the project
duration if needed to accommodate the 5 production staffing requirement. It is better if
you can keep the first draft critical path time.
XII.
Show and describe how your revised schedule meets the production staffing requirement.
(See the handout for an example!)
XIII.
Describe the impact of your leveling decision to schedule and budget if any.