Вы находитесь на странице: 1из 1

Design and Quality Management Department, Technical Division

Site Visit Report of Sheltech Eyachin Palace


By: Engr. S.M. Morsed Al Mamun (P.E.)
Visit Date: August 26, 2016
---------------------------------------------------------------------------------------------------------------------------------------------1. Conforming Observations:
Slump Table:
Slump Value
Sl
Slump Measuring time
Nos of cylinder is taken
1
2
3

105mm
75mm
90mm
125mm
112mm
98mm
95mm
103mm
108mm
105mm
74mm
95mm
100mm
127mm
110mm

4
5
6
7
8
9
10
11
12
13
14
15

117sec
110sec
112sec
115sec
115sec
113sec
120sec
116sec
115sec
113sec
114sec
116sec
110sec
125sec
120sec

Slab at level-8 casting work is observed, wherea) Casting is done using ready mix concrete. Supplier Borak.
b) Slump values are found within acceptable range.
c) Cylinders are taken for strength test from each track as per standard.
d) Stone chips quality is found satisfactory.
e) Vibrator is properly kept for proper compaction.
f) Shear key provision is found ok.
g) Casting height and level is found ok.

2. Nonconforming Observations:

No nonconforming observations are found.

3. Instructions:

Rebar should be cleaned after final setting of concrete.


Curing should be done properly at full area.
4. Feedback report Previously Observed Nonconforming Observations:
No nonconforming observations were found at last visit.

5. Safety observations:

No safety violations are found.

2nos
2nos
2nos
15nos
2nos
2nos
2nos
2nos
15nos
2nos
2nos
2nos
2nos
12nos
2nos

Вам также может понравиться