INTERNAL MODIFICATION & BOUNDARY WALL WORKS

PROGRAMME OF WORKS AS PER THE PRIORITY


FOR VILLA 18.02, AL BARARI, DUBAI
Activity ID

Activity Name

Duration

Start

Finish

y 2016

February 2016

March 2016

April 2016

May 2016

June 2016

18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20

SBM0081-2 Internal Modification & Boundary Wall for Villa 18.02


SBM0081-2.9 Milestone
SBM0081-2

105

13-Feb-16

13-Jun-16

105

13-Feb-16

13-Jun-16

13-Feb-16

A1120

Notice to proceed (After DM Appr oval)

A2070

Completion date

SBM0081-2.1 Drawings & Materials


SBM0081-2

54

13-Feb-16

14-Apr-16

42

13-Feb-16

31-Mar-16

SBM0081-2.1.1 Shop drawings


SBM0081-2.

13-Jun-16

A1140

Preparation & Appr oval of dr awi ngs for New Gym & Bedr room 5 @ the r ear area of 1st Floor

14

13-Feb-16

28-Feb-16

A1290

Preparation & Appr oval of dr awi ngs for New Maids Room @ the fron t ar ea of 1s t Floor

29-Feb-16

07-Mar-16

A1400

Preparation & Appr oval of dr awi ngs for Mod ify Master Ba th room @ the Gr ound flo or area

08-Mar-16

15-Mar-16

A1420

Preparation & Appr oval of dr awi ngs for New Stor e & Stor age @ the R ooftop are a

14

16-Mar-16

31-Mar-16

54

13-Feb-16

14-Apr-16

A2040

Prepare, & Appr ove of Mater ials

14

13-Feb-16

28-Feb-16

A2050

Procurement of Materials

40

29-Feb-16

14-Apr-16

97

13-Feb-16

04-Jun-16

97

13-Feb-16

04-Jun-16

SBM0081-2.1.2 Materials
SBM0081-2.

SBM0081-2.11 Construction
SBM0081-2
SBM0081-2.11.2 First Floor & Porch @ Ground Floor (1st Priority)
SBM0081-2.

13-Feb-16

18-Feb-16

A2080

Removal & reinstallation of gypsum board

13-Feb-16

16-Feb-16

A2090

Touch up & painting

17-Feb-16

18-Feb-16

21

13-Feb-16

07-Mar-16

SBM0081-2.11.2.1 Repairing of Ceiling @ Porch Area, Ground Floor


SBM0081-2

SBM0081-2.11.2.4 Construction Works for Shifting the Door from Passage to Bedroom 2 (FF-20)
SBM0081-2
A2010

Protection of A reas

13-Feb-16

15-Feb-16

A1390

Removal of existing door wall

16-Feb-16

18-Feb-16

A1410

Block Works & Plastering Works

20-Feb-16

24-Feb-16

A1430

1st MEP works

25-Feb-16

27-Feb-16

A1440

Painting

25-Feb-16

29-Feb-16

A1450

Ceiling

25-Feb-16

01-Mar-16

A1460

Installation of doors, threshold & tiles

02-Mar-16

05-Mar-16

A1470

Final fix for MEP

02-Mar-16

06-Mar-16

A1480

Disposal of Debris

07-Mar-16

07-Mar-16

59

29-Feb-16

07-May-16

A1590

Removal of existing tiles,doorrs, window & wall

10

29-Feb-16

10-Mar-16

A1600

Column & Beam Works

12-Mar-16

20-Mar-16

SBM0081-2.11.2.6 Construction Works for Converting Terrace to Bedroom 5 (FF-21)


SBM0081-2

Project Start : 13-Feb-16

Remaining Work
Milestone

Project Finish : 13-Jun-16

Summary

Internal Modification Boundary Wall for Vil


18.02

1 of 4

Data Date : 13-Feb-16


Duration: 105 Working Days

Date
07-Feb-16

Revision
REV.02

Checked
Marvin

Approved
Jim

INTERNAL MODIFICATION & BOUNDARY WALL WORKS


PROGRAMME OF WORKS AS PER THE PRIORITY
FOR VILLA 18.02, AL BARARI, DUBAI
Activity ID

Activity Name

Duration

Start

Finish

y 2016

February 2016

March 2016

April 2016

May 2016

June 2016

18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20
A1610

Block Works & Plastering Works

12

21-Mar-16

03-Apr-16

A1620

Roofing

15

24-Mar-16

10-Apr-16

A1630

1st MEP works

04-Apr-16

09-Apr-16

A1640

Painting

10

04-Apr-16

14-Apr-16

A1650

Ceiling

12

11-Apr-16

24-Apr-16

A1660

Installation of Sanitary Fittings, doors, window & tiles

10

25-Apr-16

05-May-16

A1670

Final fix for MEP

25-Apr-16

30-Apr-16

A1680

Disposal of Debris

07-May-16

07-May-16

62

12-Mar-16

22-May-16

A1490

Removal of existing tiles,doors, window & wall

10

12-Mar-16

22-Mar-16

A2110

Precast cutting approval

A1500

Column & Beam Works

23-Mar-16

02-Apr-16

A2100

Precast Cutting of wall

18

23-Mar-16

12-Apr-16

A1510

Block Works & Plastering Works

12

03-Apr-16

16-Apr-16

A1520

Roofing

16

06-Apr-16

24-Apr-16

A1530

1st MEP works

17-Apr-16

21-Apr-16

A1540

Painting

10

17-Apr-16

27-Apr-16

A1550

Ceiling

13

25-Apr-16

09-May-16

A1560

Installation of doors, window & tiles

10

10-May-16

21-May-16

A1570

Final fix for MEP

10-May-16

15-May-16

A1580

Disposal of Debris

22-May-16

22-May-16

SBM0081-2.11.2.5 Construction Works for Converting Terrace to Gym (FF-31)


SBM0081-2

22-Mar-16

63

23-Mar-16

04-Jun-16

A1280

Removal of existing tiles,doorrs, window & wall

10

23-Mar-16

03-Apr-16

A1300

Column & Beam Works

10

04-Apr-16

14-Apr-16

A1310

Block Works & Plastering Works

12

16-Apr-16

28-Apr-16

A1320

Roofing

16

19-Apr-16

07-May-16

A1330

1st MEP works

30-Apr-16

04-May-16

A1340

Painting

30-Apr-16

08-May-16

A1350

Ceiling

15

08-May-16

24-May-16

A1370

Final fix for MEP

25-May-16

02-Jun-16

A1360

Installation of Sanitary Fittings, doors, window & tiles

25-May-16

04-Jun-16

A1380

Disposal of Debris

04-Jun-16

04-Jun-16

SBM0081-2.11.2.3 Construction Works for Converting Terrace to 2 Maids Room with Bathrooms
SBM0081-2

Project Start : 13-Feb-16

Remaining Work
Milestone

Project Finish : 13-Jun-16

Summary

Internal Modification Boundary Wall for Vil


18.02

2 of 4

Data Date : 13-Feb-16


Duration: 105 Working Days

Date
07-Feb-16

Revision
REV.02

Checked
Marvin

Approved
Jim

INTERNAL MODIFICATION & BOUNDARY WALL WORKS


PROGRAMME OF WORKS AS PER THE PRIORITY
FOR VILLA 18.02, AL BARARI, DUBAI
Activity ID

Activity Name

Duration

Start

Finish

y 2016

February 2016

March 2016

April 2016

May 2016

June 2016

18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20

SBM0081-2.11.1 Ground Floor (2nd Priority)


SBM0081-2.
SBM0081-2.11.1.2 Construction Works for Converting bedroom 2 to Dressing 2 & Extention of Ma
SBM0081-2

81

16-Feb-16

19-May-16

81

16-Feb-16

19-May-16

A2020

Protection of areas

16-Feb-16

21-Feb-16

A1160

Removal of existing tiles, sanitary fittings doorrs, window & wall

10

22-Feb-16

03-Mar-16

A1200

Foundation & Grade slab & Beam

16-Mar-16

23-Mar-16

A2000

Precast Cutting of wall

20

23-Mar-16

14-Apr-16

A1190

Column & Beam Works

24-Mar-16

02-Apr-16

A1220

Roofing

15

06-Apr-16

23-Apr-16

A1180

Block Works & Plastering Works

09-Apr-16

14-Apr-16

A1170

1st MEP works

16-Apr-16

20-Apr-16

A1210

Painting

10

16-Apr-16

26-Apr-16

A1230

Ceiling

12

24-Apr-16

07-May-16

A1240

Installation of Sanitary Fittings, doors, window & tiles

10

08-May-16

18-May-16

A1250

Final fix for MEP

08-May-16

12-May-16

A1260

Disposal of Debris

19-May-16

19-May-16

76

05-Mar-16

31-May-16

76

05-Mar-16

31-May-16

SBM0081-2.11.3 Rooftop Floor (3rd Priority)


SBM0081-2.
SBM0081-2.11.3.7 Construction Works for Converting Terrace (RF-19) and Bath (RF-02) to Store (
SBM0081-2
A1690

Removal of existing tiles,doorrs, window, planter box & wall

10

05-Mar-16

15-Mar-16

A1700

Column & Beam Works

12

02-Apr-16

14-Apr-16

A1710

Block Works & Plastering Works

12

16-Apr-16

28-Apr-16

A1720

Roofing

15

19-Apr-16

05-May-16

A1730

1st MEP works

30-Apr-16

04-May-16

A1740

Painting

10

30-Apr-16

10-May-16

A1750

Ceiling

12

07-May-16

19-May-16

A1760

Installation of Sanitary Fittings, doors, window, sk ylight & tiles

10

21-May-16

31-May-16

A1770

Final fix for MEP

21-May-16

28-May-16

52

28-Feb-16

28-Apr-16

SBM0081-2.11.4 Boundary Wall Solid to Grill Type


SBM0081-2.
A1990

Approval from DM (Seperate approval to the Modification)

28-Feb-16

A1890

Earthworks

29-Feb-16

08-Mar-16

A1980

Demolition of existing boundary wall

12

29-Feb-16

13-Mar-16

A1970

Removal of existing trees & irrigation

09-Mar-16

14-Mar-16

A1900

RCC beam & footings

12

14-Mar-16

27-Mar-16

Project Start : 13-Feb-16

Remaining Work
Milestone

Project Finish : 13-Jun-16

Summary

Internal Modification Boundary Wall for Vil


18.02

3 of 4

Data Date : 13-Feb-16


Duration: 105 Working Days

Date
07-Feb-16

Revision
REV.02

Checked
Marvin

Approved
Jim

INTERNAL MODIFICATION & BOUNDARY WALL WORKS


PROGRAMME OF WORKS AS PER THE PRIORITY
FOR VILLA 18.02, AL BARARI, DUBAI
Activity ID

Activity Name

Duration

Start

Finish

y 2016

February 2016

March 2016

April 2016

May 2016

June 2016

18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20
A1910

Blockworks

28-Mar-16

05-Apr-16

A1930

1st fix MEP works for column lights

31-Mar-16

02-Apr-16

A1920

Plastering

06-Apr-16

14-Apr-16

A1940

Painting

16-Apr-16

24-Apr-16

A1960

MEP final fix works column lights

25-Apr-16

26-Apr-16

A1950

Disposal of debris

27-Apr-16

28-Apr-16

05-Jun-16

13-Jun-16

SBM0081-2.10 Handing Over


SBM0081-2
A1270

Snagging

05-Jun-16

08-Jun-16

A2060

Testing & Commissioning

09-Jun-16

12-Jun-16

A2030

Deep cleaning & handing over

13-Jun-16

13-Jun-16

Project Start : 13-Feb-16

Remaining Work
Milestone

Project Finish : 13-Jun-16

Summary

Internal Modification Boundary Wall for Vil


18.02

4 of 4

Data Date : 13-Feb-16


Duration: 105 Working Days

Date
07-Feb-16

Revision
REV.02

Checked
Marvin

Approved
Jim