Case Attached: Transmission Line Part 1 and II
1.
a. The transmission division in India faces numerous difficulties, the
majority of which need to do with getting licenses, arrive obtaining,
administrative and ecological clearances and so forth. The Right of Way
law for transmission lines decides the rules for the concerned powers
including pay for land securing. Each temporary worker offering for the
procedure must be reviewed deliberately, as there have been numerous
occurrences where unpracticed contractual workers made and won
unviable ventures, just to understand their habit mostly prompting to slow
down undertakings. Henceforth one of the chief errands required to be
done is checking for the budgetary practicality. On the off chance that the
venture is practical and the temporary worker chooses to proceed with the
venture, then go for endorsements. Cost benefit analysis must be led
considering money streams anticipated from wheeling charges, premium,
deterioration, leap rate and cost of capital. Venture can proceed just if it's
observed to be fiscally or deliberately achievable. Scope has to be defined
and after that the boundary cross points should be defined. Feasibility
study of not just financials, but also other feasibility studies have to be
done such as Technical feasibility, social feasibility, resource feasibility,
project feasibilities.
Approvals required are:
Specialized Approval: Central Electricity Authority conducts framework
investigations of the power framework in the nation and checks the
consonance of the venture with the nationwide framework.
Ministry of Power: Point of view planning, Policy formation, preparing of
tasks for investments decision, observing of the execution of force
undertakings, preparing and labor advancement and the organization and
authorization of enactment with respect to power era, transmission and
distribution.
Business Approval: This must be given by State Electricity Regulatory
Commission which will later affirm the Annual Revenue Requirement
presented by Transco and incorporate these charges in the sum paid by
the buyers. Recognizable proof of partners and bearers of development
cost is finished. A portion of the recipients of the line are specific/general
clients and generators. Now and then line is required to transmit force of
generator or to supply energy to a specific modern buyer. At that point
Duration
(months)
1
4-6
4-5
6-8
2-3
Funds arrangement
Gazette Notification
Total time estimated is around 22-30 months
2 i)
4-6
1
Stakehold
er
CEA
Responsible
for power
system in the
country
Regulation
adherence
and
completion
Direct
Medium
Power
&
Influe
nce
High
Transco
Need to
construct and
maintain the
line profitably
and reliably
Could be a
major
shareholder
of the
Transco apart
from public
welfare
Sets the
tariffs
Financial
Viability of
the Project
Direct
High
High
Adherence
to
standards
and
completion
Direct
High
High
Adherence
to
standards
and
completion
Environme
nt Viability
Direct
High
High
Direct
Medium
High
Low tariff,
power
supply
Indirect/
direct
High
Mediu
m
Compensat
ion in
return
Direct
High
Mediu
m
State
Governme
nt
State
Electricity
Regulatory
Commissio
n
NGOs
Consumers
People
affected by
project
Reason
Protests on
different
issues
Will better
power supply
or load
enhancement
By getting
displaced
and may
protest
Interest
Involvem
ent
Impact
Stakeholder
Displaced People
NGOs
Political parties
3.
Reason
for
Resistance
Agitate
for
not
receiving compensation
and
may
demand
higher compensation
May oppose by showing
environmental concerns
Mitiggation Plan
a.
i. The scope of the project are defined below:
Design and Fabrication of Towers as per various Standards and in line with
TransCos design
The Tower designs to be done and all the BOQ to be freeze well before in
time
The foundation designs to be done for different soil classifications like
normal, submerged, hard rock, fissured rock etc and provisional quantities
to be indicated in the BOQ.
Construction of S/C line through a combination of Overhead line on double
circuit towers and UG cable
Fitting of Insulators & hardware fittings and Construction of foundation
(Civil Work) for the towers, 4 poles structure and DPs.
Erection of Isolator with earth switches and Erection of DP structure and 4Pole structure with required Insulators and H/W fittings, Lightning
Arrestors. And other such elements
Procurement, construction and other works must be done in compliance with
ADB guidelines
Specific and clearly mentioned quality standards and various checks and
balances
Environmental and Safety metrics
Form of contract
Safety practices
Non-Disclosure agreement
Notice inviting tenders
Qualification Criteria
Evaluation and loading criteria
Job scope and technical specifications
Cost of Tender
Tender undertaking
Design documents
Scope of Tender
General purchase conditions and bank guarantee forms
3.
b. To guarantee nature of material and to legally tie contractual workers in order to make
them execute the work in the way we need the accompanying measures might be utilized:
c. Guaranteeing that the materials provided and the work done meets the required quality
measures is a vital and basic movement. For this reason, the accompanying focuses can be
considered.
d.
To guarantee that exclusive presumed contractual workers having required abilities and
capacities can make through to you, all offers should be checked for significant
responsiveness to all the specialized necessities of the offering records. On the off chance that
a temporary worker does not consent he/she might be rejected.
Few examples of potential explanations behind dismissal could be: failure to quote for a
major item in the package failure to meet major technical requirements and failure to submit
any required documents or reports, and not having the ability to bid for the entire scope of the
project and when it is clearly mentioned in the bidding documents that this is a necessary condition for
bidding.
To guarantee an intensive check of the substantive responsiveness of all offers, a Table of Substantive
Responsiveness to Commercial Terms and Table of Substantive Responsiveness to Technical Requirements
ought to be readied. The tables ought to rundown every significant condition for Commercial Terms and
every real condition for Technical Requirements which the bidders must meet for their offers to be
considered considerably responsive. The responsiveness of every offer got ought to then be checked
against this rundown and its conformance or fractional conformance, or nonconformance to everything
ought to be entered in the tables. Offers which neglect to fit in with any of the real conditions ought to
regularly be considered non-responsive and ought to be rejected.
Staff the vendor has to facilitate the completion of the Project. This
activity is to realize the vendors ability to engage Manpower.
4
a.
engineering and transmission line building. This can also be used for
reconstruction and maintenance work. It was developed to improve
visualization of repetitive tasks when planning and managing major
projects through time distance diagrams. The key benefits of using TILOS
is the flow of visual data in terms of time and place on one plan which
network diagrams and CPM schedules fail to provide.
Metro projects are carried out in linear and phased manner which makes
TILOS an important tool for project execution. They are highly complicated
projects requiring a large number of tasks to be completed linearly and
need resources such as labor and construction equipment to move along
locations and time as well. TILOS visually represent the progress and plan
on distance and time axis and also shows various elements such as
regulatory requirements, constraints, risks, other such elements for each
of the tasks. TILOS can be used in tendering phase, construction phase,
execution, disruptions, and claim management.
TILOS provides full CPM analysis, and complete support of sub projects,
full control over quantities, work rates, resources, and costs connected to
location information, and the perfect monitoring of progress along the
production line. TILOS also reduces the effort of reentering data multiple
times. The features of TILOs such as graphical layout possibilities,
powerful display of the project using various symbols, scales, grids,
diagrams, and displays and comprehensive project management
capabilities from planning to monitoring to closing the project make TILOS,
deliver a work program in minutes to analyze the feasibility of performing
the project within the planned time frame using its rich library of
comprehensive templates and standard processes
Metro Projects usually start with bidding from the governments and the
requirements of the project change with location and time. TILOS helps in
incorporating these changes on real time basis and gives out the new plan
in minutes. This can be used in claim management effectively by showing
dynamically the change in the budget because of the changes. . It also
provides maximum flexibility in organizing your plan, integrating data,
eliminating planning mistakes, controlling costs and resources, and
realistic planning using construction specifications. . It makes well use of
the standard planning processes and calculates efficiently the effect of
track description complexities on processes. This results in detailed
execution plan containing the task, the resource load, the costs and also
the train movements required for logistical support.
TILOS cannot just be used as an integrated, stand alone, fully featured
planning system but also in combination with other software such as MS
Project, Primavera, and ASTA Power project. This makes it a powerful
project management tool. All these make, TILOS, powerful, easy to use,
popular, and a brilliant tool for planning and managing linear projects such
as Metro Projects.